Yocto Project Weekly Status April 2, 2019
Current Dev Position: YP 2.7 M4 (New feature Freeze has begun.)
Next Deadline: YP 2.7 M3 Release Target was Mar. 8, 2019
SWAT Team Rotation:
- SWAT lead is currently: Ross
- SWAT team rotation: Ross -> Amanda on Apr. 5, 2019
- SWAT team rotation: Amanda -> Chen on Apr. 12, 2019
- https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Next Team Meetings:
- YP 2.8 Planning meeting Tuesday April 2nd at 8am PDT (https://zoom.us/j/990892712) or see the invite on the mailing list at: (https://lists.yoctoproject.org/pipermail/yocto/2019-April/044654.html)
- Bug Triage meeting Thursday April 4th at 7:30am PDT (https://zoom.us/j/454367603)
Key Status/Updates:
- The QA report for M3 rc1 is available. This is the first time we’ve used the new QA process so we’re still understanding how the new format for the data works out. There are some issues but right now we believe we’ll aim to fix these before the final release build and proceed to that with the first build of M4 aiming for next week.
- The YP 2.7 M3 rc1 report is summarized at https://lists.yoctoproject.org/pipermail/yocto/2019-April/044667.html and the results are at https://autobuilder.yocto.io/pub/releases/yocto-2.7_M3.rc1/testresults/.
- 2.5.3 and 2.6.2 stable releases were built and submitted to QA last week.
- The “warrior” branches for 2.7 have been created and the metadata updated. This will have a ripple effect across the layers as they update to match this. This process is important as it allows layers to indicate which versions of the project they are compatible with.
- The 2.8 planning discussions are starting and there is a google doc summarising the discussions so far: https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJGXbU/
- If people are planning to work on specific things in 2.8 please let us know so we can incorporate this into our plans. If you’re interested in working on anything in the document, please also let us know or talk with us in one of the planning meetings.
Planned Releases for YP 2.7:
- YP 2.7 M4 Cutoff is Apr. 1, 2019
- YP 2.7 M4 Release Target is Apr. 26, 2019
Planned upcoming dot releases:
- YP 2.5.3 (Sumo) is in QA.
- YP 2.6.2 (Thud) is in QA.
Tracking Metrics:
- WDD 2442 (last week 2418) (https://wiki.yoctoproject.org/charts/combo.html)
- Poky Patch Metrics
- Total patches found: 1542 (last week 1538)
- Patches in the Pending State: 654 (42%) [last week 656 (43%)]