== Yocto Project Weekly Status February 14th, 2023 ==
== Yocto Project Weekly Status February 21st, 2023 ==
Current Dev Position: YP 4.2 M3<br/>
Current Dev Position: YP 4.2 M3 Feature Freeze<br/>
Next Deadline: 20th February 2023 YP 4.2 M3 Build<br/>
Next Deadline: 20th February 2023 YP 4.2 M3 Build<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting Thursday February 16th 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Bug Triage meeting Thursday February 23rd 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Weekly Engineering Sync Tuesday February 14th 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Weekly Engineering Sync Tuesday February 21st 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Twitch -  See https://www.twitch.tv/theyoctojester
*Twitch -  See https://www.twitch.tv/theyoctojester


Line 32: Line 32:


'''Upcoming dot releases:'''<br/>
'''Upcoming dot releases:'''<br/>
*YP 3.1.23 is built and in QA
*YP 3.1.23 is ready for release
*YP 3.1.23 Release date 2023/02/24
*YP 4.0.8 build date 2023/02/27
*YP 4.0.8 build date 2023/02/27
*YP 4.0.8 Release date 2023/03/10
*YP 4.0.8 Release date 2023/03/10
Line 50: Line 49:


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2407 (last week 2437) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2402 (last week 2407) (https://wiki.yoctoproject.org/charts/combo.html)
*OE-Core/Poky Patch Metrics
*OE-Core/Poky Patch Metrics
**Total patches found: 1187 (last week 1200)
**Total patches found: 1186 (last week 1187)
**Patches in the Pending State: 277 (23%) [last week 280 (23%)]
**Patches in the Pending State: 277 (23%) [last week 277 (23%)]
*https://autobuilder.yocto.io/pub/non-release/patchmetrics/
*https://autobuilder.yocto.io/pub/non-release/patchmetrics/



Revision as of 15:35, 21 February 2023

Yocto Project Weekly Status February 21st, 2023

Current Dev Position: YP 4.2 M3 Feature Freeze
Next Deadline: 20th February 2023 YP 4.2 M3 Build

Next Team Meetings:

Key Status/Updates:

  • YP 3.1.23 was built and is in QA. There was an intermittent failure during the release build but this was a known issue recurring.
  • Next week is when M3 is due to build and this marks feature freeze for YP 4.2.
  • We saw a number of version upgrades this week (thanks Alex Kanavin).
  • There were also improvements to our runtime testing reliability (thanks Mikko Rapeli).
  • Of the issues discussed in https://lists.openembedded.org/g/openembedded-core/message/176476, the bitbake command timeout and PR serv async io issues still need to be addressed.
  • CVE levels in master are reducing but help in resolving the remaining issues would be appreciated.
  • We have a growing number of bugs in bugzilla, any help with them is appreciated.

Ways to contribute:

YP 4.2 Milestone Dates:

  • YP 4.2 M3 build date 2023/02/20
  • YP 4.2 M3 Release date 2023/03/03
  • YP 4.2 M4 build date 2023/04/03
  • YP 4.2 M4 Release date 2023/04/28

Upcoming dot releases:

  • YP 3.1.23 is ready for release
  • YP 4.0.8 build date 2023/02/27
  • YP 4.0.8 Release date 2023/03/10
  • YP 4.1.3 build date 2023/03/06
  • YP 4.1.3 Release date 2023/03/17
  • YP 3.1.24 build date 2023/03/20
  • YP 3.1.24 Release date 2023/03/31
  • YP 4.0.9 build date 2023/04/10
  • YP 4.0.9 Release date 2023/04/21
  • YP 4.1.4 build date 2023/05/01
  • YP 4.1.4 Release date 2023/05/13
  • YP 3.1.25 build date 2023/05/08
  • YP 3.1.25 Release date 2023/05/19
  • YP 4.0.10 build date 2023/05/15
  • YP 4.0.10 Release date 2023/05/26

Tracking Metrics: