Yocto Project 2.2 Release Test Plan
Reversion history
Version | Modifier | Comments |
---|---|---|
1.0 | Jose Perez Carranza | First draft |
Introduction
This article is the overall test plan for version 2.2 of the Yocto Project, for all the generic information this document will be pointing QA Master Test Plan
Objectives
QA_Master_Test_Plan#Objectives_and_Tasks
Test Strategy
Is followed the general strategy defined on QA_Master_Test_Plan#Testing_Strategy and below is showed specific information applicable only for 2.2 Release
Owned features
As QA team we are also in charge for some features to implemetn/verify
To Verify 2.2_qa_owned_features_to_verify
To Implement 2.2_qa_owned_features
Bugs to Verify
Bugs that need verification form QA team 2.2_qa_owned_bugs
Test Items
COMPONENT | TEMPLATES |
---|---|
ADT | |
BSP | |
CROPS | |
Eclipse-Plugin | |
Meta-Yocto | |
Toaster | |
eSDK | |
OE-CORE / Bitbake | |
Distro Testing | |
Runtime (Compliance) | |
Build Apliance | |
pTest |
Features to be tested
Features to be tested are defined in component Test Plan QA_Master_Test_Plan#Component
Pass / Fail Criteria
This criteria is defined in Yocto_Project_v2.2_Status#Yocto_Project_v2.2_Release_Criteria
Exit Criteria
TBD
Test Deliverables
- Live Status 2.2_QA_Status
- Execution Status #Execution History
- Mail sent to the mailing list
Test Environment
There are different environments and tools for every type of testing refer to QA_Master_Test_Plan#Test_Areas for more detailed information.
Schedule
The planed schedule for 2.2 can be found at Yocto_2.2_Schedule
Live Schedule
MILESTONE | START | FINISHED |
---|---|---|
M1 | ||
M2 | ||
M3 | ||
M4 |
Execution History
MILESTONE | REPORT |
---|---|
M1 | |
M2 | |
M3 | |
M4 |