== Yocto Project Weekly Status Aug. 5th, 2025 ==
== Yocto Project Weekly Status Oct. 28th, 2025 ==
Current Dev Position: YP 5.3 M2<br/>
Current Dev Position: YP 5.3 M4 - Stabilization and Final Build/Release<br/>
Next Deadline: YP 5.3 M2 Build date 2025-07-21<br/>
Next Deadline: YP 5.3 M4 Build Date 2025-11-10<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting - Thursday Aug. 7th at 7:30 am PST (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Bug Triage meeting - Thursday Oct. 30th at 7:30 am PST (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Weekly Project Engineering Sync - Tuesday Aug. 5th at 8 am PST (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Weekly Project Engineering Sync - Tuesday Oct. 28th at 8 am PST (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Yocto Project Patch Review - Thursday Aug. 7th 10am GMT and Monday Aug. 11th 9am PDT (https://zoom.us/j/97762397148?pwd=1xkiC9hp9SjEonaTaONwTb6iWry4Eb.1)  
*Yocto Project Patch Review - Thursday Oct. 30th 10am GMT and Monday Nov. 3rd 9am PDT (https://zoom.us/j/97762397148?pwd=1xkiC9hp9SjEonaTaONwTb6iWry4Eb.1)  


'''Project data dashboard: https://dashboard.yoctoproject.org/'''<br/>
'''Project data dashboard: https://dashboard.yoctoproject.org/'''<br/>


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*YP 5.3 M2 is due to be released
*YP 5.3 M3 is in QA
*Patches continue to merge into master for upgrades and fixes.
*YP 5.0.13 is under review for release
*Things have noticeably slowed due to holidays.
*Documentation updates related to many of the recent changes are in progress, thanks to all who have helped on these.
*xz is now a required host tool
*We have now past feature freeze for YP 5.3. To be accepted, patches that have a high bar until after we branch master from whinlatter.  Known issues:
*Patches are proposed to change the default images to be .zst compressed since these work better for releases and sharing
**check-layer tests are now running under nodistro instead of poky, so some layers are failing as they assume some DISTRO_FEATURES are enabled.
*Compressed images have implications for runqemu which needs to be run in snapshot mode to boot them
**Toaster is broken with bitbake-setup (#16012). Help moving to supporting non-poky layouts would be good if anyone is using Toaster.
*The clang build time (41min -> 76min) and size (350MB -> 535MB) increases continue to cause significant concern. There is some minor improvement with recent patches but much work remains to regain speed/space.
**The patch/cve metrics jobs need reviewing to be sure they’re correct with bitbake-setup (#16013)
*The main mirroring issues left are around “downloadfilename” support in urls which likely needs to be rewritten.
**The build performance jobs don’t know that poky and oe-core are the same so the charts are currently wrong (#16014)
*For M3, the following changes have been mentioned as possibilities:
**Help welcomed to resolve these issues!
**Bitbake-setup (although this is feeling not ready and too late for the next LTS)
*Upstream linux kernel just end-of-life’d 6.16 but whinlatter contains 6.16. We are evaluating the situation with 6.17, feedback on it (for/against and known issues) would be welcome.
**wic split from OE-Core
*“poky” as a combo-layer repository will soon no longer be needed or updated for master and whinlatter branches.
**RISC-V tune changes (final part)
*There are likely going to be breaking changes to the npm fetcher related to ongoing security concerns.
**switch classextend to use [filter] support from bitbake


'''Ways to contribute:'''<br/>
'''Ways to contribute:'''<br/>
Line 37: Line 36:


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2841 (last week 2826) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 3001 (last week 3009) (https://wiki.yoctoproject.org/charts/combo.html)
*OE-Core/Poky Patch Metrics
*OE-Core/Poky Patch Metrics
**Total patches found: 1096 (last week 1096)
**Total patches found: 1091 (last week 1091)
**Patches in the Pending State: 156 (14%) [last week 156 (14%)]
**Patches in the Pending State: 153 (14%) [last week 153 (14%)]
*https://autobuilder.yocto.io/-release/patchmetrics/
*https://autobuilder.yocto.io/-release/patchmetrics/


'''YP 5.3 Milestone Dates:'''<br/>
'''YP 5.3 Milestone Dates:'''<br/>
*YP 5.3 M2 is to be released.
*YP 5.3 M3 is in QA.
*YP 5.3 M3 Build Date 2025-09-01
*YP 5.3 M4 Build Date 2025-11-10
*YP 5.3 M3 Release Date 2025-09-12
*YP 5.3 M4 Release Date 2025-11-28
*YP 5.3 M4 Build Date 2025-10-06
*YP 5.3 M4 Release Date 2025-10-31


'''Upcoming dot releases:'''<br/>
'''Upcoming dot releases:'''<br/>
*YP 4.0.29 Build Date 2025-08-11
*YP 5.0.13 is in review for release.
*YP 4.0.29 Release Date 2025-08-25
*YP 5.2.3 Build Date 2025-08-18
*YP 5.2.3 Release Date 2025-08-29
*YP 5.0.12 Build Date 2025-08-25
*YP 5.0.12 Release Date 2025-09-05
*YP 4.0.30 Build Date 2025-09-22
*YP 4.0.30 Release Date 2025-10-03
*YP 5.2.4 Build Date 2025-09-29
*YP 5.2.4 Release Date 2025-10-10
*YP 5.0.13 Build Date 2025-10-13
*YP 5.0.13 Release Date 2025-10-24
*YP 4.0.31 Build Date 2025-11-03
*YP 4.0.31 Build Date 2025-11-03
*YP 4.031 Release Date 2025-11-14
*YP 4.0.31 Release Date 2025-11-14
*YP 5.0.14 Build Date 2025-11-17
*YP 5.0.14 Build Date 2025-11-17
*YP 5.0.14 Release Date 2025-11-28
*YP 5.0.14 Release Date 2025-11-28

Latest revision as of 14:50, 28 October 2025

Yocto Project Weekly Status Oct. 28th, 2025

Current Dev Position: YP 5.3 M4 - Stabilization and Final Build/Release
Next Deadline: YP 5.3 M4 Build Date 2025-11-10

Next Team Meetings:

Project data dashboard: https://dashboard.yoctoproject.org/

Key Status/Updates:

  • YP 5.3 M3 is in QA
  • YP 5.0.13 is under review for release
  • Documentation updates related to many of the recent changes are in progress, thanks to all who have helped on these.
  • We have now past feature freeze for YP 5.3. To be accepted, patches that have a high bar until after we branch master from whinlatter. Known issues:
    • check-layer tests are now running under nodistro instead of poky, so some layers are failing as they assume some DISTRO_FEATURES are enabled.
    • Toaster is broken with bitbake-setup (#16012). Help moving to supporting non-poky layouts would be good if anyone is using Toaster.
    • The patch/cve metrics jobs need reviewing to be sure they’re correct with bitbake-setup (#16013)
    • The build performance jobs don’t know that poky and oe-core are the same so the charts are currently wrong (#16014)
    • Help welcomed to resolve these issues!
  • Upstream linux kernel just end-of-life’d 6.16 but whinlatter contains 6.16. We are evaluating the situation with 6.17, feedback on it (for/against and known issues) would be welcome.
  • “poky” as a combo-layer repository will soon no longer be needed or updated for master and whinlatter branches.
  • There are likely going to be breaking changes to the npm fetcher related to ongoing security concerns.

Ways to contribute:

Tracking Metrics:

YP 5.3 Milestone Dates:

  • YP 5.3 M3 is in QA.
  • YP 5.3 M4 Build Date 2025-11-10
  • YP 5.3 M4 Release Date 2025-11-28

Upcoming dot releases:

  • YP 5.0.13 is in review for release.
  • YP 4.0.31 Build Date 2025-11-03
  • YP 4.0.31 Release Date 2025-11-14
  • YP 5.0.14 Build Date 2025-11-17
  • YP 5.0.14 Release Date 2025-11-28
  • YP 4.0.32 Build Date 2025-12-15
  • YP 4.0.32 Release Date 2025-12-24
  • YP 5.0.15 Build Date 2026-01-05
  • YP 5.0.15 Release Date 2026-01-16