== Yocto Project Weekly Status September 10, 2019 ==
== Yocto Project Weekly Status September 17, 2019 ==
Current Dev Position: YP 2.8 M4 Feature Freeze<br/>
Current Dev Position: YP 2.8 M4 Feature Freeze<br/>
Next Deadline: YP 3.0 Final Release 25th Oct<br/>
Next Deadline: YP 3.0 Final Release 25th Oct<br/>
Line 5: Line 5:
'''SWAT Team Rotation:'''<br/>
'''SWAT Team Rotation:'''<br/>
*SWAT lead is currently: Paul
*SWAT lead is currently: Paul
*SWAT team rotation: Paul -> Ross on Sept. 13, 2019
*SWAT team rotation: Ross -> Amanda on Sept. 20, 2019
*SWAT team rotation: Ross -> Amanda on Sept. 20, 2019
*SWAT team rotation: Amanda -> Chen on Sept. 13, 2019
*://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
*://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting Thursday Sept 12th at 7:30am PDT (https://zoom.us/j/454367603)
*Bug Triage meeting Thursday Sept 19th at 7:30am PDT (https://zoom.us/j/454367603)
*Monthly Project Meeting Tuesday Oct. 1st at 8am PDT (https://zoom.us/j/990892712)
*Monthly Project Meeting Tuesday Oct. 1st at 8am PDT (https://zoom.us/j/990892712)
*Weekly Engineering Sync Tuesday Sept. 10th at 8am PDT (https://zoom.us/j/990892712)
*Weekly Engineering Sync Tuesday Sept. 17th at 8am PDT (https://zoom.us/j/990892712)
*Twitch - Next event is Tuesday Sept. 10th at 8am PDT (https://www.twitch.tv/yocto_project)
*Twitch - Next event is Tuesday Oct. 8th at 8am PDT (https://www.twitch.tv/yocto_project)


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*We’re now in feature freeze for 3.0 and working on bug fixing for final release
*We’re now in feature freeze for 3.0 and working on bug fixing for final release
*We have not built M3 yet as some work still remains for us to be feature complete and ready for QA. This puts us behind schedule but the plan is to complete the key features we’ve planned rather than adhere strictly to dates. We hope to make up time during M4 by having M3 at high quality and take advantage of our automation.
*We have not built M3 yet as there are still three issues that need to be resolved:
*RP is away for the rest of the week which means M3 progress will be limited this week, Ross will queue patches.
**strace ptest regressions with 5.1/5.2 kernels
*Key 3.0 changes have now merged:
**systemd timeouts on mips
**5.2 linux-libc-kernel-headers
**hashequiv server rewrite
**5.2 kernel recipes by default for all reference BSPs
*The strace regressions will be discussed with the kernel community, the best workaround may be to lower the individual test timeouts so one the affected individual tests fail rather than all tests timing out.
**Removal of LSB and poky-lsb and replacement with alt config testing
*The qemumips issue with systemd is puzzling as its happening in hwdb and hwdb should be generated in advance anyway. Investigation is ongoing about why its being regenerated, a workaround is to increase the timeout as mips is just slow (it does complete eventually, its just marginal).
**systemd by default for poky-altcfg
*The hashequiv server changes are being tested in master-next
**Patches have significantly reduced the dependency on python2
It is planned to build M3 this week with the workarounds mentioned above worst case. Its expected there would be further hashequiv fixing during M4.
**Reproducible builds are now being tested for core-image-minimal
*We hope to make up time during M4 by having M3 at high quality and take advantage of our automation.
**Automated toolchain testsuite tests (binutils, gcc, glibc)
*Key blocking issues for M3 that have been fixed:
**Systemtap issues with 5.2 were debugged and patches sent/merged upstream
**5.2 dmesg on qemuarm64 fixed
**qemumips hang when using highmem root caused and worked around (for now)
**mdadm ptest timeout worked around
**quilt and libevent ptest regressions from M2 resolved
*Remaining issues blocking M3:
**systemd boot failure on qemumips
**strace ptest timeout
**Hash equivalence performance problems (RP has a simple idea to ~double speed)
**Hash equivalence bugs
**Toolchain testsuite relocation bugs (Nathan working on it)
*Hash Equivalency status:
**Ideas about removing some dependency information from the hashes to allow faster bulk queries aren’t viable so the current codebase approach is correct
**we need to rework the client/server communication to scale to the autobuilder
**there are some bugs in the code the autobuilder continues to expose
**we have cases where its not 100% clear what the correct behaviour should be
**test cases are proving to be problematic to write in a maintainable way
*Documentation - Due to illness Scott is unavailable for the next month or two so doc patches will be handled by Richard or Ross in the short term. We’ll likely limit them to correctness issues and defer any substantial new text. If anyone has availability and skills to work on the manuals please talk to us. We’re aware there is a patch backlog.
*Documentation - Due to illness Scott is unavailable for the next month or two so doc patches will be handled by Richard or Ross in the short term. We’ll likely limit them to correctness issues and defer any substantial new text. If anyone has availability and skills to work on the manuals please talk to us. We’re aware there is a patch backlog.
*If anyone has any status items for the project they’d like to add to the weekly reports, please email Richard+Stephen.
*If anyone has any status items for the project they’d like to add to the weekly reports, please email Richard+Stephen.
Line 58: Line 39:


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2424 (last week 2413) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2424 (last week 2424) (https://wiki.yoctoproject.org/charts/combo.html)
*Poky Patch Metrics   
*Poky Patch Metrics   
**Total patches found: 1417 (last week 1470)
**Total patches found: 1417 (last week 1417)
**Patches in the Pending State: 582 (41%) [last week 611 (42%)]
**Patches in the Pending State: 582 (41%) [last week 582 (41%)]


'''Key Status Links for YP:'''<br/>
'''Key Status Links for YP:'''<br/>

Revision as of 14:46, 17 September 2019

Yocto Project Weekly Status September 17, 2019

Current Dev Position: YP 2.8 M4 Feature Freeze
Next Deadline: YP 3.0 Final Release 25th Oct

SWAT Team Rotation:

  • SWAT lead is currently: Paul
  • SWAT team rotation: Ross -> Amanda on Sept. 20, 2019
  • SWAT team rotation: Amanda -> Chen on Sept. 13, 2019
    //wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Next Team Meetings:

Key Status/Updates:

  • We’re now in feature freeze for 3.0 and working on bug fixing for final release
  • We have not built M3 yet as there are still three issues that need to be resolved:
    • strace ptest regressions with 5.1/5.2 kernels
    • systemd timeouts on mips
    • hashequiv server rewrite
  • The strace regressions will be discussed with the kernel community, the best workaround may be to lower the individual test timeouts so one the affected individual tests fail rather than all tests timing out.
  • The qemumips issue with systemd is puzzling as its happening in hwdb and hwdb should be generated in advance anyway. Investigation is ongoing about why its being regenerated, a workaround is to increase the timeout as mips is just slow (it does complete eventually, its just marginal).
  • The hashequiv server changes are being tested in master-next

It is planned to build M3 this week with the workarounds mentioned above worst case. Its expected there would be further hashequiv fixing during M4.

  • We hope to make up time during M4 by having M3 at high quality and take advantage of our automation.
  • Documentation - Due to illness Scott is unavailable for the next month or two so doc patches will be handled by Richard or Ross in the short term. We’ll likely limit them to correctness issues and defer any substantial new text. If anyone has availability and skills to work on the manuals please talk to us. We’re aware there is a patch backlog.
  • If anyone has any status items for the project they’d like to add to the weekly reports, please email Richard+Stephen.

Planned Releases for YP 3.0 {2.8}:

  • M3 Release 6th Sept
  • M4 Cutoff 30th Sept - this will be YP 3.0.
  • YP 3.0 {2.8 (M4)} Final Release 25th Oct

Planned upcoming dot releases:

  • YP 2.7.2 (Warrior) is planned for after YP 3.0 release.
  • YP 2.6.4 (Thud) is planned for after YP 2.7.2 release.

Tracking Metrics:

Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule