Yocto Project Weekly Status June 4, 2019

Current Dev Position: YP 2.8 M1
Next Deadline: YP 2.8 Milestone 1 Cutoff June 9th, 2019

SWAT Team Rotation:

Next Team Meetings:

Key Status/Updates:

  • 2.8 M1 is nearly upon us with just under a week left for the remaining features/patches.
  • Stephen continues to be unavailable, please refer any queries to Richard
  • Mailing lists are moving to groups.io instead of our current mailman setup. This shouldn’t impact users directly, more details will be sent to the mailing lists before the transfer. THe Yocto Project lists will move first, followed by OE, likely a week later.
  • We have a new “newcomer” bug category which are bugs suited to someone new to the project. These can be seen here: https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
  • Uninative 2.5 was released which supports gcc 9. This should fix issues for fedora 30 builds and allow the bringup of fedora 30 workers in the autobuilder too.
  • ARM native builds are now working on the autobuilder as well as KVM accelerated ARM ptest and ltp testing.
  • There are ongoing concerns about perl module dependencies. Tim and Richard have applied bandaids to solve some ptest issues but we really need work in this area if there are any perl experts interested.
  • Many further ptests fixes have merged, thanks to all for the contributions.

Planned Releases for YP 2.8:

  • M1 Cutoff June 9th
  • M1 Release June 21st
  • M2 Cutoff 14th July
  • M2 Release 26th July
  • M3 Cutoff (Feature Freeze) 25th Aug
  • M3 Release 6th Sept
  • M4 Cutoff 30th Sept
  • 2.8 (M4) Final Release 25th Oct


Planned upcoming dot releases:

  • YP 2.6.3 (Thud) is in planning
  • YP 2.7.1 (Warrior) is in planning

Tracking Metrics:

Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features

Archives