Weekly Status: Difference between revisions
From Yocto Project
Jump to navigationJump to search
Line 1: | Line 1: | ||
== Yocto Project Weekly Status Jan. | == Yocto Project Weekly Status Jan. 12, 2021 == | ||
Current Dev Position: YP 3.3 M2 development<br/> | Current Dev Position: YP 3.3 M2 development<br/> | ||
Next Deadline: 18th January 2021 YP 3.3 M2 build<br/> | Next Deadline: 18th January 2021 YP 3.3 M2 build<br/> | ||
'''Next Team Meetings:'''<br/> | '''Next Team Meetings:'''<br/> | ||
*Bug Triage meeting Thursday Jan. | *Bug Triage meeting Thursday Jan. 14th at 7:30am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09) | ||
*Monthly Project Meeting Tuesday | *Monthly Project Meeting Tuesday Feb. 2nd at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09) | ||
*Weekly Engineering Sync Tuesday Jan. 12th at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09) | *Weekly Engineering Sync Tuesday Jan. 12th at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09) | ||
*Twitch - See https://www.twitch.tv/theyoctojester | *Twitch - See https://www.twitch.tv/theyoctojester | ||
Line 26: | Line 26: | ||
'''YP 3.3 Milestone Dates:'''<br/> | '''YP 3.3 Milestone Dates:'''<br/> | ||
*YP 3.3 M2 build date 2021/01/18 | *YP 3.3 M2 build date 2021/01/18 | ||
*YP 3.3 M2 Release date 2021/01/29 | *YP 3.3 M2 Release date 2021/01/29 | ||
Line 35: | Line 34: | ||
'''Planned upcoming dot releases:'''<br/> | '''Planned upcoming dot releases:'''<br/> | ||
*YP 3.1.5 build date 2021/01/11 | *YP 3.1.5 build date 2021/01/11 | ||
*YP 3.1.5 release date 2021/01/22 | *YP 3.1.5 release date 2021/01/22 | ||
Line 46: | Line 44: | ||
'''Tracking Metrics:'''<br/> | '''Tracking Metrics:'''<br/> | ||
*WDD | *WDD 2587 (last week 2598) (https://wiki.yoctoproject.org/charts/combo.html) | ||
*Poky Patch Metrics | *Poky Patch Metrics | ||
**Total patches found: | **Total patches found: 1298 (last week 1311) | ||
**Patches in the Pending State: | **Patches in the Pending State: 503 (39%) [last week 507 (39%)] | ||
'''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/> | '''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/> |
Revision as of 15:20, 12 January 2021
Yocto Project Weekly Status Jan. 12, 2021
Current Dev Position: YP 3.3 M2 development
Next Deadline: 18th January 2021 YP 3.3 M2 build
Next Team Meetings:
- Bug Triage meeting Thursday Jan. 14th at 7:30am PDT (https://zoom.us/j/454367603?pwd=ZGxoa2ZXL3FkM3Y0bFd5aVpHVVZ6dz09)
- Monthly Project Meeting Tuesday Feb. 2nd at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
- Weekly Engineering Sync Tuesday Jan. 12th at 8am PDT (https://zoom.us/j/990892712?pwd=cHU1MjhoM2x6ck81bkcrYjRrcmJsUT09)
- Twitch - See https://www.twitch.tv/theyoctojester
Key Status/Updates:
- YP 3.2.1 and YP 3.3 M1 were released
- Patches for 3.3 M2 development are being tested and merged. We have two weeks before M2 is due to be built.
- Many version upgrades have been merged and the project has worked closely with the upcoming autoconf and ppp releases to reduce our patch deficit and ensure we’re ready for them.
- We have seen a number of reproducibility failures from the increased test coverage on the autobuilder, several of the issues have had fixes.
- We are now tracking intermittent ptest failures and a number of bugs have been opened for these, we don’t as yet have people able to work on them though.
- CVE metrics have trended slowly downwards, thanks to everyone sending patches and quietly improving things either through patches or better CVE definitions upstream.
- Intermittent autobuilder issues continue to occur. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT
- The LTS release has changed documentation format from docbook over to sphinx to match master as it should be more maintainable and consistent with the project over the planned life of the LTS.
- For the LTS, there is also discussion on whether the wider reproducibility testing should be enabled as recently done in master due to the number of potential issues which may need to be fixed (master isn’t 100% working yet) as well as whether the pseudo path filtering should be backported. Please do give input to discussions on these topics on the mailing lists.
Ways to contribute:
- There are bugs identified as possible for newcomers to the project: https://wiki.yoctoproject.org/wiki/Newcomers
- There are bugs that are currently unassigned for YP 3.3. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.3_Unassigned_Enhancements.2FBugs
- We’d welcome new maintainers for recipes in OE-Core. Please see the list at: http://git.yoctoproject.org/cgit.cgi/poky/tree/meta/conf/distro/include/maintainers.inc and discuss with the existing maintainer, or ask on the OE-Core mailing list. We will likely move a chunk of these to “Unassigned” soon to help facilitate this.
YP 3.3 Milestone Dates:
- YP 3.3 M2 build date 2021/01/18
- YP 3.3 M2 Release date 2021/01/29
- YP 3.3 M3 build date 2021/03/01
- YP 3.3 M3 Release date 2021/03/12
- YP 3.3 M4 build date 2021/04/05
- YP 3.3 M4 Release date 2021/04/30
Planned upcoming dot releases:
- YP 3.1.5 build date 2021/01/11
- YP 3.1.5 release date 2021/01/22
- YP 3.2.2 build date 2021/02/08
- YP 3.2.2 release date 2021/02/19
- YP 3.1.6 build date 2021/02/22
- YP 3.1.6 release date 2021/03/05
- YP 3.1.7 build date 2021/03/22
- YP 3.1.7 release date 2021/04/02
Tracking Metrics:
- WDD 2587 (last week 2598) (https://wiki.yoctoproject.org/charts/combo.html)
- Poky Patch Metrics
- Total patches found: 1298 (last week 1311)
- Patches in the Pending State: 503 (39%) [last week 507 (39%)]
The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC