== Yocto Project Weekly Status May 7, 2019 ==
== Yocto Project Weekly Status May 14, 2019 ==
Current Dev Position: YP 2.8 M1<br/>
Current Dev Position: YP 2.8 M1<br/>
Next Deadline: YP 2.8 Milestone 1 Target May ??, 2019<br/>
Next Deadline: YP 2.8 Milestone 1 Cutoff June 9th, 2019<br/>


'''SWAT Team Rotation:'''<br/>
'''SWAT Team Rotation:'''<br/>


*SWAT lead is currently: Anuj
*SWAT lead is currently: Amanda
*SWAT team rotation: Anuj -> Ross on May. 10, 2019
*SWAT team rotation: Amanda -> Ross on May. 17, 2019
*SWAT team rotation: Ross -> Amanda on May. 17, 2019
*SWAT team rotation: Ross -> Chen on May. 24, 2019
*https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
*https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*YP 2.8 Planning meeting Tuesday May 7th at 8am PDT (https://zoom.us/j/990892712)  
*Bug Triage meeting Thursday May 16th at 7:30am PDT (https://zoom.us/j/454367603)
*Bug Triage meeting Thursday May 9th at 7:30am PDT (https://zoom.us/j/454367603)
*Monthly Project Meeting Tuesday June 4th at 8am PDT (https://zoom.us/j/990892712)  




'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*Stephen is going to be unavailable for several weeks, please refer any queries to Richard
*Stephen is going to be unavailable for several weeks, please refer any queries to Richard
*YP 2.7 was released
*The final 2.8 planning meeting was held. The google doc summarising the discussions so far: https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJGXbU/
*The 2.8 planning discussions are starting and there is a google doc summarising the discussions so far: https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJGXbU/
*If people are planning to work on specific things in 2.8 please let us know so we can incorporate this into our plans. If you’re interested in working on anything in the document, please also let us know or talk with us in one of the planning meetings.
*If people are planning to work on specific things in 2.8 please let us know so we can incorporate this into our plans. If you’re interested in working on anything in the document, please also let us know or talk with us in one of the planning meetings.
*At this point we believe we’ve made our final release for the sumo (2.5) series
*Most items planned to be worked upon should now be in the bugzilla with appropriately detailed entries there.
*The project is planning to adopt SPDX license headers in its source code where practical, bitbake has had these merged as a first step.
*The project is planning to adopt SPDX license headers in its source code where practical, OE-Core now has the markup on its scripts too.
*Mailing lists are moving to groups.io instead of our current mailman setup on 27th May. This shouldn’t impact users directly, more details will be sent to the mailing lists in due course.
*We have a new “newcomer” bug category which are bugs suited to someone new to the project. These can be seen here: https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
*We have a new “newcomer” bug category which are bugs suited to someone new to the project. These can be seen here: https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
*We’re about ready to switch over to gcc 9 by default with one more issue needing to be resolved on mips.
*We’re likely going to change the tuning of qemux86 to something more modern
*We’re likely to drop openssl 1.0 and irda from OE-Core imminently


'''Planned Releases for YP 2.8:'''<br/>
'''Planned Releases for YP 2.8:'''<br/>
*TBA
*M1 Cutoff June 9th
*M1 Release June 21st
*M2 Cutoff 14th July
*M2 Release 26th July
*M3 Cutoff (Feature Freeze) 25th Aug
*M3 Release 6th Sept
*M4 Cutoff 30th Sept
*2.8 (M4) Final Release 25th Oct
 


'''Planned upcoming dot releases:'''<br/>
'''Planned upcoming dot releases:'''<br/>
Line 32: Line 43:


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2602 (last week 2593) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2596 (last week 2602) (https://wiki.yoctoproject.org/charts/combo.html)
*Poky Patch Metrics   
*Poky Patch Metrics   
**Total patches found: 1558 (last week 1565)
**Total patches found: 1560 (last week 1558)
**Patches in the Pending State: 655 (42%) [last week 655 (42%)]
**Patches in the Pending State: 665 (43%) [last week 655 (42%)]


'''Key Status Links for YP:'''<br/>
'''Key Status Links for YP:'''<br/>

Revision as of 16:15, 14 May 2019

Yocto Project Weekly Status May 14, 2019

Current Dev Position: YP 2.8 M1
Next Deadline: YP 2.8 Milestone 1 Cutoff June 9th, 2019

SWAT Team Rotation:

Next Team Meetings:


Key Status/Updates:

  • Stephen is going to be unavailable for several weeks, please refer any queries to Richard
  • The final 2.8 planning meeting was held. The google doc summarising the discussions so far: https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJGXbU/
  • If people are planning to work on specific things in 2.8 please let us know so we can incorporate this into our plans. If you’re interested in working on anything in the document, please also let us know or talk with us in one of the planning meetings.
  • Most items planned to be worked upon should now be in the bugzilla with appropriately detailed entries there.
  • The project is planning to adopt SPDX license headers in its source code where practical, OE-Core now has the markup on its scripts too.
  • Mailing lists are moving to groups.io instead of our current mailman setup on 27th May. This shouldn’t impact users directly, more details will be sent to the mailing lists in due course.
  • We have a new “newcomer” bug category which are bugs suited to someone new to the project. These can be seen here: https://wiki.yoctoproject.org/wiki/Bug_Triage#Newcomer_Bugs
  • We’re about ready to switch over to gcc 9 by default with one more issue needing to be resolved on mips.
  • We’re likely going to change the tuning of qemux86 to something more modern
  • We’re likely to drop openssl 1.0 and irda from OE-Core imminently

Planned Releases for YP 2.8:

  • M1 Cutoff June 9th
  • M1 Release June 21st
  • M2 Cutoff 14th July
  • M2 Release 26th July
  • M3 Cutoff (Feature Freeze) 25th Aug
  • M3 Release 6th Sept
  • M4 Cutoff 30th Sept
  • 2.8 (M4) Final Release 25th Oct


Planned upcoming dot releases:

  • YP 2.6.3 (Thud) is in planning
  • YP 2.7.1 (Warrior) is in planning

Tracking Metrics:

Key Status Links for YP: