== Yocto Project Weekly Status January 7, 2020 ==
== Yocto Project Weekly Status May 28th, 2024 ==
Current Dev Position: YP 3.1 M2 <br/>
Current Dev Position: YP 5.1 M1 <br/>
Next Deadline: YP 3.1 M2 build date 1/20/2020<br/>
Next Deadline: YP 5.1 M1 Build 20 May 2024<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting Thursday Jan. 9th  at 7:30am PDT (https://zoom.us/j/454367603)
*Bug Triage meeting Thursday May 30th at 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Monthly Project Meeting Tuesday  Jan. 7th  at 8am  PDT (https://zoom.us/j/990892712)
*Weekly Engineering Sync Tuesday May 28th at 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Weekly Engineering Sync Tuesday Jan. 14th at 8am PDT (https://zoom.us/j/990892712)
*Twitch - See https://www.twitch.tv/theyoctojester
*Twitch - Next event is Tuesday Jan. 14th at 8am PDT (https://www.twitch.tv/yocto_project)


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*YP 3.1 M1 was released.
*YP 5.0.1 has been released.
*Over the last two weeks there were a number of significant fixes for hash equivalence which should resolve some of the long standing bugs reported here. Some of these fixes may require further architectural tweaks to the codebase but those are cleanups which can happen in due course now the root causes are identified.
*We have suspected a performance problem for a while, this has now been identified/confirmed as an issue with hash equivalence. The public server using websockets/SSL has significantly slowed down things, to the point a 2 hour world build is taking 18+ hours. In trying to improve this, we ended up destablising the autobuilders entirely, breaking many builds and halting the patch merging.
*There are performance issues that remain in hashequivlence but these will be looked at only once the correctness issues and intermittent test failures are addressed.
The problem is visible both at build initialization time and also at any point it rehashes due to new hash information from the server. We are still trying to work out ways to improve things but there appears to be multiple levels of different problems, including the hashserve client parallelism seeming to have bugs. The issue affects scarthgap as well as master.
*There are some puzzling selftest failures that remain, in particular a locked signatures one which seems to be caused through bad interaction with the hash equivalence code but is intermittent and does not make sense.
*A new gcc 14 compatible version of uninative was released allowing fedora 40 testing. Unfortunately there are issues with build failures on that host that are as yet uninvestigated.
*The patch queue for master should be roughly up to date which some key changes such as the gettext upgrade having merged recently. Some pending changes like the glibc upgrade look problematic.
*The WORKDIR to UNPACKDIR transition has merged and other layers are now working on the updates needed. There appear to be some challenges around go modules in particular which are needing more investigation and development time.
*A key functionality change has merged this week where the layout of the sstate directory has changed. This was done to try and improve performance and handle some performance issues where the previous code simply wasn’t scaling. There is no user visible impact but it does mean new sstate will be generated into a new layout and the older sstate will be ignored. The sstate filename length issues should also be addressed by this patchset.
*We aim to build YP 5.1 M1 after the performance issue is addressed and we have stable builds.
*Whilst the SWAT process is disbanded, the effect of this is that Richard now has to file the bugs personally. This distracts from other things that could be worked on.
*We were able to merge a chunk of pending patches but things are still processing slowly unfortunately.
*The triage team is worried about attendance at triage meetings and the project is finding it hard to find people to help fix bugs. If anyone is willing to work on bugs, assistance would be greatly appreciated.
*There are some CVE related announcements which are helpful to us:
*The TSC is working on LTS plans, productive discussions have been had and a new policy on handling this and stable releases should be available in the coming weeks.
**There was a CVE 5.1 Record format announcement with changes that encourage more useful data from our perspective
*We are continuing to collect ideas for YP 3.1 in this document: https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjnABc/edit?usp=sharing
**CISA announced on linkedin the creation of https://github.com/cisagov/vulnrichment
**Unfortunately there are reports that the backlog of CVEs without version constraints is growing rapidly
*There is an open letter the project has created related to the CVE/NVD situation, more information is available here: https://lists.openembedded.org/g/openembedded-architecture/message/1990
**Please consider signing this to show support for those changes.
**Signatures from small businesses/consultancies are as welcome as those from larger organizations as we want to demonstrate the breadth of the need for these changes.
*The project is sponsoring Syslinbit to separate out our CVE tooling from the build system into a standalone tool so that it can be used on software manifests of output at a later date.
*The project is in the process of testing a new way of hosting our autobuilder with plans to switch soon if successful. Our existing hardware is past end of life and showing increased hardware failures so is currently down on capacity meaning builds are taking longer than normal, also not helped with the performance issue identfiied above.
*Further performance graph improvements have merged and the graphs now have links to specific revisions allowing regressions to be much more easily tracked down.


'''Proposed YP 3.1 Milestone Dates'''<br/>
'''Ways to contribute:'''<br/>
*YP 3.1 M2 build date 1/20/2020
*As people are likely aware, the project has a number of components which are either unmaintained, or have people with little to no time trying to keep them alive. These components include: devtool, toaster, wic, oeqa, autobuilder, CROPs containers, pseudo and more. Many have open bugs. Help is welcome in trying to better look after these components!
*YP 3.1 M2 release date 1/31/2020
*There are bugs identified as possible for newcomers to the project: https://wiki.yoctoproject.org/wiki/Newcomers
*YP 3.1 M3 build date 2/24/2020
*There are bugs that are currently unassigned for YP 5.1. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium+_5.1_Unassigned_Enhancements/Bugs
*YP 3.1 M3 release date 3/6/2020
*We’d welcome new maintainers for recipes in OE-Core. Please see the list at: http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/maintainers.inc and discuss with the existing maintainer, or ask on the OE-Core mailing list. We will likely move a chunk of these to “Unassigned” soon to help facilitate this.
*YP 3.1 M4 build date  3/30/2020
*Help is very much welcome in trying to resolve our autobuilder intermittent issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT.
*YP 3.1 M4 release date  4/24/2020
*Help us resolve CVE issues: CVE metrics
*We have a growing number of bugs in bugzilla, any help with them is appreciated.


'''Planned upcoming dot releases:'''<br/>
'''Tracking Metrics:'''<br/>
*YP 2.7.3 build date  2/10/20
*WDD 2772 (last week 2752) (https://wiki.yoctoproject.org/charts/combo.html)
*YP 2.7.3 release date 2/21/20
*OE-Core/Poky Patch Metrics
*YP 3.0.2 build date  2/3/20
**Total patches found: 1121 (last week 1127)
*YP 3.0.2 release date 2/14/20
**Patches in the Pending State: 221 (20%) [last week 221 (20%)]
*https://autobuilder.yocto.io/pub/non-release/patchmetrics/


'''Tracking Metrics:'''<br/>
'''YP 5.1 Milestone Dates:'''<br/>
*WDD 2773 (last week 2783) (https://wiki.yoctoproject.org/charts/combo.html)
*YP 5.1 M1 Build date 2024-05-20
*Poky Patch Metrics 
*YP 5.1 M1 Release date 2024-05-31
**Total patches found: 1400 (last week 1400)
*YP 5.1 M2 Build date 2024-07-08
**Patches in the Pending State: 562 (40%) [last week 561 (40%)]
*YP 5.1 M2 Release date 2024-07-19
*YP 5.1 M3 Build date 2024-08-26
*YP 5.1 M3 Release date 2024-09-06
*YP 5.1 M4 Build date 2024-09-30
*YP 5.1 M4 Release date 2024-10-25
 
'''Upcoming dot releases:'''<br/>
*YP 5.0.1 is released.
*YP 4.0.19 build date 2024-06-03
*YP 4.0.19 Release date 2024-06-14
*YP 5.0.2 Build Date 2024-06-24
*YP 5.0.2 Release Date 2024-07-05
*YP 4.0.20 Build Date 2024-07-15
*YP 4.0.20 Release Date 2024-07-26
*YP 5.0.3 Build Date 2024-08-12
*YP 5.0.3 Release Date 2024-08-23
*YP 4.0.21 Build Date 2024-09-09
*YP 4.0.21 Release Date 2024-09-20
*YP 5.0.4 Build Date 2024-09-23
*YP 5.0.4 Release Date 2024-10-04
*YP 4.0.22 Build Date 2024-10-14
*YP 4.0.22 Release Date 2024-10-25
*YP 5.0.5 Build Date 2024-11-11
*YP 5.0.5 Release Date 2024-11-22
*YP 4.0.23 Build Date 2024-11-18
*YP 4.0.23 Release Date 2024-11-29


'''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/>
'''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/>
Line 45: Line 78:


== Archives ==
== Archives ==
*[[2024 Yocto Project Weekly Status Archive]]
*[[2023 Yocto Project Weekly Status Archive]]
*[[2022 Yocto Project Weekly Status Archive]]
*[[2021 Yocto Project Weekly Status Archive]]
*[[2020 Yocto Project Weekly Status Archive]]
*[[2020 Yocto Project Weekly Status Archive]]
*[[2019 Yocto Project Weekly Status Archive]]
*[[2019 Yocto Project Weekly Status Archive]]
*[[2018 Yocto Project Weekly Status Archive]]
*[[2018 Yocto Project Weekly Status Archive]]

Latest revision as of 14:40, 28 May 2024

Yocto Project Weekly Status May 28th, 2024

Current Dev Position: YP 5.1 M1
Next Deadline: YP 5.1 M1 Build 20 May 2024

Next Team Meetings:

Key Status/Updates:

  • YP 5.0.1 has been released.
  • We have suspected a performance problem for a while, this has now been identified/confirmed as an issue with hash equivalence. The public server using websockets/SSL has significantly slowed down things, to the point a 2 hour world build is taking 18+ hours. In trying to improve this, we ended up destablising the autobuilders entirely, breaking many builds and halting the patch merging.

The problem is visible both at build initialization time and also at any point it rehashes due to new hash information from the server. We are still trying to work out ways to improve things but there appears to be multiple levels of different problems, including the hashserve client parallelism seeming to have bugs. The issue affects scarthgap as well as master.

  • A new gcc 14 compatible version of uninative was released allowing fedora 40 testing. Unfortunately there are issues with build failures on that host that are as yet uninvestigated.
  • The WORKDIR to UNPACKDIR transition has merged and other layers are now working on the updates needed. There appear to be some challenges around go modules in particular which are needing more investigation and development time.
  • We aim to build YP 5.1 M1 after the performance issue is addressed and we have stable builds.
  • We were able to merge a chunk of pending patches but things are still processing slowly unfortunately.
  • There are some CVE related announcements which are helpful to us:
    • There was a CVE 5.1 Record format announcement with changes that encourage more useful data from our perspective
    • CISA announced on linkedin the creation of https://github.com/cisagov/vulnrichment
    • Unfortunately there are reports that the backlog of CVEs without version constraints is growing rapidly
  • There is an open letter the project has created related to the CVE/NVD situation, more information is available here: https://lists.openembedded.org/g/openembedded-architecture/message/1990
    • Please consider signing this to show support for those changes.
    • Signatures from small businesses/consultancies are as welcome as those from larger organizations as we want to demonstrate the breadth of the need for these changes.
  • The project is sponsoring Syslinbit to separate out our CVE tooling from the build system into a standalone tool so that it can be used on software manifests of output at a later date.
  • The project is in the process of testing a new way of hosting our autobuilder with plans to switch soon if successful. Our existing hardware is past end of life and showing increased hardware failures so is currently down on capacity meaning builds are taking longer than normal, also not helped with the performance issue identfiied above.
  • Further performance graph improvements have merged and the graphs now have links to specific revisions allowing regressions to be much more easily tracked down.

Ways to contribute:

Tracking Metrics:

YP 5.1 Milestone Dates:

  • YP 5.1 M1 Build date 2024-05-20
  • YP 5.1 M1 Release date 2024-05-31
  • YP 5.1 M2 Build date 2024-07-08
  • YP 5.1 M2 Release date 2024-07-19
  • YP 5.1 M3 Build date 2024-08-26
  • YP 5.1 M3 Release date 2024-09-06
  • YP 5.1 M4 Build date 2024-09-30
  • YP 5.1 M4 Release date 2024-10-25

Upcoming dot releases:

  • YP 5.0.1 is released.
  • YP 4.0.19 build date 2024-06-03
  • YP 4.0.19 Release date 2024-06-14
  • YP 5.0.2 Build Date 2024-06-24
  • YP 5.0.2 Release Date 2024-07-05
  • YP 4.0.20 Build Date 2024-07-15
  • YP 4.0.20 Release Date 2024-07-26
  • YP 5.0.3 Build Date 2024-08-12
  • YP 5.0.3 Release Date 2024-08-23
  • YP 4.0.21 Build Date 2024-09-09
  • YP 4.0.21 Release Date 2024-09-20
  • YP 5.0.4 Build Date 2024-09-23
  • YP 5.0.4 Release Date 2024-10-04
  • YP 4.0.22 Build Date 2024-10-14
  • YP 4.0.22 Release Date 2024-10-25
  • YP 5.0.5 Build Date 2024-11-11
  • YP 5.0.5 Release Date 2024-11-22
  • YP 4.0.23 Build Date 2024-11-18
  • YP 4.0.23 Release Date 2024-11-29

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at: