Yocto Project v1.2 Status
From Yocto Project
Jump to navigationJump to search
Yocto Project 1.2 release Status
Feature/Task Board
Design | Design Review | Development | Patch Review | Testing | Done |
1634 [1], Bruce, 1 | 1644[2], Bruce, 1 | 1564[3], Dongxiao, 1 | |||
1580[4], Jessica, 1 | 1008[5], ScottG, 1 | ||||
1582[6], Joshua, 1 | |||||
1603[7], Kai, 1 | |||||
1589[8], Robert, 1 | |||||
1598[9], Paul, 1 | |||||
1567[10], Yi, 1 |
Note: Each column lists "Feature #, Owner, # of weeks in this stage".
Feature/Task Effort Burndown Chart
Yocto Project 1.2 Release Criteria
Milestone 1
Release Criteria | Milestone 1 Target | Milestone 1 Status |
Functional Completion | All P1 features are completed. | See https://wiki.yoctoproject.org/wiki/Yocto_1.2_Schedule for details. |
Build and Release (Yocto) | All completed features can be built with no errors. | |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | [11] - new bugs for 1.2. HIGH priority bugs - high bugs for 1.2 See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse current version | |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report |
Documentation | Doc for windows user to deploy a Yocto BSP image on the hardware | |
Build Performance | Try to at least maintain the current performance and improve if possible. | |
Package Update | TBD | |
Upstream Commits | Have upstream status updated on 90% of patches (so that we can have a status update) | Complete |
Marketing Deliverables | None | N/A |
Publication | Yocto 1.2, Milestone 1 release is announced |