== Yocto Project Weekly Status February 27th, 2024 ==
== Yocto Project Weekly Status May 14th, 2024 ==
Current Dev Position: YP 5.0 M3 - Feature Freeze <br/>
Current Dev Position: YP 5.1 M1 <br/>
Next Deadline: 19th February 2024 YP 5.0 M3 build<br/>
Next Deadline: YP 5.1 M1 Build 20 May 2024<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting Thursday February 29th at 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Bug Triage meeting Thursday May 16th at 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Weekly Engineering Sync Tuesday February 27th at 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Weekly Engineering Sync Tuesday May 14th at 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Twitch -  See https://www.twitch.tv/theyoctojester
*Twitch -  See https://www.twitch.tv/theyoctojester


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*We are now at feature freeze for 5.0, preparing to build M3
*YP 4.0.18 has been released
*YP 4.3.3 passed QA and is in review pending release
*YP 5.0.1 rc2 is in QA.
*The changes which we’d still like to see in 5.0 that have not merged yet are:
*YP 5.0.1 rc1 was abandoned due to high numbers of intermittent failures.
**genericarm64 machine (there is a draft and it is close)
*There are some CVE related announcements which are helpful to us:
**QA screenshot comparison
**There was a CVE 5.1 Record format announcement with changes that encourage more useful data from our perspective
**sstate permissions issue testcase
**CISA announced on linkedin the creation of https://github.com/cisagov/vulnrichment
*Several changes have merged for M3:
*There is an open letter the project has created related to the CVE/NVD situation, more information is available here: https://lists.openembedded.org/g/openembedded-architecture/message/1990
**ncurses based task dependency explorer (thanks David!)
**Please consider signing this to show support for those changes.
**change to rust test suite logging
**Signatures from small businesses/consultancies are as welcome as those from larger organizations as we want to demonstrate the breadth of the need for these changes.
**useradd fix
*The project is sponsoring Syslinbit to separate out our CVE tooling from the build system into a standalone tool so that it can be used on software manifests of output at a later date.
**dbus configuration security fix
*The WORKDIR to UNPACKDIR transition and redefinition of UNPACKDIR now has patches under testing in master-next, including updates to recipetool and devtool which pass our automated tests.
**bitbake hashserve improvements to better position future server capability/functionality
*gcc 14 has patches pending thanks for Khem and Martin in particular. Merging the new gcc version is needed to generate new uninative tarballs to support Fedora 40 builds or any other distro using the new gcc version.
**tweaks to support recipe locale support
*The project is in the process of testing a new way of hosting our autobuilder with plans to switch soon if successful. Our existing hardware is past end of life and showing increased hardware failures so is currently down on capacity meaning builds are taking longer than normal.
**support for BB_LOADFACTOR_MAX load regulation in bitbake when psi is unavailable.
*Mailing list changes now mean any google hosted email accounts have the mailing list From: address rewritten. This had impacted our ability to handle patches but key maintainers now have workarounds for this.
**further IDE integration tweaks and improvements
*Our automated tests have been seeing a number of intermittent issues. An email was sent detailing a few of these and the response with several patches or patches in progress has been extremely helpful and they’re very gratefully received.
*There are also several concerning issues without any clear resolution path at present:
**rust upgrade blocked by reproducibility issues
**musl upgrade blocked by large number of unsubmitted pending patches
**nativesdk-systemd usage broken by usrmerge requirement (we can’t changing the SDK layout now)
**go isn't upgraded (although there now are partial patches)
*There have been questions about official RISC-V support in this next release, especially since it is an LTS. We will trial qemuriscv64 support in M3 but remove it before the final LTS release as there is no sponsor for that support.


'''Ways to contribute:'''<br/>
'''Ways to contribute:'''<br/>
*As people are likely aware, the project has a number of components which are either unmaintained, or have people with little to no time trying to keep them alive. These components include: patchtest, layerindex, devtool, toaster, wic, oeqa, autobuilder, CROPs containers, pseudo and more. Many have open bugs. Help is welcome in trying to better look after these components!
*As people are likely aware, the project has a number of components which are either unmaintained, or have people with little to no time trying to keep them alive. These components include: devtool, toaster, wic, oeqa, autobuilder, CROPs containers, pseudo and more. Many have open bugs. Help is welcome in trying to better look after these components!
*There are bugs identified as possible for newcomers to the project: https://wiki.yoctoproject.org/wiki/Newcomers
*There are bugs identified as possible for newcomers to the project: https://wiki.yoctoproject.org/wiki/Newcomers
*There are bugs that are currently unassigned for YP 5.0. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium+_5.0_Unassigned_Enhancements/Bugs
*There are bugs that are currently unassigned for YP 5.1. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium+_5.1_Unassigned_Enhancements/Bugs
*We’d welcome new maintainers for recipes in OE-Core. Please see the list at: http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/maintainers.inc and discuss with the existing maintainer, or ask on the OE-Core mailing list. We will likely move a chunk of these to “Unassigned” soon to help facilitate this.
*We’d welcome new maintainers for recipes in OE-Core. Please see the list at: http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/maintainers.inc and discuss with the existing maintainer, or ask on the OE-Core mailing list. We will likely move a chunk of these to “Unassigned” soon to help facilitate this.
*Help is very much welcome in trying to resolve our autobuilder intermittent issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT.
*Help is very much welcome in trying to resolve our autobuilder intermittent issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT.
*Help us resolve CVE issues: CVE metrics  
*Help us resolve CVE issues: CVE metrics  
*We have a growing number of bugs in bugzilla, any help with them is appreciated.
*We have a growing number of bugs in bugzilla, any help with them is appreciated.
'''YP 5.0 Milestone Dates:'''<br/>
*YP 5.0 M3 build date  2024/02/19
*YP 5.0 M3 Release date 2024/03/01
*YP 5.0 M4 build date  2024/04/01
*YP 5.0 M4 Release date 2024/04/30
'''Upcoming dot releases:'''<br/>
*YP 4.3.3 is ready for release.
*YP 3.1.32 build date 2024/03/04
*YP 3.1.32 Release date 2024/03/15
*YP 4.0.17 build date 2024/03/11
*YP 4.0.17 Release date 2024/03/22
*YP 4.3.4 build date 2024/03/25
*YP 4.3.4 Release date 2024/04/05
*YP 3.1.33 build date 2024/04/15
*YP 3.1.33 Release date 2024/04/26
*YP 4.0.18 build date 2024/04/22
*YP 4.0.18 Release date 2024/05/03
*YP 4.0.19 build date 2024/06/03
*YP 4.0.19 Release date 2024/06/14


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2633 (last week 2636) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2740 (last week 2720) (https://wiki.yoctoproject.org/charts/combo.html)
*OE-Core/Poky Patch Metrics
*OE-Core/Poky Patch Metrics
**Total patches found: 1144 (last week 1145)
**Total patches found: 1128 (last week 1125)
**Patches in the Pending State: 250 (22%) [last week 250 (22%)]
**Patches in the Pending State: 221 (20%) [last week 221 (20%)]
*https://autobuilder.yocto.io/pub/non-release/patchmetrics/
*https://autobuilder.yocto.io/pub/non-release/patchmetrics/
'''YP 5.1 Milestone Dates:'''<br/>
*YP 5.1 M1 Build date 2024-05-20
*YP 5.1 M1 Release date 2024-05-31
*YP 5.1 M2 Build date 2024-07-08
*YP 5.1 M2 Release date 2024-07-19
*YP 5.1 M3 Build date 2024-08-26
*YP 5.1 M3 Release date 2024-09-06
*YP 5.1 M4 Build date 2024-09-30
*YP 5.1 M4 Release date 2024-10-25
'''Upcoming dot releases:'''<br/>
*YP 4.0.18 is released.
*YP 5.0.1 is in QA.
*YP 4.0.19 build date 2024-06-03
*YP 4.0.19 Release date 2024-06-14
*YP 5.0.2 Build Date 2024-06-24
*YP 5.0.2 Release Date 2024-07-05
*YP 4.0.20 Build Date 2024-07-15
*YP 4.0.20 Release Date 2024-07-26
*YP 5.0.3 Build Date 2024-08-12
*YP 5.0.3 Release Date 2024-08-23
*YP 4.0.21 Build Date 2024-09-09
*YP 4.0.21 Release Date 2024-09-20
*YP 5.0.4 Build Date 2024-09-23
*YP 5.0.4 Release Date 2024-10-04
*YP 4.0.22 Build Date 2024-10-14
*YP 4.0.22 Release Date 2024-10-25
*YP 5.0.5 Build Date 2024-11-11
*YP 5.0.5 Release Date 2024-11-22
*YP 4.0.23 Build Date 2024-11-18
*YP 4.0.23 Release Date 2024-11-29


'''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/>
'''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/>

Revision as of 14:38, 14 May 2024

Yocto Project Weekly Status May 14th, 2024

Current Dev Position: YP 5.1 M1
Next Deadline: YP 5.1 M1 Build 20 May 2024

Next Team Meetings:

Key Status/Updates:

  • YP 4.0.18 has been released
  • YP 5.0.1 rc2 is in QA.
  • YP 5.0.1 rc1 was abandoned due to high numbers of intermittent failures.
  • There are some CVE related announcements which are helpful to us:
    • There was a CVE 5.1 Record format announcement with changes that encourage more useful data from our perspective
    • CISA announced on linkedin the creation of https://github.com/cisagov/vulnrichment
  • There is an open letter the project has created related to the CVE/NVD situation, more information is available here: https://lists.openembedded.org/g/openembedded-architecture/message/1990
    • Please consider signing this to show support for those changes.
    • Signatures from small businesses/consultancies are as welcome as those from larger organizations as we want to demonstrate the breadth of the need for these changes.
  • The project is sponsoring Syslinbit to separate out our CVE tooling from the build system into a standalone tool so that it can be used on software manifests of output at a later date.
  • The WORKDIR to UNPACKDIR transition and redefinition of UNPACKDIR now has patches under testing in master-next, including updates to recipetool and devtool which pass our automated tests.
  • gcc 14 has patches pending thanks for Khem and Martin in particular. Merging the new gcc version is needed to generate new uninative tarballs to support Fedora 40 builds or any other distro using the new gcc version.
  • The project is in the process of testing a new way of hosting our autobuilder with plans to switch soon if successful. Our existing hardware is past end of life and showing increased hardware failures so is currently down on capacity meaning builds are taking longer than normal.
  • Mailing list changes now mean any google hosted email accounts have the mailing list From: address rewritten. This had impacted our ability to handle patches but key maintainers now have workarounds for this.
  • Our automated tests have been seeing a number of intermittent issues. An email was sent detailing a few of these and the response with several patches or patches in progress has been extremely helpful and they’re very gratefully received.

Ways to contribute:

Tracking Metrics:

YP 5.1 Milestone Dates:

  • YP 5.1 M1 Build date 2024-05-20
  • YP 5.1 M1 Release date 2024-05-31
  • YP 5.1 M2 Build date 2024-07-08
  • YP 5.1 M2 Release date 2024-07-19
  • YP 5.1 M3 Build date 2024-08-26
  • YP 5.1 M3 Release date 2024-09-06
  • YP 5.1 M4 Build date 2024-09-30
  • YP 5.1 M4 Release date 2024-10-25

Upcoming dot releases:

  • YP 4.0.18 is released.
  • YP 5.0.1 is in QA.
  • YP 4.0.19 build date 2024-06-03
  • YP 4.0.19 Release date 2024-06-14
  • YP 5.0.2 Build Date 2024-06-24
  • YP 5.0.2 Release Date 2024-07-05
  • YP 4.0.20 Build Date 2024-07-15
  • YP 4.0.20 Release Date 2024-07-26
  • YP 5.0.3 Build Date 2024-08-12
  • YP 5.0.3 Release Date 2024-08-23
  • YP 4.0.21 Build Date 2024-09-09
  • YP 4.0.21 Release Date 2024-09-20
  • YP 5.0.4 Build Date 2024-09-23
  • YP 5.0.4 Release Date 2024-10-04
  • YP 4.0.22 Build Date 2024-10-14
  • YP 4.0.22 Release Date 2024-10-25
  • YP 5.0.5 Build Date 2024-11-11
  • YP 5.0.5 Release Date 2024-11-22
  • YP 4.0.23 Build Date 2024-11-18
  • YP 4.0.23 Release Date 2024-11-29

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC

Archives