*YP 2.7 M1 is out of QA and being prepared for release.
*YP 2.7 M1 was released on Jan. 10, 2019
*YP 2.5.2 was released on Jan. 4, 2019.
*YP 2.6.1 is in QA and 79% complete. See: https://wiki.yoctoproject.org/wiki/2.6_QA_Status
*YP 2.6.1 should build once the current patch queue from Armin has final review and is merged.
*We merged the perl changes and version upgrade. This exposed some race issues but we’re hoping those have now been resolved. Thanks AlexK! This may cause fallout for perl module recipes in other layers.
*The hash equivalency server code merged, thanks to Joshua Watt for his patience in working through some of the details with that!
*There is a proposed patchset to add GL passthrough support for qemu, feedback on the proposals is welcome. There are build time performance implications, particularly due to the use of gtk3+-native.
*Many different patches for upgrades, features and fixes continue to be merged and we should be mostly up to date with incoming patches.
*There is a -dev kernel recipe for the Linux 5.0 kernel, thanks Bruce.
*There do continue to be intermittent failures on the autobuilder, albeit at lower frequency than previously.
*M2 cutoff is next week!
*The cross-perl patchset from AlexK is building successfully on the autobuilder so others are requested to give feedback as its likely to merge soon based on the test results.


'''Planned Releases for YP 2.7:'''<br/>
'''Planned Releases for YP 2.7:'''<br/>

Revision as of 15:59, 15 January 2019

Yocto Project Weekly Status January 15, 2019

Current Dev Position: YP 2.7 M2
Next Deadline: YP 2.7 M2 Cutoff is Jan. 21, 2019

SWAT Team Rotation:

Key Status/Updates:

  • YP 2.7 M1 was released on Jan. 10, 2019
  • YP 2.6.1 is in QA and 79% complete. See: https://wiki.yoctoproject.org/wiki/2.6_QA_Status
  • We merged the perl changes and version upgrade. This exposed some race issues but we’re hoping those have now been resolved. Thanks AlexK! This may cause fallout for perl module recipes in other layers.
  • There is a proposed patchset to add GL passthrough support for qemu, feedback on the proposals is welcome. There are build time performance implications, particularly due to the use of gtk3+-native.
  • There is a -dev kernel recipe for the Linux 5.0 kernel, thanks Bruce.
  • M2 cutoff is next week!

Planned Releases for YP 2.7:

  • YP 2.7 M2 Cutoff is Jan. 21, 2019
  • YP 2.7 M2 Release Target is Feb. 1, 2019
  • YP 2.7 M3 Cutoff is Feb. 25, 2019
  • YP 2.7 M3 Release Target is Mar. 8, 2019
  • YP 2.7 M4 Cutoff is Apr. 1, 2019
  • YP 2.7 M4 Release Target is Apr. 26, 2019

Planned upcoming dot releases:

  • YP 2.6.1 (Thud) will is in QA.
  • YP 2.5.3 (Sumo) will be targeted after YP 2.7 M2 is done.
  • YP 2.5.4 (Sumo) will be targeted after YP 2.7 M4 is done.
  • YP 2.6.2 (Thud) will be targeted after YP 2.5.4 is done.

Tracking Metrics:

Key Status Links for YP:
https://wiki.yoctoproject.org/wiki/Yocto_Project_v2.7_Status
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Schedule
https://wiki.yoctoproject.org/wiki/Yocto_2.7_Features

Archives