Weekly Status: Difference between revisions
From Yocto Project
Jump to navigationJump to search
No edit summary |
|||
Line 1: | Line 1: | ||
== Yocto Project Weekly Status April | == Yocto Project Weekly Status April 23, 2019 == | ||
Current Dev Position: YP 2.7 M4 (2.7 rc2 is in QA)<br/> | Current Dev Position: YP 2.7 M4 (2.7 rc2 is in QA)<br/> | ||
Next Deadline: YP 2.7 Release Target April 26, 2019<br/> | Next Deadline: YP 2.7 Release Target April 26, 2019<br/> | ||
Line 5: | Line 5: | ||
'''SWAT Team Rotation:'''<br/> | '''SWAT Team Rotation:'''<br/> | ||
*SWAT lead is currently: | *SWAT lead is currently: Armin | ||
*SWAT team rotation: Armin -> Anuj on Apr. 26, 2019 | *SWAT team rotation: Armin -> Anuj on Apr. 26, 2019 | ||
*SWAT team rotation: Armin -> Paul on May. 3, 2019 | |||
*https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team | *https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team | ||
'''Next Team Meetings:'''<br/> | '''Next Team Meetings:'''<br/> | ||
* | *Bug Triage meeting Thursday April 25th at 7:30am PDT (https://zoom.us/j/454367603) | ||
* | *YP 2.8 Planning meeting Tuesday May 7th at 8am PDT (https://zoom.us/j/990892712) | ||
'''Key Status/Updates:'''<br/> | '''Key Status/Updates:'''<br/> | ||
*Stephen is unavailable | *Stephen is going to be unavailable for several weeks, please refer any queries to Richard | ||
*YP 2.6.2 was | *YP 2.6.2 was released! | ||
*YP 2.5.3 is | *YP 2.5.3 is likely to be released imminently | ||
*YP 2.7 rc2 (warrior) is currently going through QA. | |||
*The final two members of the new YP TSC were elected, Denys and Armin. The TSC will therefore now start to discuss how its going to establish itself and operate. | |||
*Huge thanks to Joshua Watt for diving in and helping file some ptest bugs and helping sort some missing tweaks with resulttool, it was just appreciated | |||
*YP 2.7 rc2 (warrior) | *Patches are continuing to flow into master, slightly impeded by holidays/vacation in some parts of the world. | ||
*The | *WDD, our bug tracking metric is sharply rising as there are few people helping with bugs. | ||
* | |||
* | |||
*The 2.8 planning discussions are starting and there is a google doc summarising the discussions so far: https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJGXbU/ | *The 2.8 planning discussions are starting and there is a google doc summarising the discussions so far: https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJGXbU/ | ||
*If people are planning to work on specific things in 2.8 please let us know so we can incorporate this into our plans. If you’re interested in working on anything in the document, please also let us know or talk with us in one of the planning meetings. | *If people are planning to work on specific things in 2.8 please let us know so we can incorporate this into our plans. If you’re interested in working on anything in the document, please also let us know or talk with us in one of the planning meetings. | ||
Line 38: | Line 31: | ||
'''Planned upcoming dot releases:'''<br/> | '''Planned upcoming dot releases:'''<br/> | ||
*YP 2.5.3 (Sumo) | *YP 2.5.3 (Sumo) due for release. | ||
'''Tracking Metrics:'''<br/> | '''Tracking Metrics:'''<br/> | ||
*WDD | *WDD 2598 (last week 2523) (https://wiki.yoctoproject.org/charts/combo.html) | ||
*Poky Patch Metrics | *Poky Patch Metrics | ||
**Total patches found: 1553 (last week 1553) | **Total patches found: 1553 (last week 1553) | ||
**Patches in the Pending State: 654 (42%) [last week | **Patches in the Pending State: 654 (42%) [last week 654 (42%)] | ||
'''Key Status Links for YP:'''<br/> | '''Key Status Links for YP:'''<br/> |
Revision as of 14:47, 23 April 2019
Yocto Project Weekly Status April 23, 2019
Current Dev Position: YP 2.7 M4 (2.7 rc2 is in QA)
Next Deadline: YP 2.7 Release Target April 26, 2019
SWAT Team Rotation:
- SWAT lead is currently: Armin
- SWAT team rotation: Armin -> Anuj on Apr. 26, 2019
- SWAT team rotation: Armin -> Paul on May. 3, 2019
- https://wiki.yoctoproject.org/wiki/Yocto_Build_Failure_Swat_Team
Next Team Meetings:
- Bug Triage meeting Thursday April 25th at 7:30am PDT (https://zoom.us/j/454367603)
- YP 2.8 Planning meeting Tuesday May 7th at 8am PDT (https://zoom.us/j/990892712)
Key Status/Updates:
- Stephen is going to be unavailable for several weeks, please refer any queries to Richard
- YP 2.6.2 was released!
- YP 2.5.3 is likely to be released imminently
- YP 2.7 rc2 (warrior) is currently going through QA.
- The final two members of the new YP TSC were elected, Denys and Armin. The TSC will therefore now start to discuss how its going to establish itself and operate.
- Huge thanks to Joshua Watt for diving in and helping file some ptest bugs and helping sort some missing tweaks with resulttool, it was just appreciated
- Patches are continuing to flow into master, slightly impeded by holidays/vacation in some parts of the world.
- WDD, our bug tracking metric is sharply rising as there are few people helping with bugs.
- The 2.8 planning discussions are starting and there is a google doc summarising the discussions so far: https://docs.google.com/document/d/1CNEKA4d0eT6-e0hnS2pwi7xdZ5_t6smpZO2HbaJGXbU/
- If people are planning to work on specific things in 2.8 please let us know so we can incorporate this into our plans. If you’re interested in working on anything in the document, please also let us know or talk with us in one of the planning meetings.
Planned Releases for YP 2.7:
- YP 2.7 M4 Cutoff was Apr. 1, 2019
- YP 2.7 M4 Release Target is Apr. 26, 2019
Planned upcoming dot releases:
- YP 2.5.3 (Sumo) due for release.
Tracking Metrics:
- WDD 2598 (last week 2523) (https://wiki.yoctoproject.org/charts/combo.html)
- Poky Patch Metrics
- Total patches found: 1553 (last week 1553)
- Patches in the Pending State: 654 (42%) [last week 654 (42%)]
Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features