Weekly Status
From Yocto Project
Jump to navigationJump to search
Yocto Project Weekly Status April 30, 2019
Current Dev Position: YP 2.7 M4 (2.7 rc2 is in QA)
Next Deadline: YP 2.7 Release Target April 26, 2019
SWAT Team Rotation:
- SWAT lead is currently: Paul
- SWAT team rotation: Paul -> Anuj on May. 3, 2019
- SWAT team rotation: Anuj -> Ross on May. 10, 2019
- https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Next Team Meetings:
- Bug Triage meeting Thursday May 2nd at 7:30am PDT (https://zoom.us/j/454367603)
- YP 2.8 Planning meeting Tuesday May 7th at 8am PDT (https://zoom.us/j/990892712)
Key Status/Updates:
- Stephen is going to be unavailable for several weeks, please refer any queries to Richard
- YP 2.5.3 was released.
- YP 2.7 is out of QA but pending answers to some questions on the QA report and the final pieces of release process.
- Huge kudos this week go to Armin for work on test automation of some of the manual tests
- We’ve merged ltp test automation which is now being run automatically on the autobuilder on a-full builds.
- Master continues to take patches, somewhat slowed by host specific build issues with vte-native
- WDD, our bug tracking metric is high and there are few people helping with bugs.
- The 2.8 planning discussions are starting and there is a google doc summarising the discussions so far: https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJGXbU/
- If people are planning to work on specific things in 2.8 please let us know so we can incorporate this into our plans. If you’re interested in working on anything in the document, please also let us know or talk with us in one of the planning meetings.
- We have a new “newcomer” bug category which are bugs suited to someone new to the project. These can be seen here: https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
Planned Releases for YP 2.7:
- YP 2.7 M4 Cutoff was Apr. 1, 2019
- YP 2.7 M4 Release Target is Apr. 26, 2019
Planned upcoming dot releases:
- YP 2.6.3 (Thud) is in planning
Tracking Metrics:
- WDD 2593 (last week 2598) (https://wiki.yoctoproject.org/charts/combo.html)
- Poky Patch Metrics
- Total patches found: 1565 (last week 1553)
- Patches in the Pending State: 655 (42%) [last week 654 (42%)]
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features