Yocto Project Weekly Status June 9, 2020

Current Dev Position: YP 3.2 M1
Next Deadline: YP 3.2 M1 build date 2020/6/16

Next Team Meetings:

Key Status/Updates:

  • YP 2.7.4 was released
  • YP 3.1.1 has been built with two issues being investigated before it enters QA
  • A significant number of upgrades have merged into master and we are up to date with a majority of recipes, particularly due work from Alex, thanks! One which isn’t and is looking slightly more problematic is the qemu upgrade to 5.0.0, help would be welcome there.
  • YP 3.2 M1 is due to build next week so patches for M1 need to be sent for review now in order to make it in.
  • We are struggling with maintainers for some key components of the system/infrastructure such as devtool, wic, buildhistory and patchwork/patchtest. If anyone can help in these areas please contact Richard.
  • There remain a large number of bugs that we’d ideally like to fix in 3.2 M1 (or M2) but they are “unassigned”, there is nobody to work on them. If anyone has time, looking at these bugs would be a great way to help us. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.2_Unassigned_Enhancements.2FBugs

YP 3.2 Milestone Dates:

  • YP 3.2 M1 build date 2020/6/16
  • YP 3.2 M1 Release date 2020/6/26
  • YP 3.2 M2 build date 2020/7/27
  • YP 3.2 M2 Release date 2020/8/7
  • YP 3.2 M3 build date 2020/8/31
  • YP 3.2 M3 Release date 2020/9/11
  • YP 3.2 M4 build date 2020/10/5
  • YP 3.2 M4 Release date 2020/10/30

Planned upcoming dot releases:

  • YP 2.7.4 has been released
  • YP 3.1.1 build date 2020/6/09
  • YP 3.1.1 release date 2020/6/20
  • YP 3.0.4 build date 2020/8/10
  • YP 3.0.4 release date 2020/8/21
  • YP 3.1.2 build date 2020/9/14
  • YP 3.1.2 release date 2020/9/25