Weekly Status
From Yocto Project
Jump to navigationJump to search
Yocto Project Weekly Status August 13, 2019
Current Dev Position: YP 2.8 M3
Next Deadline: YP 2.8 Milestone M3 Cutoff (Feature Freeze) Aug 25, 2019
SWAT Team Rotation:
- SWAT lead is currently: Amanda
- SWAT team rotation: Amanda -> Chen on Aug. 16, 2019
- SWAT team rotation: Chen -> Armin on Aug. 23, 2019
- //wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Next Team Meetings:
- Bug Triage meeting Thursday August 15th at 7:30am PDT (https://zoom.us/j/454367603)
- Monthly Project Meeting Sept. 3rd at 8am PDT (https://zoom.us/j/990892712)
- Twitch - Next event is Sept. 3rd at 8am PDT (https://www.twitch.tv/yocto_project)
Key Status/Updates:
- YP 2.6.3 is out of QA and being readied for release.
- This release which was 2.8 will now become 3.0.
- The sstate has equivalency work has run into some challenges:
- performance of the hash server is not able to scale to the autibuilder’s load
- performance of runqueue has regressed even when not using the hash equivalency code
- bugfixes in master-next regress performance even further
- there are bugs being triggered by the has equivalency code that need investigation and resolution (along with test cases creating).
These issues are being worked on but we need to ensure correctness of the new code first before the performance can be fixed
- There were updates so some key components for bug fixes this week, in particular pseudo.
- General patch merging is happening and the queue is mostly clear and flowing but it isn’t happening as frequently as usual due to the hash equivalency work.
Planned Releases for YP 3.0 {2.8}:
- M2 is released.
- M3 Cutoff (Feature Freeze) 25th Aug
- M3 Release 6th Sept
- M4 Cutoff 30th Sept - this will be YP 3.0.
- YP 3.0 {2.8 (M4)} Final Release 25th Oct
Planned upcoming dot releases:
- YP 2.7.2 (Warrior) is planned for after YP 3.0 release.
- YP 2.6.3 (Thud) is out of QA and being readied for release.
- YP 2.6.4 (Thud) is planned for after YP 2.7.2 release.
Tracking Metrics:
- WDD 2482 (last week 2481) (https://wiki.yoctoproject.org/charts/combo.html)
- Poky Patch Metrics
- Total patches found: 1489 (last week 14996)
- Patches in the Pending State: 617 (41%) [last week 615 (41%)]
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.8_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.8_Features