== Yocto Project Weekly Status Aug. | == Yocto Project Weekly Status Aug. 13th, 2024 == | ||
Current Dev Position: YP 5.1 M3 <br/> | Current Dev Position: YP 5.1 M3 <br/> | ||
Next Deadline: YP 5.1 M3 Build 26 Aug. 2024<br/> | Next Deadline: YP 5.1 M3 Build 26 Aug. 2024<br/> | ||
'''Next Team Meetings:'''<br/> | '''Next Team Meetings:'''<br/> | ||
*Bug Triage meeting Thursday Aug. | *Bug Triage meeting Thursday Aug. 15th at 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09) | ||
*Weekly Engineering Sync Tuesday Aug. | *Weekly Engineering Sync Tuesday Aug. 13th at 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09) | ||
*Twitch - See https://www.twitch.tv/theyoctojester | *Twitch - See https://www.twitch.tv/theyoctojester | ||
'''Key Status/Updates:'''<br/> | '''Key Status/Updates:'''<br/> | ||
*Feature freeze for YP 5.1 is now | *Feature freeze for YP 5.1 is now 2 weeks away! | ||
*YP 5. | *YP 5.0.3 is in QA | ||
* | *The 6.10 is now enabled by default (thanks Bruce). Warnings for genericarm64 remain for at least 6.6. | ||
* | *Rust was upgraded to 1.77.2, thanks Yash. | ||
*Gcc was upgraded to 14.2, thanks Khem. | |||
*A new version of the cve-check/vex series is under review, thanks Marta. | |||
*The new mesa version requires meta-clang for the intel drivers. We need to make a decision on how to handle this, clang is likely to make its way to core at some point but work is needed to make the overrides suitable for core before that can happen. | *The new mesa version requires meta-clang for the intel drivers. We need to make a decision on how to handle this, clang is likely to make its way to core at some point but work is needed to make the overrides suitable for core before that can happen. | ||
'''Ways to contribute:'''<br/> | '''Ways to contribute:'''<br/> | ||
Line 32: | Line 28: | ||
'''Tracking Metrics:'''<br/> | '''Tracking Metrics:'''<br/> | ||
*WDD | *WDD 2758 (last week 2088) (https://wiki.yoctoproject.org/charts/combo.html) | ||
*OE-Core/Poky Patch Metrics | *OE-Core/Poky Patch Metrics | ||
**Total patches found: | **Total patches found: 1088 (last week 1072) | ||
**Patches in the Pending State: | **Patches in the Pending State: 178 (16%) [last week 179 (17%)] | ||
*https://autobuilder.yocto.io/pub/non-release/patchmetrics/ | *https://autobuilder.yocto.io/pub/non-release/patchmetrics/ | ||
'''YP 5.1 Milestone Dates:'''<br/> | '''YP 5.1 Milestone Dates:'''<br/> | ||
*YP 5.1 M3 Build date 2024-08-26 | *YP 5.1 M3 Build date 2024-08-26 | ||
*YP 5.1 M3 Release date 2024-09-06 | *YP 5.1 M3 Release date 2024-09-06 | ||
Line 46: | Line 41: | ||
'''Upcoming dot releases:'''<br/> | '''Upcoming dot releases:'''<br/> | ||
*YP 5.0.3 | *YP 5.0.3 is in QA. | ||
*YP 4.0.21 Build Date 2024-09-09 | *YP 4.0.21 Build Date 2024-09-09 | ||
*YP 4.0.21 Release Date 2024-09-20 | *YP 4.0.21 Release Date 2024-09-20 |
Revision as of 14:54, 13 August 2024
Yocto Project Weekly Status Aug. 13th, 2024
Current Dev Position: YP 5.1 M3
Next Deadline: YP 5.1 M3 Build 26 Aug. 2024
Next Team Meetings:
- Bug Triage meeting Thursday Aug. 15th at 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
- Weekly Engineering Sync Tuesday Aug. 13th at 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
- Twitch - See https://www.twitch.tv/theyoctojester
Key Status/Updates:
- Feature freeze for YP 5.1 is now 2 weeks away!
- YP 5.0.3 is in QA
- The 6.10 is now enabled by default (thanks Bruce). Warnings for genericarm64 remain for at least 6.6.
- Rust was upgraded to 1.77.2, thanks Yash.
- Gcc was upgraded to 14.2, thanks Khem.
- A new version of the cve-check/vex series is under review, thanks Marta.
- The new mesa version requires meta-clang for the intel drivers. We need to make a decision on how to handle this, clang is likely to make its way to core at some point but work is needed to make the overrides suitable for core before that can happen.
Ways to contribute:
- As people are likely aware, the project has a number of components which are either unmaintained, or have people with little to no time trying to keep them alive. These components include: devtool, toaster, wic, oeqa, autobuilder, CROPs containers, pseudo and more. Many have open bugs. Help is welcome in trying to better look after these components!
- There is an issue open upstream with the openssl project related to making path relocation of openssl easier (as used in our buildtools tarball and SDK). We’d love assistance in moving this forward and getting some kind of upstream feature merged to make this easier: https://github.com/openssl/openssl/pull/19260
- There are bugs identified as possible for newcomers to the project: https://wiki.yoctoproject.org/wiki/Newcomers
- There are bugs that are currently unassigned for YP 5.1. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium+_5.1_Unassigned_Enhancements/Bugs
- We’d welcome new maintainers for recipes in OE-Core. Please see the list at: http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/maintainers.inc and discuss with the existing maintainer, or ask on the OE-Core mailing list. We will likely move a chunk of these to “Unassigned” soon to help facilitate this.
- Help is very much welcome in trying to resolve our autobuilder intermittent issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT.
- Help us resolve CVE issues: CVE metrics
- We have a growing number of bugs in bugzilla, any help with them is appreciated.
Tracking Metrics:
- WDD 2758 (last week 2088) (https://wiki.yoctoproject.org/charts/combo.html)
- OE-Core/Poky Patch Metrics
- Total patches found: 1088 (last week 1072)
- Patches in the Pending State: 178 (16%) [last week 179 (17%)]
- https://autobuilder.yocto.io/pub/non-release/patchmetrics/
YP 5.1 Milestone Dates:
- YP 5.1 M3 Build date 2024-08-26
- YP 5.1 M3 Release date 2024-09-06
- YP 5.1 M4 Build date 2024-09-30
- YP 5.1 M4 Release date 2024-10-25
Upcoming dot releases:
- YP 5.0.3 is in QA.
- YP 4.0.21 Build Date 2024-09-09
- YP 4.0.21 Release Date 2024-09-20
- YP 5.0.4 Build Date 2024-09-23
- YP 5.0.4 Release Date 2024-10-04
- YP 4.0.22 Build Date 2024-10-14
- YP 4.0.22 Release Date 2024-10-25
- YP 5.0.5 Build Date 2024-11-11
- YP 5.0.5 Release Date 2024-11-22
- YP 4.0.23 Build Date 2024-11-18
- YP 4.0.23 Release Date 2024-11-29
The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC