== Yocto Project Weekly Status March 17, 2020 ==
== Yocto Project Weekly Status March 17, 2020 ==
Current Dev Position: YP 3.1 M4 - Stabilization <br/>
Current Dev Position: YP 3.1 M4 - Stabilization <br/>
Next Deadline: YP 3.1 M3 is in QA<br/>
Next Deadline: YP 3.1 M4 build date 3/30/2020<br/>


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>

Revision as of 15:09, 17 March 2020

Yocto Project Weekly Status March 17, 2020

Current Dev Position: YP 3.1 M4 - Stabilization
Next Deadline: YP 3.1 M4 build date 3/30/2020

Next Team Meetings:

Key Status/Updates:

  • M3 has now been built and is in QA. We are therefore feature frozen.
  • YP 3.1 has been announced as an LTS release: https://www.yoctoproject.org/yocto-project-long-term-support-announced/
  • There were logging changes merged to better handle hashequiv and usability concerns, thanks Joshua
  • We have seen a welcome rise in green builds recently although several key intermittent failures have not been addressed. It is crucial for an LTS release we do resolve these.
  • Recipe upgrades are now unlikely to be merged into 3.1 as we focus on stabilizing and bug fixing for the final release

Proposed YP 3.1 Milestone Dates

  • YP 3.1 M3 is in QA
  • YP 3.1 M3 release date 3/6/2020
  • YP 3.1 M4 build date 3/30/2020
  • YP 3.1 M4 release date 4/24/2020

Planned upcoming dot releases:

  • YP 3.0.3 build date 5/4/2020
  • YP 3.0.3 release date 5/15/2020
  • YP 2.7.4 build date 5/18/2020
  • YP 2.7.4 release date 5/29/2020

Tracking Metrics:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at: