Yocto Project Weekly Status March 7th, 2023

Current Dev Position: YP 4.2 M4
Next Deadline: 3rd April 2023 YP 4.2 M4 Build

Next Team Meetings:

Key Status/Updates:

  • YP 4.2 M3 is in QA
  • YP 4.0.8 is ready to be built
  • YP 3.1.23 was released
  • We are now in feature freeze for 4.2. There are some patches which we will take in M4 such as the CVE fetching changes.
  • We now have the ability to track regression changes between releases using resulttool for example with a command like “yocto_testresults_query.py regression-report 4.2_M1 4.2_M2”. This did already spot one regression in quilt ptest which we’ve tracked down and fixed.
  • A regression report was included with M3 using the above tool automatically: https://autobuilder.yocto.io/pub/releases/yocto-4.2_M3.rc1/testresults/testresult-regressions-report.txt - some tweaks are needed but it is good progress.
  • CVE levels in master look much better, thanks to everyone who helped. We are in the process of including kernel CVEs in these reports for master going forward.
  • We have a growing number of bugs in bugzilla, any help with them is appreciated.
  • We have had patches from a few new submitters, this is very very much appreciated and great to see. Some bugs have moved forward as a result of this. All of these changes combine together to make the project what it is!

Ways to contribute:

YP 4.2 Milestone Dates:

  • YP 4.2 M3 is released
  • YP 4.2 M4 build date 2023/04/03
  • YP 4.2 M4 Release date 2023/04/28

Upcoming dot releases:

  • YP 4.0.8 is built and in QA
  • YP 4.1.3 is built
  • YP 4.1.3 Release date 2023/03/17
  • YP 3.1.24 build date 2023/03/20
  • YP 3.1.24 Release date 2023/03/31
  • YP 4.0.9 build date 2023/04/10
  • YP 4.0.9 Release date 2023/04/21
  • YP 4.1.4 build date 2023/05/01
  • YP 4.1.4 Release date 2023/05/13
  • YP 3.1.25 build date 2023/05/08
  • YP 3.1.25 Release date 2023/05/19
  • YP 4.0.10 build date 2023/05/15
  • YP 4.0.10 Release date 2023/05/26

Tracking Metrics: