Yocto Project Weekly Status January 22, 2019

Current Dev Position: YP 2.7 M2
Next Deadline: YP 2.7 M2 Cutoff is Jan. 21, 2019

SWAT Team Rotation:

  • SWAT lead is currently: Chen

SWAT team rotation: Chen -> Armin on Jan. 25, 2019

Key Status/Updates:

  • YP 2.7 M1 was released on Jan. 10, 2019
  • YP 2.6.1 is in QA and 79% complete. See: https://wiki.yoctoproject.org/wiki/2.6_QA_Status
  • We merged the perl changes and version upgrade. This exposed some race issues but we’re hoping those have now been resolved. Thanks AlexK! This may cause fallout for perl module recipes in other layers.
  • There is a proposed patchset to add GL passthrough support for qemu, feedback on the proposals is welcome. There are build time performance implications, particularly due to the use of gtk3+-native.
  • There is a -dev kernel recipe for the Linux 5.0 kernel, thanks Bruce.
  • M2 cutoff is next week!

Planned Releases for YP 2.7:

  • YP 2.7 M2 Cutoff is Jan. 21, 2019
  • YP 2.7 M2 Release Target is Feb. 1, 2019
  • YP 2.7 M3 Cutoff is Feb. 25, 2019
  • YP 2.7 M3 Release Target is Mar. 8, 2019
  • YP 2.7 M4 Cutoff is Apr. 1, 2019
  • YP 2.7 M4 Release Target is Apr. 26, 2019

Planned upcoming dot releases:

  • YP 2.6.1 (Thud) will is out of QA.
  • YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.
  • YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.
  • YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.

Tracking Metrics:

Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features