Yocto Project v1.2 Status: Difference between revisions
From Yocto Project
Jump to navigationJump to search
Line 72: | Line 72: | ||
| Build Performance || Try to at least maintain the current performance and improve if possible. || bgcolor="" | | | Build Performance || Try to at least maintain the current performance and improve if possible. || bgcolor="" | | ||
|- | |- | ||
| Package Update || | | Package Update || 50% of the target || bgcolor="" | | ||
|- | |- | ||
| Upstream Commits || Have upstream status updated on 100% of patches (so that we can have a status update) || bgcolor="" | Complete | | Upstream Commits || Have upstream status updated on 100% of patches (so that we can have a status update) || bgcolor="" | Complete |
Revision as of 21:46, 21 December 2011
Yocto Project 1.2 release Status
Feature/Task Board
Design | Design Review | Development | Patch Review | Testing | Done | Blocked |
1629[1], M2, Beth, 5 | 1634[2], M2, Bruce, 3 | 1582[3], M2, Joshua, 4 | 1674[4], M1, Xiaofeng, 1 | 1461[5], M1, Beth, 0 | ||
1598[6], M2, Paul, 7 | 1764[7], M2, Belen, 5 | 1635[8], M1, Darren, 3 | 1008[9], M1, ScottG, 1 | 1580[10], M1, Jessica, 0 | ||
1636[11], M1, Darren, 4 | 1568[12], M1, Jiajun, 1 | 1627[13], M1, Beth, 0 | ||||
1567[14], M1, Yi, 3 | 1564[15], M1, Dongxiao, 0 | |||||
1644[16], M1, Bruce, 0 | ||||||
1742[17], M1, Dongxiao, 0 | ||||||
1743[18], M1, Dongxiao, 0 | ||||||
1745[19], M1, Dongxiao, 0 | ||||||
1747[20], M1, Dongxiao, 0 | ||||||
1732[21], M1, Dexuan, 0 | ||||||
1660[22], M1, Tom, 0 | ||||||
1661[23], M1, Tom, 0 | ||||||
1751[24], M1, Shane, 0 | ||||||
1565[25], M1, Paul, 0 | ||||||
1546[26], M1, Beth, 0 | ||||||
1603[27], M1, Wenzhong, 0 |
Note: Each column lists "Feature #, Target Milestone, Owner, # of weeks in this stage".
Project Dashboard
Yocto Project 1.2 Release Criteria
Milestone 1
Release Criteria | Milestone 1 Target | Milestone 1 Status |
Functional Completion | All P1 features are completed. | See https://wiki.yoctoproject.org/wiki/Yocto_1.2_Schedule for details. |
Build and Release (Yocto) | All completed features can be built with no errors. | |
Build and Release (BSPs) | Core and meta-intel BSPs can be built with no errors. | |
Open Bugs | All bugs have been dispositioned. High issues have been fixed. | [28] - new bugs for 1.2. HIGH priority bugs - high bugs for 1.2 See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend. |
Functional Tests | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report |
Distros Tested | Fedora, Ubuntu, Opensuse current version | |
BSP Testing | 100% of planned tests are executed and results are logged in bugzilla. | https://wiki.yoctoproject.org/wiki/Yocto_1.2_Milestone_Test_Report |
Documentation | Doc for windows user to deploy a Yocto BSP image on the hardware | |
Build Performance | Try to at least maintain the current performance and improve if possible. | |
Package Update | 50% of the target | |
Upstream Commits | Have upstream status updated on 100% of patches (so that we can have a status update) | Complete |
Marketing Deliverables | None | N/A |
Publication | Yocto 1.2, Milestone 1 release is announced |