== Yocto Project Weekly Status | == Yocto Project Weekly Status Sept. 7, 2021 == | ||
Current Dev Position: YP 3.4 | Current Dev Position: YP 3.4 M4<br/> | ||
Next Deadline: | Next Deadline: 4th Oct. 2021 YP 3.4 M4 build<br/> | ||
'''Next Team Meetings:'''<br/> | '''Next Team Meetings:'''<br/> | ||
*Bug Triage meeting Thursday Sept. | *Bug Triage meeting Thursday Sept. 9th at 7:30am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09) | ||
*Monthly Project Meeting Tuesday Sept. 7th at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09) | *Monthly Project Meeting Tuesday Sept. 7th at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09) | ||
*Weekly Engineering Sync Tuesday | *Weekly Engineering Sync Tuesday Sept. 14th at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09) | ||
*Twitch - See https://www.twitch.tv/theyoctojester | *Twitch - See https://www.twitch.tv/theyoctojester | ||
'''Key Status/Updates:'''<br/> | '''Key Status/Updates:'''<br/> | ||
* | *YP 3.4 M3 is built and now in QA. This means we are now feature complete for 3.4 and will be working on stabilization. | ||
* | *YP 3.3.3 has been built and is waiting in the queue for QA after 3.4 M3. This includes the override syntax compatibility changes. | ||
* | *SBOM generation work was merged in and will be in the release as preliminary work on this topic, there will likely be some further tweaks during M4. | ||
* | *Further rust issues were resolved such as the centos7 build issues. | ||
* | *A work around for the glibc 2.34 clone3 syscalls in uninative was added and a new uninative built/released. | ||
*A fix for some of the multiconfig issues where deadlocked tasks and tasks were showing errors being on both the “covered and not covered lists” is available in master-next for review, hopefully addressing the issues that were being reported. This was possible from a better test case that was submitted enabling debugging. | |||
*Intermittent issues are ongoing and help is very much welcome on these issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT | *Intermittent issues are ongoing and help is very much welcome on these issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT | ||
Line 23: | Line 24: | ||
'''YP 3.4 Milestone Dates:'''<br/> | '''YP 3.4 Milestone Dates:'''<br/> | ||
*YP 3.4 M3 | *YP 3.4 M3 built and in QA | ||
*YP 3.4 M3 Release date 2021/09/03 | *YP 3.4 M3 Release date 2021/09/03 | ||
*YP 3.4 M4 build date 2021/10/04 | *YP 3.4 M4 build date 2021/10/04 | ||
Line 29: | Line 30: | ||
'''Planned upcoming dot releases:'''<br/> | '''Planned upcoming dot releases:'''<br/> | ||
*YP 3.3.3 built and in QA | |||
*YP 3.3.3 release date 2021/10/1 | |||
*YP 3.1.11 build date 2021/09/13 | *YP 3.1.11 build date 2021/09/13 | ||
*YP 3.1.11 release date 2021/9/24 | *YP 3.1.11 release date 2021/9/24 | ||
'''Tracking Metrics:'''<br/> | '''Tracking Metrics:'''<br/> | ||
*WDD | *WDD 2673 (last week 2633) (https://wiki.yoctoproject.org/charts/combo.html) | ||
*Poky Patch Metrics | *Poky Patch Metrics | ||
**Total patches found: | **Total patches found: 1303 (last week 1301) | ||
**Patches in the Pending State: 482 (37%) [last week | **Patches in the Pending State: 482 (37%) [last week 482 (37%)] | ||
'''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/> | '''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/> |
Revision as of 14:40, 7 September 2021
Yocto Project Weekly Status Sept. 7, 2021
Current Dev Position: YP 3.4 M4
Next Deadline: 4th Oct. 2021 YP 3.4 M4 build
Next Team Meetings:
- Bug Triage meeting Thursday Sept. 9th at 7:30am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
- Monthly Project Meeting Tuesday Sept. 7th at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
- Weekly Engineering Sync Tuesday Sept. 14th at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
- Twitch - See https://www.twitch.tv/theyoctojester
Key Status/Updates:
- YP 3.4 M3 is built and now in QA. This means we are now feature complete for 3.4 and will be working on stabilization.
- YP 3.3.3 has been built and is waiting in the queue for QA after 3.4 M3. This includes the override syntax compatibility changes.
- SBOM generation work was merged in and will be in the release as preliminary work on this topic, there will likely be some further tweaks during M4.
- Further rust issues were resolved such as the centos7 build issues.
- A work around for the glibc 2.34 clone3 syscalls in uninative was added and a new uninative built/released.
- A fix for some of the multiconfig issues where deadlocked tasks and tasks were showing errors being on both the “covered and not covered lists” is available in master-next for review, hopefully addressing the issues that were being reported. This was possible from a better test case that was submitted enabling debugging.
- Intermittent issues are ongoing and help is very much welcome on these issues. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT
Ways to contribute:
- There are bugs identified as possible for newcomers to the project: https://wiki.yoctoproject.org/wiki/Newcomers
- There are bugs that are currently unassigned for YP 3.3. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.3_Unassigned_Enhancements.2FBugs
- We’d welcome new maintainers for recipes in OE-Core. Please see the list at: http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/maintainers.inc and discuss with the existing maintainer, or ask on the OE-Core mailing list. We will likely move a chunk of these to “Unassigned” soon to help facilitate this.
YP 3.4 Milestone Dates:
- YP 3.4 M3 built and in QA
- YP 3.4 M3 Release date 2021/09/03
- YP 3.4 M4 build date 2021/10/04
- YP 3.4 M4 Release date 2021/10/29
Planned upcoming dot releases:
- YP 3.3.3 built and in QA
- YP 3.3.3 release date 2021/10/1
- YP 3.1.11 build date 2021/09/13
- YP 3.1.11 release date 2021/9/24
Tracking Metrics:
- WDD 2673 (last week 2633) (https://wiki.yoctoproject.org/charts/combo.html)
- Poky Patch Metrics
- Total patches found: 1303 (last week 1301)
- Patches in the Pending State: 482 (37%) [last week 482 (37%)]
The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC