Weekly Status: Difference between revisions

From Yocto Project
Jump to navigationJump to search
Line 28: Line 28:


'''Planned Releases for YP 3.0 {2.8}:'''<br/>
'''Planned Releases for YP 3.0 {2.8}:'''<br/>
*M2 is out of QA and being reviewed.
*M2 is released.
*M2 Release 26th July
*M3 Cutoff (Feature Freeze) 25th Aug
*M3 Cutoff (Feature Freeze) 25th Aug
*M3 Release 6th Sept
*M3 Release 6th Sept
Line 36: Line 35:


'''Planned upcoming dot releases:'''<br/>
'''Planned upcoming dot releases:'''<br/>
*YP 2.7.2 (Warrior) is planned for after 2.8 M2  release.
*YP 2.7.2 (Warrior) is planned for after YP 3.0 release.
*YP 2.6.3 (Thud) is in QA.
*YP 2.6.3 (Thud) is out of QA and being readied for release.
*YP 2.6.4 (Thud) is planned for after YP 2.7.2  release.


'''Tracking Metrics:'''<br/>
'''Tracking Metrics:'''<br/>
*WDD 2481 (last week 2466) (https://wiki.yoctoproject.org/charts/combo.html)
*WDD 2482 (last week 2481) (https://wiki.yoctoproject.org/charts/combo.html)
*Poky Patch Metrics   
*Poky Patch Metrics   
**Total patches found: 1496 (last week 1498)
**Total patches found: 1489 (last week 14996)
**Patches in the Pending State: 615 (41%) [last week 619 (41%)]
**Patches in the Pending State: 617 (41%) [last week 615 (41%)]


'''Key Status Links for YP:'''<br/>
'''Key Status Links for YP:'''<br/>

Revision as of 14:50, 13 August 2019

Yocto Project Weekly Status August 13, 2019

Current Dev Position: YP 2.8 M3
Next Deadline: YP 2.8 Milestone M3 Cutoff (Feature Freeze) Aug 25, 2019

SWAT Team Rotation:

  • SWAT lead is currently: Amanda
  • SWAT team rotation: Amanda -> Chen on Aug. 16, 2019
  • SWAT team rotation: Chen -> Armin on Aug. 23, 2019
    //wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Next Team Meetings:

Key Status/Updates:

  • YP 2.6.3 is out of QA and being readied for release.
  • This release which was 2.8 will now become 3.0.
  • The sstate has equivalency work has run into some challenges:
    • performance of the hash server is not able to scale to the autibuilder’s load
    • performance of runqueue has regressed even when not using the hash equivalency code
    • bugfixes in master-next regress performance even further
    • there are bugs being triggered by the has equivalency code that need investigation and resolution (along with test cases creating).

These issues are being worked on but we need to ensure correctness of the new code first before the performance can be fixed

  • There were updates so some key components for bug fixes this week, in particular pseudo.
  • General patch merging is happening and the queue is mostly clear and flowing but it isn’t happening as frequently as usual due to the hash equivalency work.

Planned Releases for YP 3.0 {2.8}:

  • M2 is released.
  • M3 Cutoff (Feature Freeze) 25th Aug
  • M3 Release 6th Sept
  • M4 Cutoff 30th Sept - this will be YP 3.0.
  • YP 3.0 {2.8 (M4)} Final Release 25th Oct

Planned upcoming dot releases:

  • YP 2.7.2 (Warrior) is planned for after YP 3.0 release.
  • YP 2.6.3 (Thud) is out of QA and being readied for release.
  • YP 2.6.4 (Thud) is planned for after YP 2.7.2 release.

Tracking Metrics:

Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features

Archives