Yocto Project 1.2 release Status

Feature/Task Board

Scheduled Design Design Review Development Patch Review Merged Testing Done Blocked

Note: Each column lists "Feature #, Target Milestone, Owner, # of weeks in this stage".

Project Dashboard

Feature-burndown13.png



Yocto Project SWAT team

Chairperson of the current week: darren.hart@intel.com

Please see here for the details of the SWAT team: https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team

Yocto Project 1.3 Release Criteria

Milestone 1

Release Criteria Milestone 1 Target Milestone 1 Status
Functional Completion All P1 features are completed. Feature-burndown13-M1.png
See https://wiki.yoctoproject.org/wiki/Yocto_1.2_Schedule for details.
Build and Release (Yocto) All completed features can be built with no errors.
Build and Release (BSPs) Core and meta-intel BSPs can be built with no errors.
Open Bugs All bugs have been dispositioned. High issues have been fixed. [1] - new bugs for 1.3.
HIGH priority bugs - high bugs for 1.3
See trend chart at https://wiki.yoctoproject.org/wiki/Yocto_Bug_Trend.
Functional Tests 100% of planned tests are executed and results are logged in bugzilla. https://wiki.yoctoproject.org/wiki/Yocto_1.3_Milestone_Test_Report
Distros Tested Fedora, Ubuntu, Opensuse current version
BSP Testing 100% of planned tests are executed and results are logged in bugzilla. https://wiki.yoctoproject.org/wiki/Yocto_1.3_Milestone_Test_Report
Documentation TBD
Build Performance Try to at least maintain the current performance and improve if possible.
Package Update 50% of the target
Upstream Commits Have upstream status updated on 100% of patches (so that we can have a status update)
Publication Yocto 1.3, Milestone 1 release is announced