Weekly Status

From Yocto Project
Jump to navigationJump to search

Yocto Project Weekly Status Aug. 18, 2020

Current Dev Position: YP 3.2 M3
Next Deadline: YP 3.2 M3 build date 2020/8/31

Next Team Meetings:

Key Status/Updates:

  • YP 3.2 M2 is out of QA and going through release approval
  • We’re now in M3 which is the last milestone for new feature development for this release
  • YP 3.0.4 is due to be built this week and will be the last point release for zeus as we migrate over to our new LTS policy and cadence.
  • A number of new intermittent autobuilder failures were seen this week and logged in bugzilla including one showing signs of another bitbake lockfile race issue.
  • You can see the rest of the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT Help with any of these would be much appreciated, unfortunately it is proving hard to find anyone interested in helping figure these out and they significantly hamper our testing.
  • One way to help the project is to help us with bugs that are currently unassigned but ideally needed during YP 3.2. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.2_Unassigned_Enhancements.2FBugs
  • Help with any of the recent failed AUH recipe upgrades would also be appreciated.

YP 3.2 Milestone Dates:

  • YP 3.2 M3 build date 2020/8/31
  • YP 3.2 M3 Release date 2020/9/11
  • YP 3.2 M4 build date 2020/10/5
  • YP 3.2 M4 Release date 2020/10/30

Planned upcoming dot releases:

  • YP 3.0.4 is in QA
  • YP 3.1.3 build date 2020/9/14
  • YP 3.1.3 release date 2020/9/25

Tracking Metrics:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC

Archives