Yocto Project Weekly Status December 18, 2018
Current Dev Position: YP 2.7 M1 is in QA
Next Deadline: YP 2.7 M1 Release Target is Dec. 21, 2018
SWAT Team Rotation:
- SWAT lead is currently: Armin
- SWAT team rotation: Armin -> Anuj on Dec. 21, 2018
- SWAT team rotation: Anuj -> Paul on Nov. 28, 2018
- https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
- The next status report will be published on 2019/1/2 as we expect things to slow down over the holiday season in many locations.
- YP 2.5.2 rc1 is out of QA and should release today or tomorrow.
- YP 2.7 M1 is in QA.
- The distrodata bbclass in OE-Core is being removed since the tinfoil API provides a much better way to handle this kind of issue/data.
- We discovered potential hash collision issues with some of bitbake’s caching of objects so we are likely going to change to use sha256 everywhere including for sstate objects.
- There are occasional issues continuing in oe-selftest which we’re struggling to get to the bottom of unfortunately.
- There are some patches like the perl upgrade which are blocked on merging due to limited help in fixing fallout from them in layers like meta-openembedded. Khem in particular does a great job but we can’t rely on him alone.
Planned Releases for YP 2.6:
- YP 2.7 M1 Cutoff is in QA.
- YP 2.7 M1 Release Target is Dec. 21, 2018
- YP 2.7 M2 Cutoff is Jan. 21, 2019
- YP 2.7 M2 Release Target is Feb. 1, 2019
- YP 2.7 M3 Cutoff is Feb. 25, 2019
- YP 2.7 M3 Release Target is Mar. 8, 2019
- YP 2.7 M4 Cutoff is Apr. 1, 2019
- YP 2.7 M4 Release Target is Apr. 26, 2019
Planned upcoming dot releases:
- YP 2.5.2 (Sumo) is out of QA and should release shortly.
- YP 2.6.1 (Thud) will be targeted after YP 2.7 M1 is done.
- YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.
- YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.
- YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.
Tracking Metrics:
- WDD 2332 (last week 2295) (https://wiki.yoctoproject.org/charts/combo.html)
- Poky Patch Metrics
- Total patches found: 1629 (last week 1678)
- Patches in the Pending State: 720 (44%) [last week 740 (44%)]