'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*YP 3.2 rc2 is out of QA, approved by the TSC and should be released imminently.
*YP 3.2 has been released
*Happy 10th Anniversary Yocto Project! Jefro presented a video to celebrate at ELC-E which is available here: https://www.youtube.com/watch?v=nnhD5CRmfOw He is collecting more video clips, quotes and photos to put on a page on the website so please send them over to him, it was great to see people past and present from the project.
*Master has now opened up for 3.3 development. Unfortunately there have been a lot of issues showing up with some of the more adventurous patches being proposed, the issues are being worked through.
*The Yocto Project Summit was a success, thanks to everyone who helped organise or participated.
Intermittent autobuilder issues continue to occur. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT
*Unfortunately, intermittent autobuilder issues continue to occur. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT
*A YP 3.3 planning document has been created for ideas about what may happen in the YP 3.3 release (assuming there are people to work on the items):
*A YP 3.3 planning document has been created for ideas about what may happen in the YP 3.3 release (assuming there are people to work on the items):
https://docs.google.com/document/d/1IHiE0NU0XspDocgxZeLQ_W7o-yr0nVeBjbqImQUtH5A/edit Request edit/suggest access if you want to add to it.
https://docs.google.com/document/d/1IHiE0NU0XspDocgxZeLQ_W7o-yr0nVeBjbqImQUtH5A/edit Request edit/suggest access if you want to add to it.
*YP 3.3 dates for builds, milestones and release have been added below.
YP 3.3 dates for builds, milestones and release have been added below.
*Development for 3.3 has started and various queued recipe upgrades and other changes have merged to master.
*Anuj Mittal has kindly agreed to maintain the YP 3.2 series (gatesgarth), thanks!
*The SWAT team has been re-established. A new mailing has been created as swat@lists.yoctoproject.org to support this and a number of member organisations have agreed to help staff this team. We are in the process of getting the process running again and in due course there will be the option of other community members being able to help too. The tools and processes are under review to allow us to optimise the process. Thanks to the members and everyone participating to make this happen!


'''Ways to contribute:'''<br/>
'''Ways to contribute:'''<br/>

Revision as of 15:42, 10 November 2020

Yocto Project Weekly Status Nov. 10, 2020

Current Dev Position: YP 3.3 M1 development
Next Deadline: 7th December 2020 YP 3.3 M1 build

Next Team Meetings:

Key Status/Updates:

  • YP 3.2 has been released
  • Master has now opened up for 3.3 development. Unfortunately there have been a lot of issues showing up with some of the more adventurous patches being proposed, the issues are being worked through.

Intermittent autobuilder issues continue to occur. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT

  • A YP 3.3 planning document has been created for ideas about what may happen in the YP 3.3 release (assuming there are people to work on the items):

https://docs.google.com/document/d/1IHiE0NU0XspDocgxZeLQ_W7o-yr0nVeBjbqImQUtH5A/edit Request edit/suggest access if you want to add to it. YP 3.3 dates for builds, milestones and release have been added below.

  • Anuj Mittal has kindly agreed to maintain the YP 3.2 series (gatesgarth), thanks!
  • The SWAT team has been re-established. A new mailing has been created as swat@lists.yoctoproject.org to support this and a number of member organisations have agreed to help staff this team. We are in the process of getting the process running again and in due course there will be the option of other community members being able to help too. The tools and processes are under review to allow us to optimise the process. Thanks to the members and everyone participating to make this happen!

Ways to contribute:

YP 3.2 Milestone Dates:

  • YP 3.2 M4 released.

YP 3.3 Milestone Dates:

  • YP 3.3 M1 build date 2020/12/07
  • YP 3.3 M1 Release date 2020/12/18
  • YP 3.3 M2 build date 2021/01/18
  • YP 3.3 M2 Release date 2021/01/29
  • YP 3.3 M3 build date 2021/03/01
  • YP 3.3 M3 Release date 2021/03/12
  • YP 3.3 M4 build date 2021/04/05
  • YP 3.3 M4 Release date 2021/04/30

Planned upcoming dot releases:

  • YP 3.1.4 build date 2020/11/2
  • YP 3.1.4 release date 2020/11/13
  • YP 3.2.1 build date 2020/11/16
  • YP 3.2.1 release date 2020/12/4
  • YP 3.1.5 build date 2021/01/11
  • YP 3.1.5 release date 2021/01/22
  • YP 3.2.2 build date 2021/02/08
  • YP 3.2.2 release date 2021/02/19
  • YP 3.1.6 build date 2021/02/22
  • YP 3.1.6 release date 2021/03/05
  • YP 3.1.7 build date 2021/03/22
  • YP 3.1.7 release date 2021/04/02

Tracking Metrics:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at: