== Yocto Project Weekly Status June 20th, 2023 ==
== Yocto Project Weekly Status June 27th, 2023 ==
Current Dev Position: YP 4.3 M2<br/>
Current Dev Position: YP 4.3 M2<br/>
Next Deadline: 17th July 2023 YP 4.3 M2 build date<br/>
Next Deadline: 17th July 2023 YP 4.3 M2 build date<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting Thursday June 22nd 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Bug Triage meeting Thursday June 29th 7:30 am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
*Weekly Engineering Sync Tuesday June 20th 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Weekly Engineering Sync Tuesday June 27th 8 am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
*Twitch -  See https://www.twitch.tv/theyoctojester
*Twitch -  See https://www.twitch.tv/theyoctojester


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*YP 4.3 M1 was released
*YP 4.0.11 is in QA
*YP 3.1.26 is in QA
*YP 3.1.26 is due to be released
*The project has some exciting plans in progress and we're now in the fortunate position of seeking quotations for some development work. For more details please see this page on our website: https://www.yoctoproject.org/community/yocto-project-engineering-request-for-quotation/
*We’re pleased to announce that kirkstone LTS releases will be extended from 2 to 4 years and that project LTS releases will default to 4 years in future.
*The automated regression reporting saw some issues for the M1 report so this is being worked on.
*A lot of people have vacation booked for next week so we’re planning to skip a week with status reports and project meetings.
*There are pending patches to enable layer-<layername> overrides which is particularly useful for enabling layer specific QA checks. This does bring some changes of behavior for QA checks on bbappends
*We have an open request for quotation for several engineering tasks/projects: https://www.yoctoproject.org/community/yocto-project-engineering-request-for-quotation/
*usrmerge is now enabled by default for poky-altcfg, in preparation for the changes being required by systemd.
*We have merged changes to make 64 bit time_t the default for several 32 bit platforms as part of our plan to handle Y2038 issues. This does break ABI and may need careful handling for those with binaries where compatibility is needed.
*The 6.1 kernel hang regression was identified and we reverted the problematic patch until the correct fix merges and filters through the stable kernel trees.
*There have been a lot of ptest issues this week, not least after issues with “No-section” tracebacks were fixed, leading to an increase in reported failures as that was masking issues. There are some fixes proposed for ptest-runner but further help is needed on the various failures.
*We have been approached by a potential new maintainer for the eclipse plugins. There were some questions about who was still using it and what the test matrix should look like so please let us know if you are and we can connect you.
*The tunctl functionality for runqemu has been dropped as the ip tool can handle everything needed.


'''Ways to contribute:'''<br/>
'''Ways to contribute:'''<br/>
Line 30: Line 26:


'''YP 4.3 Milestone Dates:'''<br/>
'''YP 4.3 Milestone Dates:'''<br/>
*YP 4.3 M1 is released
*YP 4.3 M2 build date  2023/07/17
*YP 4.3 M2 build date  2023/07/17
*YP 4.3 M2 Release date 2023/07/28
*YP 4.3 M2 Release date 2023/07/28
Line 39: Line 34:


'''Upcoming dot releases:'''<br/>
'''Upcoming dot releases:'''<br/>
*YP 3.1.26 is in QA
*YP 3.1.26 is ready for  release
*YP 4.0.11 build date 2023/06/26
*YP 4.0.11 is in QA
*YP 4.0.11 Release date 2023/07/07
*YP 4.0.11 Release date 2023/07/07
*YP 4.2.2 build date 2023/07/10
*YP 4.2.2 build date 2023/07/10

Revision as of 14:42, 27 June 2023

Yocto Project Weekly Status June 27th, 2023

Current Dev Position: YP 4.3 M2
Next Deadline: 17th July 2023 YP 4.3 M2 build date

Next Team Meetings:

Key Status/Updates:

  • YP 4.0.11 is in QA
  • YP 3.1.26 is due to be released
  • We’re pleased to announce that kirkstone LTS releases will be extended from 2 to 4 years and that project LTS releases will default to 4 years in future.
  • A lot of people have vacation booked for next week so we’re planning to skip a week with status reports and project meetings.
  • We have an open request for quotation for several engineering tasks/projects: https://www.yoctoproject.org/community/yocto-project-engineering-request-for-quotation/
  • We have merged changes to make 64 bit time_t the default for several 32 bit platforms as part of our plan to handle Y2038 issues. This does break ABI and may need careful handling for those with binaries where compatibility is needed.

Ways to contribute:

YP 4.3 Milestone Dates:

  • YP 4.3 M2 build date 2023/07/17
  • YP 4.3 M2 Release date 2023/07/28
  • YP 4.3 M3 build date 2023/08/28
  • YP 4.3 M3 Release date 2023/09/08
  • YP 4.3 M4 build date 2023/10/02
  • YP 4.3 M4 Release date 2023/10/27

Upcoming dot releases:

  • YP 3.1.26 is ready for release
  • YP 4.0.11 is in QA
  • YP 4.0.11 Release date 2023/07/07
  • YP 4.2.2 build date 2023/07/10
  • YP 4.2.2 Release date 2023/07/21
  • YP 3.1.27 build date 2023/07/31
  • YP 3.1.27 Release date 2023/08/11
  • YP 4.0.12 build date 2023/08/07
  • YP 4.0.12 Release date 2023/08/18
  • YP 4.2.3 build date 2023/08/28
  • YP 4.2.3 Release date 2023/09/08
  • YP 3.1.28 build date 2023/09/18
  • YP 3.1.28 Release date 2023/09/29
  • YP 4.0.13 build date 2023/09/25
  • YP 4.0.13 Release date 2023/10/06
  • YP 3.1.29 build date 2023/10/30
  • YP 3.1.29 Release date 2023/11/10
  • YP 4.0.14 build date 2023/11/06
  • YP 4.0.14 Release date 2023/11/17
  • YP 4.2.4 build date 2023/11/13
  • YP 4.2.4 Release date 2023/11/24
  • YP 3.1.30 build date 2023/12/11
  • YP 3.1.30 Release date 2023/12/22
  • YP 4.0.15 build date 2023/12/18
  • YP 4.0.15 Release date 2023/12/29

Tracking Metrics:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC

Archives