Weekly Status

From Yocto Project
Jump to navigationJump to search

Yocto Project Weekly Status November 26, 2019

Current Dev Position: YP 3.1 M1
Next Deadline: YP 3.1 M1 build Dec. 2, 2019

Next Team Meetings:

Key Status/Updates:

  • YP 3.0.1 is out of QA with good test results so should be released soon.
  • We have set a deadline of Monday 9th December for removing python2 support from OE-Core, a separate email was sent out about this. The patches to do this are in master-next and they remove python and python2 from HOSTTOOLS.
  • Reproducible builds are now enabled by default in poky, we should also consider this for the default in OE-Core.
  • Hash equivalence continues to undergo testing and further work.
  • We’re likely to build M1 after the python 2 removal is merged next week, also giving time for the hash equivalence work to move forward further.
  • Intermittent build failures continue to hamper builds, particularly combined with the above issues and as few people are available to attempt to debug and resolve them.
  • The TSC is working on LTS plans, productive discussions have been had and a new policy on handling this and stable releases should be available in the coming weeks.
  • We are continuing to collect ideas for YP 3.1 in this document: https://docs.google.com/document/d/1UKZIGe88-eq3-pOPtkAvFAegbQDzhy_f4ye64yjnABc/edit?usp=sharing
  • If anyone has any status items for the project they’d like to add to the weekly reports, please email Richard and Stephen.

Proposed YP 3.1 Milestone Dates

  • YP 3.1 M1 build date 12/2/2019
  • YP 3.1 M1 release date 12/13/2019
  • YP 3.1 M2 build date 1/20/2020
  • YP 3.1 M2 release date 1/31/2020
  • YP 3.1 M3 build date 2/24/2020
  • YP 3.1 M3 release date 3/6/2020
  • YP 3.1 M4 build date 3/30/2020
  • YP 3.1 M4 release date 4/24/2020

Planned upcoming dot releases:

  • YP 3.0.1 is out of QA and should be released soon.
  • YP 2.7.3 build date 2/10/20
  • YP 2.7.3 release date 2/21/20
  • YP 3.0.2 build date 2/3/20
  • YP 3.0.2 release date 2/14/20

Tracking Metrics:

The Yocto Project’s technical governance is through its Technical Steering Committee, more information is available at:
https://wiki.yoctoproject.org/wiki/TSC

Archives