== Yocto Project Status 5 May 2026 ==
== Yocto Project Status 21 July 2026 ==
Current Dev Position: YP 6.1 M1<br/>
Current Dev Position: YP 6.1 M2<br/>
Next Deadline: YP 6.1 M1: w/c 2026-06-22<br/>
Next Deadline: YP 6.1 M2: w/c 2026-07-20<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting - Thursday 7th May 7:30am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Bug Triage meeting - Thursday 23rd July 7:30am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Weekly Project Engineering Sync - Tuesday 5th May 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Weekly Project Engineering Sync - Tuesday 21st July 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Yocto Project Patch Review - Thursday 7th May 10am GMT and Monday 11th May 9am PDT (https://zoom.us/j/97762397148?pwd=1xk0iC9hp9SjEonaTaONwTb6iWry4Eb.1)
*Yocto Project Patch Review - Thursday 23rd July 10am GMT and Monday 27th July 9am PDT (https://zoom.us/j/97762397148?pwd=1xk0iC9hp9SjEonaTaONwTb6iWry4Eb.1)


'''Project data dashboard: https://dashboard.yoctoproject.org/'''<br/>
'''Project data dashboard: https://dashboard.yoctoproject.org/'''<br/>


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*YP 4.0.35 was released
*YP 6.0.2 has been released
*YP 5.3.4 is due to release, pending TSC approval
*YP 5.0.19 is due to release
*YP 6.0 is due to release, pending TSC approval
*YP 6.1 M2 will build this week after pseudo, systemd and resulttool changes merge
*We’re working through the backlog of patches, the bandwidth for changes needing in depth review/feedback continues to be a challenge
*Some invasive LICENSE changes have merged into master:
*Intermittent build failures continue to be problematic
**We now require the LICENSE field to match SPDX identifiers.
*Patch review/merging is slow due to public holidays clashing with a review call
**The build will issue warnings when this isn’t the case.
*Master is open for new development.
**Non SPDX licenses will need to be of the form LicenseRef-XXX
**CLOSED is no longer a valid value.
**‘WITH’ license exceptions are now supported
Big thanks for Joshua for getting us to the point where we can finally clean this up!
*We have identified a few linux-yocto CVEs which need triaging due to missing version information in the CVE databases (affecting master, wrynose and scarthgap), see the email sent to the list: https://lists.yoctoproject.org/g/yocto/topic/120036383
*Patches generated by the automatic upgrade helper (AUH) now include changelogs where these can be extracted from upstream.
*A couple of further pseudo related issues were identified, one with linkat flags and one with openat2 (tar related/triggered). We hope to have patches merged soon.
*Systemd issues with older host kernels (e.g. RHEL 8) is still being worked on https://lists.openembedded.org/g/openembedded-architecture/topic/119870359
*We’re working through the backlog of patches, the bandwidth for changes needing in depth review/feedback continues to be a challenge. The review calls are running out of time each meeting which limits progress.
**We’re making little progress on intermittent build failures despite the problems continuing to impact test builds:
**several qemu ‘hang’ type issues on ARM
**sometimes yocto-check-layer is showing checksum mismatch issues
**siggen reset issues (“ResourceWarning: unclosed transport”)
**groff build race issues
**intermittent ptest failures in many recipes
*For the qemuarmv5 amba crash (#16217), we did confirm it doesn’t seem to be load or memory usage related and does seem to happen on the autobuilder but not on other systems, for reasons still currently unknown.


'''Ways to contribute:'''<br/>
'''Ways to contribute:'''<br/>
Line 29: Line 44:


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2698 (last week 2788) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2719 (last week 2689) (https://wiki.yoctoproject.org/charts/combo.html)
*OE-Core/Poky Patch Metrics
*OE-Core/Poky Patch Metrics
**Total patches found: 1087 (last week 1085)
**Total patches found: 1019 (last week 1019+)
**Patches in the Pending State: 146 (13%) [last week 146 (13%)]
**Patches in the Pending State: 144 (14%) [last week 145 (14%)]
**https://valkyrie.yocto.io/pub/non-release/patchmetrics/
**https://valkyrie.yocto.io/pub/non-release/patchmetrics/
'''Upcoming development releases:'''<br/>
*6.1 M2:
**Build Date: w/c 2026-07-20
**Release Date: w/c 2026-08-03
*6.1 M3:
**Build Date: w/c 2026-08-31
**Release Date: w/c 2026-09-14
*6.1.0:
**Build Date (M4): w/c 2026-10-12
**Release Date: w/c 2026-11-02


'''Upcoming dot releases:'''<br/>
'''Upcoming dot releases:'''<br/>
*YP 5.3.4 is due to release, pending TSC approval
*YP 5.0.19 due to release
*YP 5.0.18
**Release Date w/c 2026-07-13
**Build Date 2026-05-11
*YP 6.0.3
**Release Date 2026-05-25
**Build Date w/c 2026-08-10
*YP 6.0.1
**Release Date w/c 2026-08-24
**Build Date 2026-05-18
*YP 5.0.20
**Release Date 2026-06-01
**Build Date w/c 2026-08-17
**Release Date w/c 2026-08-31
 
*For future release dates, see https://wiki.yoctoproject.org/wiki/Release_calendar
*For future release dates, see https://wiki.yoctoproject.org/wiki/Release_calendar



Latest revision as of 14:50, 21 July 2026

Yocto Project Status 21 July 2026

Current Dev Position: YP 6.1 M2
Next Deadline: YP 6.1 M2: w/c 2026-07-20

Next Team Meetings:

Project data dashboard: https://dashboard.yoctoproject.org/

Key Status/Updates:

  • YP 6.0.2 has been released
  • YP 5.0.19 is due to release
  • YP 6.1 M2 will build this week after pseudo, systemd and resulttool changes merge
  • Some invasive LICENSE changes have merged into master:
    • We now require the LICENSE field to match SPDX identifiers.
    • The build will issue warnings when this isn’t the case.
    • Non SPDX licenses will need to be of the form LicenseRef-XXX
    • CLOSED is no longer a valid value.
    • ‘WITH’ license exceptions are now supported

Big thanks for Joshua for getting us to the point where we can finally clean this up!

  • We have identified a few linux-yocto CVEs which need triaging due to missing version information in the CVE databases (affecting master, wrynose and scarthgap), see the email sent to the list: https://lists.yoctoproject.org/g/yocto/topic/120036383
  • Patches generated by the automatic upgrade helper (AUH) now include changelogs where these can be extracted from upstream.
  • A couple of further pseudo related issues were identified, one with linkat flags and one with openat2 (tar related/triggered). We hope to have patches merged soon.
  • Systemd issues with older host kernels (e.g. RHEL 8) is still being worked on https://lists.openembedded.org/g/openembedded-architecture/topic/119870359
  • We’re working through the backlog of patches, the bandwidth for changes needing in depth review/feedback continues to be a challenge. The review calls are running out of time each meeting which limits progress.
    • We’re making little progress on intermittent build failures despite the problems continuing to impact test builds:
    • several qemu ‘hang’ type issues on ARM
    • sometimes yocto-check-layer is showing checksum mismatch issues
    • siggen reset issues (“ResourceWarning: unclosed transport”)
    • groff build race issues
    • intermittent ptest failures in many recipes
  • For the qemuarmv5 amba crash (#16217), we did confirm it doesn’t seem to be load or memory usage related and does seem to happen on the autobuilder but not on other systems, for reasons still currently unknown.

Ways to contribute:

New to the project?

Tracking Metrics:

Upcoming development releases:

  • 6.1 M2:
    • Build Date: w/c 2026-07-20
    • Release Date: w/c 2026-08-03
  • 6.1 M3:
    • Build Date: w/c 2026-08-31
    • Release Date: w/c 2026-09-14
  • 6.1.0:
    • Build Date (M4): w/c 2026-10-12
    • Release Date: w/c 2026-11-02

Upcoming dot releases:

  • YP 5.0.19 due to release
    • Release Date w/c 2026-07-13
  • YP 6.0.3
    • Build Date w/c 2026-08-10
    • Release Date w/c 2026-08-24
  • YP 5.0.20
    • Build Date w/c 2026-08-17
    • Release Date w/c 2026-08-31