Yocto Project Weekly Status February 26, 2019
Current Dev Position: YP 2.7 M3
Next Deadline: YP 2.7 M3 Cutoff was Feb. 25, 2019
SWAT Team Rotation:
- SWAT lead is currently: Ross
- SWAT team rotation: Ross -> Chen on Mar. 1, 2019
- SWAT team rotation: Chen -> Anuj on Mar. 8, 2019
- https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Key Status/Updates:
- We have now passed the feature freeze point for 2.7
- YP 2.7 M2 rc2 is out of QA and being readied for release. See: https://wiki.yoctoproject.org/wiki/WW07_-_2019-02-14_-_Full_Test_Cycle_2.7_M2_RC2 and https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status#Milestone_2_-_Target_Feb._1.2C_2019
- We now have resulttool, buildhistory and build-performance all working with the autobuilder and will be using this as the primary QA mechanism going forward. More details can be found here:
http://lists.openembedded.org/pipermail/openembedded-architecture/2019-February/001591.html
- There were some serious usability issues found with multiconfig, those have been fixed in master and thud.
- Various recipe upgrades made it in, thanks to all who contributed. Several recipes also converted to meson including glib-2.0 and gdk-pixbuf.
- We now need to build M3 as we’re past feature freeze point for 2.7. Right now we’re aware of the following things which ideally need to be resolved first:
- Bug 13178 “X server and matchbox desktop don't start up properly on beaglebone” needs to be fixed
- Find the framebuffer problem with qemuarmv7 and switch to that
- Several ptest issues would be addressed (missing openssl tests, 3 timeouts)
- Arm build host issues identified and resolved
- It’s unlikely we’ll switch to virtgl by default for 2.7 due to lack of testing from the community although the base patches for this have merged.
Planned Releases for YP 2.7:
- YP 2.7 M2 rc2 is out of QA.
- YP 2.7 M2 Release Target was Feb. 1, 2019
- YP 2.7 M3 Cutoff is Feb. 25, 2019
- YP 2.7 M3 Release Target is Mar. 8, 2019
- YP 2.7 M4 Cutoff is Apr. 1, 2019
- YP 2.7 M4 Release Target is Apr. 26, 2019
Planned upcoming dot releases:
- YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.
- YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.
- YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.
Tracking Metrics:
- WDD 2415 (last week 2392) (https://wiki.yoctoproject.org/charts/combo.html)
- Poky Patch Metrics
- Total patches found: 1516 (last week 1527)
- Patches in the Pending State: 660 (44%) [last week 663 (43%)]
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features