== Yocto Project Weekly Status Feb. 11th, 2025 ==
== Yocto Project Weekly Status Mar. 25th, 2025 ==
Current Dev Position: YP 5.2 M3<br/>
Current Dev Position: YP 5.2 M4 - Feature Freeze<br/>
Next Deadline: YP 5.2 M3 Build date 2025-03-03<br/>
Next Deadline: YP 5.2 M4 Build Date 2025-03-31 - Feature Freeze<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting Thursday Feb. 13th at 7:30 am PST (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Bug Triage meeting - Thursday Mar. 27th at 7:30 am PST (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Weekly Project Engineering Sync Tuesday Feb. 11th at 8 am PST (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Weekly Project Engineering Sync - Tuesday Mar. 25th at 8 am PST (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Twitch - See https://www.twitch.tv/theyoctojester
*Yocto Project Patch Review - Thursday Mar. Mar 27th 10am GMT and Monday Mar. 31st 9am PDT (https://zoom.us/j/97762397148?pwd=1xkiC9hp9SjEonaTaONwTb6iWry4Eb.1)
 
'''Project data dashboard: https://dashboard.yoctoproject.org/'''<br/>


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*YP 5.2 M2 was released
*YP 5.2 M3 is due to be released
*YP 5.0.7 is under review and passed QA
*YP 5.0.8 is due to be released
*We are now 3 weeks from feature freeze for 5.2
*YP 5.1.4 is in QA
*The project autobuilder has upgraded the controller to buildbot 4.2 which was tricky due to our custom plugin and changes to the framework used for the UI. The new UI should have the same functionality and seems faster and easier to use in places.
*We are at feature freeze for YP 5.2 with our first rc build next week
*We’d like to request help to process the open github pull requests for openembedded-core and bitbake:
*We have continued to merge gcc 15 fixes in anticipation of being prepared for host distro changes in the next six months.
**https://github.com/openembedded/openembedded-core/pulls
*The minimum python version was increased to 3.9 with support for Ubuntu 20.04 now requiring buildtools due to changing g++ requirements.
**https://github.com/openembedded/bitbake/pulls
*SRC_URI entries for git now support tag verification against a specified source revision
*Having these open doesn’t look good for the projects and we can’t disable them, some have been open for a long time. We did already clean up the poky pull requests.
*Bitbake fetcher support for multiple revisions in a single git SRC_URI entry was removed for code simplification.
*The project has agreed guidance on AI submissions: https://lists.yoctoproject.org/g/docs/message/6300
*Kernel stable updates merged including a key qemumips fix and various CVE fixes.
*There are multiple occasional but annoying autobuilder failures we could do with help debugging/fixing, summarized by https://valkyrie.yocto.io/pub/non-release/abint/ :
*A pseudo bug was identified and there is a reproduction patch posted however we’re struggling to work out how to fix it. We do have a workaround for the underlying pciutils trigger.
**An occasional hang for non-kvm x86/x86-64 qemu images early in boot, see in multiple kernels including the recent 6.12:
*We are aware of 500/502 errors from the project git servers. These are caused by load from the significant number of AI crawlers the infrastructure is being overloaded with which is hard to mitigate against.
***https://autobuilder.yoctoproject.org/valkyrie/#/builders/28/builds/955
***https://bugzilla.yoctoproject.org/show_bug.cgi?id=15463
**dnf failures in where ssh appears to fail, usually on qemumips but also seen on qemuarm: https://bugzilla.yoctoproject.org/show_bug.cgi?id=13674
**Ongoing CDN failures
**New memory allocation issues hinting we may need to scale builds back
*We are open to help developing patches to help debug issue further or other ideas on the causes and/or ways to mitigate them
*The Linux Foundation published information on navigating global regulations and sanctions: https://www.linuxfoundation.org/blog/navigating-global-regulations-and-open-source-us-ofac-sanctions
*Please contact TSC members if there are questions/concerns.
*The gomod mirror issue in meta-openembedded continues to give failed builds on the autobuilder.
*Gold linker support was removed from core.
*Linux 6.6 was removed so we now just have the 6.12 kernel we plan to release YP 5.2 with.
*The performance metric charts were improved to be able to show both commit based and time based data, allowing performance changes to be isolated more easily.
*The triage team decided to clear out the “newcomer” bugs in bugzilla since the remaining ones were likely too hard without specialist knowledge. We’d love to see new/realist newcomer bugs being added.
*The 5.2 development plans are being developed in this document: https://docs.google.com/document/d/1xsnN_HcaMhqg6Dn1P_19AnumDaUMQSdFZ_I4rjD830A/edit?usp=sharing
*We need to continue to develop this, thanks to all who have contributed so far!


'''Ways to contribute:'''<br/>
'''Ways to contribute:'''<br/>
Line 45: Line 32:
*Help us resolve CVE issues: CVE metrics  
*Help us resolve CVE issues: CVE metrics  
*We have a growing number of bugs in bugzilla, any help with them is appreciated.
*We have a growing number of bugs in bugzilla, any help with them is appreciated.
*Ongoing project development plans are being developed in this document: https://docs.google.com/document/d/1xsnN_HcaMhqg6Dn1P_19AnumDaUMQSdFZ_I4rjD830A/edit?usp=sharing We need to continue to develop this as it will allow us to potentially find ways to fund specific work items.


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2711 (last week 2704) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2801 (last week 2786) (https://wiki.yoctoproject.org/charts/combo.html)
*OE-Core/Poky Patch Metrics
*OE-Core/Poky Patch Metrics
**Total patches found: 1025 (last week 1029)
**Total patches found: 1060 (last week 1049)
**Patches in the Pending State: 172 (17%) [last week 173 (17%)]
**Patches in the Pending State: 168 (16%) [last week 171 (17%)]
*https://autobuilder.yocto.io/-release/patchmetrics/
*https://autobuilder.yocto.io/-release/patchmetrics/


'''YP 5.2 Milestone Dates:'''<br/>
'''YP 5.2 Milestone Dates:'''<br/>
*YP 5.2 M2 was released.
*YP 5.2 M3 is ready for release.
*YP 5.2 M3 Build Date 2025-03-03
*YP 5.2 M3 Release Date 2025-03-14
*YP 5.2 M4 Build Date 2025-03-31
*YP 5.2 M4 Build Date 2025-03-31
*YP 5.2 M4 Release Date 2025-04-25
*YP 5.2 M4 Release Date 2025-04-25


'''Upcoming dot releases:'''<br/>
'''Upcoming dot releases:'''<br/>
*YP 5.0.7 is in review.
*YP 5.0.8 is ready for release.
*YP 4.0.25 Build Date 2025-02-17
*YP 5.1.4 is in QA.
*YP 4.0.25 Release Date 2025-02-28
*YP 5.1.3 Build Date 2025-02-24
*YP 5.1.3 Release Date 2025-03-07
*YP 5.0.8 Build Date 2025-03-10
*YP 5.0.8 Release Date 2025-03-21
*YP 5.1.4 Build Date 2025-03-24
*YP 5.1.4 Release Date 2025-04-04
*YP 4.0.26 Build Date 2025-04-07
*YP 4.0.26 Build Date 2025-04-07
*YP 4.0.26 Release Date 2025-04-18
*YP 4.0.26 Release Date 2025-04-18

Revision as of 14:46, 25 March 2025

Yocto Project Weekly Status Mar. 25th, 2025

Current Dev Position: YP 5.2 M4 - Feature Freeze
Next Deadline: YP 5.2 M4 Build Date 2025-03-31 - Feature Freeze

Next Team Meetings:

Project data dashboard: https://dashboard.yoctoproject.org/

Key Status/Updates:

  • YP 5.2 M3 is due to be released
  • YP 5.0.8 is due to be released
  • YP 5.1.4 is in QA
  • We are at feature freeze for YP 5.2 with our first rc build next week
  • We have continued to merge gcc 15 fixes in anticipation of being prepared for host distro changes in the next six months.
  • The minimum python version was increased to 3.9 with support for Ubuntu 20.04 now requiring buildtools due to changing g++ requirements.
  • SRC_URI entries for git now support tag verification against a specified source revision
  • Bitbake fetcher support for multiple revisions in a single git SRC_URI entry was removed for code simplification.
  • Kernel stable updates merged including a key qemumips fix and various CVE fixes.
  • A pseudo bug was identified and there is a reproduction patch posted however we’re struggling to work out how to fix it. We do have a workaround for the underlying pciutils trigger.
  • We are aware of 500/502 errors from the project git servers. These are caused by load from the significant number of AI crawlers the infrastructure is being overloaded with which is hard to mitigate against.

Ways to contribute:

Tracking Metrics:

YP 5.2 Milestone Dates:

  • YP 5.2 M3 is ready for release.
  • YP 5.2 M4 Build Date 2025-03-31
  • YP 5.2 M4 Release Date 2025-04-25

Upcoming dot releases:

  • YP 5.0.8 is ready for release.
  • YP 5.1.4 is in QA.
  • YP 4.0.26 Build Date 2025-04-07
  • YP 4.0.26 Release Date 2025-04-18
  • YP 5.0.9 Build Date 2025-04-21
  • YP 5.0.9 Release Date 2025-05-02
  • YP 4.0.27 Build Date 2025-05-19
  • YP 4.0.27 Release Date 2025-05-30
  • YP 5.0.10 Build Date 2025-06-02
  • YP 5.0.10 Release Date 2025-06-13
  • YP 4.0.28 Build Date 2025-06-30
  • YP 4.0.28 Release Date 2025-07-11