== Yocto Project Weekly Status November 12, 2019 ==
== Yocto Project Weekly Status November 19, 2019 ==
Current Dev Position: YP 3.1 M1 <br/>
Current Dev Position: YP 3.1 M1 <br/>
Next Deadline: YP 3.1 M1 build Dec. 2, 2019<br/>
Next Deadline: YP 3.1 M1 build Dec. 2, 2019<br/>
'''SWAT Team Rotation:'''<br/>
*SWAT lead is currently: Anuj
*SWAT team rotation: Anuj -> Chen on Nov. 15, 2019
*SWAT team rotation: Chen > Paul on Nov. 22, 2019
*://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team


'''Next Team Meetings:'''<br/>
'''Next Team Meetings:'''<br/>
*Bug Triage meeting Thursday Nov. 14th at 7:30am PDT (https://zoom.us/j/454367603)
*Bug Triage meeting Thursday Nov. 21st at 7:30am PDT (https://zoom.us/j/454367603)
*Monthly Project Meeting Tuesday Dec. 3rd at 8am  PDT (https://zoom.us/j/990892712)
*Monthly Project Meeting Tuesday Dec. 3rd at 8am  PDT (https://zoom.us/j/990892712)
*Weekly Engineering Sync Tuesday Nov. 12th at 8am PDT (https://zoom.us/j/990892712)
*Weekly Engineering Sync Tuesday Nov. 19th at 8am PDT (https://zoom.us/j/990892712)
*Twitch - Next event is Tuesday Nov. 12th at 8am PDT (https://www.twitch.tv/yocto_project)
*Twitch - Next event is Tuesday Dec. 10th at 8am PDT (https://www.twitch.tv/yocto_project)


'''Key Status/Updates:'''<br/>
'''Key Status/Updates:'''<br/>
*YP 2.7.2 is still undergoing QA
*YP 2.7.2 is under review by the TSC and likely to be released.
*There were some key fixes for pseudo related issues which mean it continues to work with modern distros like Fedora 31.
*Tests were made on making reproducibility the default for poky. There were several issues found for which bugs were filed:
*Patches have continued to merge and master is staying roughly current with the pending patch queue but there continue to be recurring build failures that are not being addressed.
**A double free issue in opkg (Alejandro looking into, thanks)
*The YP TSC worked on and shared a proposal on how an LTS release could work which is available at: https://docs.google.com/document/d/1AwAFDf52f_FoXksbHEVUMlu4hpcI0JMGVG-Kj_sUkyc/ . There has been much discussion about this, patience would be appreciated as the TSC and governing board work through this to come up with plans on how we proceed.
**devtool failures (Paul sent a fix, thanks)
**recipetool failures (Richard sent a fix)
*Tests were made on making the hashserver default for poky. There were also several issues found and RP is trying to understand and work through those. At least one critical issue has been identified and due to be tested.
*The SWAT team no longer has enough people on it to make it sustainable and has therefore been disbanded. This means build owners need to triage their own build failures. Richard will be responsible for failures in the scheduled master builds.
*Intermittent build failures continue to hamper builds, particularly combined with the above issues and as few people are available to attempt to debug and resolve them.
*The TSC is working on LTS plans, productive discussions have been had and a new policy on handling this and stable releases should be available in the next couple of weeks.
*We have begun collecting ideas for YP 3.1 in this document: https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjnABc/edit?usp=sharing
*We have begun collecting ideas for YP 3.1 in this document: https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjnABc/edit?usp=sharing
*If anyone has any status items for the project they’d like to add to the weekly reports, please email Richard+Stephen.
*If anyone has any status items for the project they’d like to add to the weekly reports, please email Richard+Stephen.
Line 34: Line 33:


'''Planned upcoming dot releases:'''<br/>
'''Planned upcoming dot releases:'''<br/>
*YP 3.0.1 has patches being queued in poky-contrib
*YP 2.7.2 Should release this week.
*YP 2.7.2 (Warrior) is in QA.
*YP 3.0.1 Proposed build date  11/25/2019
*YP 3.0.1 Proposed release date 12/06/2019
*YP 2.7.3 Proposed build date  2/10/20
*YP 2.7.3 Proposed release date 2/21/20
*YP 3.0.2 Proposed build date  2/3/20
*YP 3.0.2 Proposed release date 2/14/20


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2508 (last week 2518) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2533 (last week 2508) (https://wiki.yoctoproject.org/charts/combo.html)
*Poky Patch Metrics   
*Poky Patch Metrics   
**Total patches found: 1445 (last week 1446)
**Total patches found: 1461 (last week 1445)
**Patches in the Pending State: 579 (40%) [last week 579 (40%)]
**Patches in the Pending State: 579 (40%) [last week 579 (40%)]



Revision as of 15:45, 19 November 2019

Yocto Project Weekly Status November 19, 2019

Current Dev Position: YP 3.1 M1
Next Deadline: YP 3.1 M1 build Dec. 2, 2019

Next Team Meetings:

Key Status/Updates:

  • YP 2.7.2 is under review by the TSC and likely to be released.
  • Tests were made on making reproducibility the default for poky. There were several issues found for which bugs were filed:
    • A double free issue in opkg (Alejandro looking into, thanks)
    • devtool failures (Paul sent a fix, thanks)
    • recipetool failures (Richard sent a fix)
  • Tests were made on making the hashserver default for poky. There were also several issues found and RP is trying to understand and work through those. At least one critical issue has been identified and due to be tested.
  • The SWAT team no longer has enough people on it to make it sustainable and has therefore been disbanded. This means build owners need to triage their own build failures. Richard will be responsible for failures in the scheduled master builds.
  • Intermittent build failures continue to hamper builds, particularly combined with the above issues and as few people are available to attempt to debug and resolve them.
  • The TSC is working on LTS plans, productive discussions have been had and a new policy on handling this and stable releases should be available in the next couple of weeks.
  • We have begun collecting ideas for YP 3.1 in this document: https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjnABc/edit?usp=sharing
  • If anyone has any status items for the project they’d like to add to the weekly reports, please email Richard+Stephen.

Proposed YP 3.1 Milestone Dates

  • YP 3.1 M1 Proposed build date 12/2/2019
  • YP 3.1 M1 Proposed release date 12/13/2019
  • YP 3.1 M2 Proposed build date 1/20/2020
  • YP 3.1 M2 Proposed release date 1/31/2020
  • YP 3.1 M3 Proposed build date 2/24/2020
  • YP 3.1 M3 Proposed release date 3/6/2020
  • YP 3.1 M4 Proposed build date 3/30/2020
  • YP 3.1 M4 Proposed release date 4/24/2020

Planned upcoming dot releases:

  • YP 2.7.2 Should release this week.
  • YP 3.0.1 Proposed build date 11/25/2019
  • YP 3.0.1 Proposed release date 12/06/2019
  • YP 2.7.3 Proposed build date 2/10/20
  • YP 2.7.3 Proposed release date 2/21/20
  • YP 3.0.2 Proposed build date 2/3/20
  • YP 3.0.2 Proposed release date 2/14/20

Tracking Metrics:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC

Archives