= Feature/Task Board = | = Feature/Task Board = | ||
{|border="1" {{table}} | {|border="1" {{table}} | ||
| align="center" style="background:#f0f0f0;"|''' | | align="center" style="background:#f0f0f0;"|'''Desing''' | ||
| align="center" style="background:#f0f0f0;"|'''Design Review''' | | align="center" style="background:#f0f0f0;"|'''Design Review''' | ||
| align="center" style="background:#f0f0f0;"|'''Development''' | | align="center" style="background:#f0f0f0;"|'''Development''' | ||
Line 9: | Line 9: | ||
| align="center" style="background:#f0f0f0;"|'''Testing''' | | align="center" style="background:#f0f0f0;"|'''Testing''' | ||
| align="center" style="background:#f0f0f0;"|'''Done''' | | align="center" style="background:#f0f0f0;"|'''Done''' | ||
| align="center" style="background:#ff0000;"|'''Blocked''' | |||
|- | |- | ||
| 1634 | | 1634, Bruce, 1||1644, Bruce, 1||1564, dongxiao, 1|||||||| | ||
|- | |- | ||
| 1580 | | 1580, Jessica, 1||1674, Xiaofeng, 1||1008, ScottG, 1|||||||| | ||
|- | |- | ||
| 1582 | | 1582, Joshua, 1||||1661, Tom, 1|||||||| | ||
|- | |- | ||
| 1603 | | 1603, Kai, 1|||||||||||| | ||
|- | |- | ||
| 1589 | | 1589, Robert, 1|||||||||||| | ||
|- | |- | ||
| 1598 | | 1598, Paul, 1|||||||||||| | ||
|- | |- | ||
| 1567 | | 1635, Darren, 1|||||||||||| | ||
|- | |||
| 1636, Darren, 1|||||||||||| | |||
|- | |||
| 1660, Tom, 1|||||||||||| | |||
|- | |||
| 1567, Yi, 1|||||||||||| | |||
|} | |} | ||
Revision as of 19:05, 9 November 2011
Yocto Project 1.2 release Status
Feature/Task Board
Desing | Design Review | Development | Patch Review | Testing | Done | Blocked |
1634, Bruce, 1 | 1644, Bruce, 1 | 1564, dongxiao, 1 | ||||
1580, Jessica, 1 | 1674, Xiaofeng, 1 | 1008, ScottG, 1 | ||||
1582, Joshua, 1 | 1661, Tom, 1 | |||||
1603, Kai, 1 | ||||||
1589, Robert, 1 | ||||||
1598, Paul, 1 | ||||||
1635, Darren, 1 | ||||||
1636, Darren, 1 | ||||||
1660, Tom, 1 | ||||||
1567, Yi, 1 |
Note: Each column lists "Feature #, Owner, # of weeks in this stage".
Feature/Task Effort Burndown Chart
Yocto Project 1.2 Release Criteria
Milestone 1
Release Criteria | Milestone 1 Target | Milestone 1 Status |
Functional Completion | All P1 features are completed. | See https://wiki.yoctoproject.org/wiki/Yocto_1.2_Schedule for details. |
Build and Release (Yocto) | All completed features can be built with no errors. | |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | [1] - new bugs for 1.2. HIGH priority bugs - high bugs for 1.2 See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse current version | |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report |
Documentation | Doc for windows user to deploy a Yocto BSP image on the hardware | |
Build Performance | Try to at least maintain the current performance and improve if possible. | |
Package Update | TBD | |
Upstream Commits | Have upstream status updated on 100% of patches (so that we can have a status update) | Complete |
Marketing Deliverables | None | N/A |
Publication | Yocto 1.2, Milestone 1 release is announced |