Yocto Project Weekly Status July 14, 2020

Current Dev Position: YP 3.2 M2
Next Deadline: YP 3.2 M2 build date 2020/7/27

Next Team Meetings:

Key Status/Updates:

  • A key autobuilder race has been identified as a race around the bitbake lock file which will hopefully continue to reduce the number of intermittent failures being seen. It potentially explains a number of the open bugs. You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT
  • We are struggling with maintainers for some key components of the system/infrastructure such as devtool, wic, buildhistory and patchwork/patchtest. If anyone can help in these areas please contact Richard.
  • Another way to help the project is to help us with bugs that are currently unassigned but ideally needed during 3.2. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.2_Unassigned_Enhancements.2FBugs
  • We’re planning to migrate the project documentation from docbook to sphinx. If you’re interested/able to help with this please join the discussion over on the docs mailing list.

YP 3.2 Milestone Dates:

  • YP 3.2 M2 build date 2020/7/27
  • YP 3.2 M2 Release date 2020/8/7
  • YP 3.2 M3 build date 2020/8/31
  • YP 3.2 M3 Release date 2020/9/11
  • YP 3.2 M4 build date 2020/10/5
  • YP 3.2 M4 Release date 2020/10/30

Planned upcoming dot releases:

  • YP 3.0.4 build date 2020/8/10
  • YP 3.0.4 release date 2020/8/21
  • YP 3.1.2 build date 2020/9/14
  • YP 3.1.2 release date 2020/9/25