== Yocto Project Weekly Status Aug. 18, 2020 ==
== Yocto Project Weekly Status Aug. 25, 2020 ==
Current Dev Position: YP 3.2 M3<br/>
Current Dev Position: YP 3.2 M3<br/>
Next Deadline: YP 3.2 M3 build date 2020/8/31<br/>
Next Deadline: YP 3.2 M3 build date 2020/8/31<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting Thursday Aug 20th at 7:30am PDT (https://zoom.us/j/454367603)
*Bug Triage meeting Thursday Aug 27th at 7:30am PDT (https://zoom.us/j/454367603)
*Monthly Project Meeting Tuesday Sept. 1st at 8am  PDT (https://zoom.us/j/990892712)
*Monthly Project Meeting Tuesday Sept. 1st at 8am  PDT (https://zoom.us/j/990892712)
*Weekly Engineering Sync Tuesday Aug 18th at 8am PDT (https://zoom.us/j/990892712)
*Weekly Engineering Sync Tuesday Aug 25th at 8am PDT (https://zoom.us/j/990892712)
*Twitch -  See https://www.twitch.tv/theyoctojester
*Twitch -  See https://www.twitch.tv/theyoctojester


Line 26: Line 26:


'''Planned upcoming dot releases:'''<br/>
'''Planned upcoming dot releases:'''<br/>
*YP 3.0.4 is in QA
*YP 3.0.4 is ireleased
*YP 3.1.3 build date 2020/9/14
*YP 3.1.3 build date 2020/9/14
*YP 3.1.3 release date 2020/9/25
*YP 3.1.3 release date 2020/9/25


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2429 (last week 2404) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2424 (last week 2429) (https://wiki.yoctoproject.org/charts/combo.html)
*Poky Patch Metrics   
*Poky Patch Metrics   
**Total patches found: 1271 (last week 1280)
**Total patches found: 1273 (last week 1271)
**Patches in the Pending State: 495 (39%) [last week 500 (39%)]
**Patches in the Pending State: 502 (39%) [last week 495 (39%)]


'''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/>
'''The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:'''<br/>

Revision as of 14:29, 25 August 2020

Yocto Project Weekly Status Aug. 25, 2020

Current Dev Position: YP 3.2 M3
Next Deadline: YP 3.2 M3 build date 2020/8/31

Next Team Meetings:

Key Status/Updates:

  • YP 3.0.4 is going through QA at this time
  • YP 3.2 M2 was released
  • We’ve had a sharp increase in the autobuilder intermittent bugs
  • You can see the list of failures we’re continuing to see by searching for the “AB-INT” tag in bugzilla: https://bugzilla.yoctoproject.org/buglist.cgi?quicksearch=AB-INT Help with any of these would be much appreciated, unfortunately it is proving hard to find anyone interested in helping figure these out and they significantly hamper our testing.
  • One way to help the project is to help us with bugs that are currently unassigned but ideally needed during YP 3.2. See: https://wiki.yoctoproject.org/wiki/Bug_Triage#Medium.2B_3.2_Unassigned_Enhancements.2FBugs
  • Help with any of the recent failed AUH recipe upgrades would also be appreciated. We’d also like to remind recipe maintainers to submit the successful upgrades.
  • We are trying to drop the fcommon/fno-common hacks from gcc however there are still a number of failures it triggers, particularly in perf. Khem has done great work in fixing many of the issues already.
  • Improved shell backtracing capability was added to bitbake, thanks Chris.

YP 3.2 Milestone Dates:

  • YP 3.2 M3 build date 2020/8/31
  • YP 3.2 M3 Release date 2020/9/11
  • YP 3.2 M4 build date 2020/10/5
  • YP 3.2 M4 Release date 2020/10/30

Planned upcoming dot releases:

  • YP 3.0.4 is ireleased
  • YP 3.1.3 build date 2020/9/14
  • YP 3.1.3 release date 2020/9/25

Tracking Metrics:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC

Archives