Yocto Project 2.2 Release Test Plan

From Yocto Project
Jump to navigationJump to search

Reversion history

Version Modifier Comments
1.0 Jose Perez Carranza First draft

Introduction

This article is the overall test plan for version 2.2 of the Yocto Project, for all the generic information this document will be pointing QA Master Test Plan

Objectives

QA_Master_Test_Plan#Objectives_and_Tasks

Test Strategy

Is followed the general strategy defined on QA_Master_Test_Plan#Testing_Strategy and below is showed specific information applicable only for 2.2 Release

Owned features

As QA team we are also in charge for some features to implemetn/verify

To Verify 2.2_qa_owned_features_to_verify

To Implement 2.2_qa_owned_features

Bugs to Verify

Bugs that need verification form QA team 2.2_qa_owned_bugs

Test Items

ADT

BSP

CROPS

Eclipse-Plugin

Meta-Yocto

Toaster

  • []
  • []

eSDK

OE-CORE / Bitbake

Automated Build Test / Distro


Runtime (Compliance)

Build Apliance

pTest

  • []

SWUpd (Software Updater)

  • []
COMPONENT TEMPLATES
ADT
BSP
CROPS
Eclipse-Plugin
Meta-Yocto
Toaster
eSDK
OE-CORE / Bitbake
Distro Testing
Runtime (Compliance)
Build Apliance
pTest
SWUpd (Software Updater)

Features to be tested

All component to be tested on 2.2 are in #Test Items a detailed list of features per component can be found in Test Plan of the components QA_Master_Test_Plan#Component

Pass / Fail Criteria

This criteria is defined in Yocto_Project_v2.2_Status#Yocto_Project_v2.2_Release_Criteria

Exit Criteria

As defined in QA_Master_Test_Plan#Entry and Exit Criteria

Test Deliverables

Test Environment

There are different environments and tools for every type of testing refer to QA_Master_Test_Plan#Test_Areas for more detailed information.

Schedule

The planed schedule for 2.2 can be found at Yocto_2.2_Schedule

Live Schedule

MILESTONE STARTED FINISHED
M1
M2
M3
M4

Execution History

MILESTONE REPORT
M1
M2
M3
M4