== Yocto Project Status 19 May 2026 ==
== Yocto Project Status 26 May 2026 ==
Current Dev Position: YP 6.1 M1<br/>
Current Dev Position: YP 6.1 M1<br/>
Next Deadline: YP 6.1 M1: w/c 2026-06-08<br/>
Next Deadline: YP 6.1 M1: w/c 2026-06-08<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting - Thursday 21st May 7:30am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Bug Triage meeting - Thursday 28th May 7:30am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Weekly Project Engineering Sync - Tuesday 19th May 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Weekly Project Engineering Sync - Tuesday 26th May 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Yocto Project Patch Review - Thursday 21st May 10am GMT and Monday 25th May 9am PDT (https://zoom.us/j/97762397148?pwd=1xk0iC9hp9SjEonaTaONwTb6iWry4Eb.1)
*Yocto Project Patch Review - Thursday 28th May 10am GMT and Monday 1st June 9am PDT (https://zoom.us/j/97762397148?pwd=1xk0iC9hp9SjEonaTaONwTb6iWry4Eb.1)


'''Project data dashboard: https://dashboard.yoctoproject.org/'''<br/>
'''Project data dashboard: https://dashboard.yoctoproject.org/'''<br/>


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*YP 6.0 was released, thanks everyone who contributed!
*YP 5.0.18 is out of QA and under review.
*YP 5.0.18 is in QA.
*YP 6.0.1 is in QA
*We’re working through the backlog of patches, the bandwidth for changes needing in depth review/feedback continues to be a challenge.
*We’re working through the backlog of patches, the bandwidth for changes needing in depth review/feedback continues to be a challenge.
*Intermittent build failures continue to be problematic:
*Intermittent build failures continue to be problematic and unchanged from last week:
**several qemu ‘hang’ type issues
**several qemu ‘hang’ type issues
**sometimes yocto-check-layer is showing checksum mismatch issues
**sometimes yocto-check-layer is showing checksum mismatch issues
Line 20: Line 20:
**groff build race issues
**groff build race issues
**intermittent ptest failures in many recipes
**intermittent ptest failures in many recipes
*Master (blacksail) is open for new development
*Is anyone using 32 bit SDKs, if so let us know. Qemu dropped support for 32 bit hosts and we are considering discontinuing 32 bit SDKs.
*We are likely to merge the gcc 16 upgrade soon
*We would like to know what people are planning to work on for Yocto Project 6.1 and beyond. We have a roadmap document in Google Docs: https://docs.google.com/document/d/12xgAzSjDj5zVlo4eQIbiv1s3QMjtBTCvBFY3_T7OPto
*We would like to know what people are planning to work on for Yocto Project 6.1 and beyond. We have a roadmap document in Google Docs: https://docs.google.com/document/d/12xgAzSjDj5zVlo4eQIbiv1s3QMjtBTCvBFY3_T7OPto
*We are updating the project’s security team and welcome nominations and/or feedback: https://lists.openembedded.org/g/openembedded-architecture/topic/119388716
*We are updating the project’s security team and welcome nominations and/or feedback: https://lists.openembedded.org/g/openembedded-architecture/topic/119388716
*Monday 25th May is a public holiday in the UK and USA so there will be no patch review call.


'''Ways to contribute:'''<br/>
'''Ways to contribute:'''<br/>
Line 35: Line 35:


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2673 (last week 2688) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2660 (last week 2673) (https://wiki.yoctoproject.org/charts/combo.html)
*OE-Core/Poky Patch Metrics
*OE-Core/Poky Patch Metrics
**Total patches found: 1083 (last week 1087)
**Total patches found: 1083 (last week 1083)
**Patches in the Pending State: 148 (14%) [last week 146 (13%)]
**Patches in the Pending State: 148 (14%) [last week 148 (13%)]
**https://valkyrie.yocto.io/pub/non-release/patchmetrics/
**https://valkyrie.yocto.io/pub/non-release/patchmetrics/


'''Upcoming dot releases:'''<br/>
'''Upcoming dot releases:'''<br/>
*YP 5.3.4 was released.
*YP 5.0.18 is in review.
*YP 5.0.18 is in QA.
*YP 6.0.1 is in QA.
*YP 6.0.1
**Build Date  2026-05-18
**Release Date 2026-06-01
*YP 5.0.19
*YP 5.0.19
**Build Date  2026-06-30
**Build Date  2026-06-30

Latest revision as of 14:41, 26 May 2026

Yocto Project Status 26 May 2026

Current Dev Position: YP 6.1 M1
Next Deadline: YP 6.1 M1: w/c 2026-06-08

Next Team Meetings:

Project data dashboard: https://dashboard.yoctoproject.org/

Key Status/Updates:

  • YP 5.0.18 is out of QA and under review.
  • YP 6.0.1 is in QA
  • We’re working through the backlog of patches, the bandwidth for changes needing in depth review/feedback continues to be a challenge.
  • Intermittent build failures continue to be problematic and unchanged from last week:
    • several qemu ‘hang’ type issues
    • sometimes yocto-check-layer is showing checksum mismatch issues
    • siggen reset issues (“ResourceWarning: unclosed transport”)
    • groff build race issues
    • intermittent ptest failures in many recipes
  • Is anyone using 32 bit SDKs, if so let us know. Qemu dropped support for 32 bit hosts and we are considering discontinuing 32 bit SDKs.
  • We are likely to merge the gcc 16 upgrade soon
  • We would like to know what people are planning to work on for Yocto Project 6.1 and beyond. We have a roadmap document in Google Docs: https://docs.google.com/document/d/12xgAzSjDj5zVlo4eQIbiv1s3QMjtBTCvBFY3_T7OPto
  • We are updating the project’s security team and welcome nominations and/or feedback: https://lists.openembedded.org/g/openembedded-architecture/topic/119388716

Ways to contribute:

New to the project?

Tracking Metrics:

Upcoming dot releases:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC

Archives