Yocto Project v1.2 Status

From Yocto Project
Jump to navigationJump to search

Yocto Project 1.2 release Status

Feature/Task Board

Scheduled Design Design Review Development Patch Review Testing Done Blocked
1691[1], M3, Shane, 5 822[2], M3, Joshua, 3 1625 [3], M3, Josh, 4 1582[4], M3, Joshua, 11 1555[5], M3, Lianhao, 8 1126[6], M2, Lianhao, 7 1461[7], M1, Beth, 0 1598[8], M3, Paul, 3
1581[9], M3, Shane, 5 1567[10], M3, Yi, 11 1655[11], M3, Xiaofeng, 7 1556[12], M2, Lianhao, 7 1580[13], M1, Jessica, 0
1303[14], M3, Dongxiao, 5 1643[15], M3, Bruce, 8 1590[16], M3, Wenzhong, 7 1628[17], M3, Beth, 5 1627[18], M1, Beth, 0
1729[19], M3, Dongxiao, 5 1678[20], M3, Tom, 7 1589[21], M3, Liezhi, 7 1871[22], M3, Dongxiao, 4 1564[23], M1, Dongxiao, 0
1730[24], M3, Dongxiao, 5 1654[25], M3, Paul, 6 1656[26], M3, Kai, 3 1573[27], M3, Shane, 4 1644[28], M1, Bruce, 0
1563[29], M3, Dongxiao, 5 1595[30], M3, Jiajun, 7 1735[31], M3, Dexuan, 3 1873[32], M3, Edwin, 1 1742[33], M1, Dongxiao, 0
1788[34], M3, Dongxiao, 5 1629[35], M4, Beth, 7 1753[36], M3, Shane, 1 1743[37], M1, Dongxiao, 0
1737[38], M3, Dexuan, 5 1675[39], M3, Xiaofeng, 5 1745[40], M1, Dongxiao, 0
1763[41], M3, Saul, 5 1778[42], M3, Beth, 5 1747[43], M1, Dongxiao, 0
1584[44], M3, Jiajun, 5 1679[45], M3, Bruce, (k-tree) 1732[46], M1, Dexuan, 0
1649[47], M3, Daren, 5 1644[48], M3, Bruce, 5 1660[49], M1, Tom, 0
718[50], M3, Xiaofeng, 5 1543[51], M3, ScottG, 4 1661[52], M1, Tom, 0
1551[53], M3, Tom, 5 1145[54], M3, ScottG, 4 1751[55], M1, Shane, 0
1633[56], M3, Tom, 5 1277[57], M3, Shane, 4 1565[58], M1, Paul, 0
1890[59], M3, Paul, 5 1738[60], M3, Dexuan, 3 1546[61], M1, Beth, 0
1606[62], M3, Paul, 5 1960[63], M3, Dongxiao, 3 1603[64], M1, Wenzhong, 0
1682[65], M3, Liezhi, 5 1837[66], M3, Shane, 1 1568[67], M1, Jiajun, 0
1893[68], M3, Liezhi, 5 1731[69], M3, Dongxiao, 1 1776[70], M1, Beth, 0
1894[71], M3, Liezhi, 5 1806[72], M3, Dexuan, 1 1642[73], M2, Darren, 0
1561[74], M3, Kai, 5 1611[75], M3, Lianhao, 1 1647[76], M2, Daren, 0
1741[77], M3, Kai, 5 1744[78], M2, Shane, 0
1502[79], M3, Josh, 5 1748[80], M2, Shane, 0
1610[81], M3, Jessica, 5 1566[82], M2, Paul, 0
1736[83], M3, Edwin, 5 1847[84], M2, Liming, 0
1645[85], M3, Darren, 5 1734[86]1734, M2, Edwin, 0
1272, M2, Dongxiao, 0
1572, M2, Dongxiao, 0
1750, M2, Dongxiao, 0
1752, M2, Dongxiao, 0
1775, M2, Dongxiao, 0
1787, M2, Dongxiao, 0
1792, M2, Dongxiao, 0
1872, M2, Dongxiao, 0
1674, M1, Xiaofeng, 0
1608, M2, Josh, 0
1651, M2, Leizhi, 0
1809, M2, Belen, 0
1573, M3, Shane, 0
1241, M2, Shane, 0
1127, M3, ScottG, 0
1805, M2, Jessica, 0
1638, M2, Bruce, 0
1008, M1, ScottG, 0
542, M3, Richard, 0
1540, M3, Richard, 0
1141, M3, Paul, 0
1143, M3, Paul, 0
1749, M3, Dongxiao, 0
1630, M3, Tom, 0
1620, M3, Nitin, 0
1636, M3, Darren, 0
1764, M3, Belen, 0
717, M3, Josh, 0
1740, M3, Kai, 0
37, M3, Edwin, 0

Note: Each column lists "Feature #, Target Milestone, Owner, # of weeks in this stage".

Project Dashboard

Feature-burndown12.png



Yocto Project SWAT team

Chairperson of the current week: Jiajun Xu [jiajun.xu@intel.com]

Please see here for the details of the SWAT team: https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Yocto Project 1.2 Release Criteria

Milestone 1

Release Criteria Milestone 1 Target Milestone 1 Status
Functional Completion All P1 features are completed. Feature-burndown12-M1.png
See https://wiki.yoctoproject.org/wiki/Yocto_1.2_Schedule for details.
Build and Release (Yocto) All completed features can be built with no errors. Complete
Build and Release (BSPs) Core and meta-intel BSPs can be built with no errors. Complete
Open Bugs All bugs have been dispositioned. High issues have been fixed. [87] - new bugs for 1.2.
HIGH priority bugs - high bugs for 1.2
See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend.
Functional Tests 100% of planned tests are executed and results are logged in bugzilla. https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report
Distros Tested Fedora, Ubuntu, Opensuse current version Fedora 15, Opensuse 11.4 and Ubuntu 11.04
BSP Testing 100% of planned tests are executed and results are logged in bugzilla. https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report
Documentation Doc for windows user to deploy a Yocto BSP image on the hardware Complete
Build Performance Try to at least maintain the current performance and improve if possible. M1 improved performance.
Package Update 50% of the target 90%
Upstream Commits Have upstream status updated on 100% of patches (so that we can have a status update) Complete (a little below the target, will do better)
Marketing Deliverables None N/A
Publication Yocto 1.2, Milestone 1 release is announced Complete



Milestone 2

Release Criteria Milestone 2 Target Milestone 2 Status
Functional Completion All P1 features are completed. Feature-burndown12-M2.png
See https://wiki.yoctoproject.org/wiki/Yocto_1.2_Schedule for details.
Build and Release (Yocto) All completed features can be built with no errors. RC1 has been generated and passed full path testing
Build and Release (BSPs) Core BSPs can be built with no errors. All core BSPs have been generated and tested, no major issues.
Open Bugs All bugs have been dispositioned. High issues have been fixed. [88] - new bugs for 1.2.
HIGH priority bugs - high bugs for 1.2
See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend.
Functional Tests 100% of planned tests are executed and results are logged in bugzilla. Complete https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report
Distros Tested Fedora, Ubuntu, Opensuse current version Fedora 16, Opensuse 12.1, Ubuntu 11.10
BSP Testing 100% of planned tests are executed and results are logged in bugzilla. Complete https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report
Documentation None n/a
Build Performance Try to at least maintain the current performance and improve if possible. 20 minutes more for qemux86 sato build compared with M1, no change compared with 1.1 M4.
Package Update about 70% of the target Exceeded
Upstream Commits Have upstream status updated on 100% of patches (so that we can have a status update) 99%
Marketing Deliverables None N/A
Publication Yocto 1.2, Milestone 2 release is announced


Milestone 3

Release Criteria Milestone 3 Target Milestone 3 Status
Functional Completion All P1 features are completed. Feature-burndown12-M3.png
See https://wiki.yoctoproject.org/wiki/Yocto_1.2_Schedule for details. Passed
Build and Release (Yocto) All completed features can be built with no errors. M3 RC1 has been built and passed full pass QA test.
Build and Release (BSPs) Core BSPs can be built with no errors. All core BSPs have been build with no errir
Open Bugs All bugs have been dispositioned. High issues have been fixed. [89] - new bugs for 1.2.
HIGH priority bugs - high bugs for 1.2
See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend.
Functional Tests 100% of planned tests are executed and results are logged in bugzilla. https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report
Distros Tested Fedora, Ubuntu, Opensuse current version Fedora 16, Opensuse 12.1, Ubuntu 11.10, Centos 6.2/5.7
BSP Testing 100% of planned tests are executed and results are logged in bugzilla. https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report
Documentation None
Build Performance Try to at least maintain the current performance and improve if possible. Stays the same with
Package Update about 70% of the target Exceeded
Upstream Commits Have upstream status updated on 100% of patches (so that we can have a status update)
Marketing Deliverables None N/A
Publication Yocto 1.2, Milestone 3 release is announced