Yocto Project 1.0.1 Release Criteria

The Yocto Project 1.0.1 release will contain critical bug fixes from Yocto Project 1.0.

Release Criteria Target Status
Functional Completion No new significant features are added. Any minor functionality added is documented in git logs. There are 300 commits that Richard is looking through to pull for 1.0.1.
Build and Release (Yocto) 1.0.1 build can be built with no errors. Build will run May 14th to May 21st. Beth will run a test build the week of May 3rd. She has a plan that doesn't require getting new hardware to do.
Build and Release (BSPs) BSPs targeted for 1.0.1 (= all current BSPs) are built. Build will run May 14th to May 21st. Beth will run a test build the week of May 3rd. She has a plan that doesn't require getting new hardware to do.
Open Bugs All bugs targeted for 1.0.1 are in the build by May 13th. 17 bugs exist for 1.0.1 so far; triage team will disposition to ensure we have the right list.
30 bugs total
Functional Tests 100% of planned tests are executed and results are logged in bugzilla. First test pass will be May 21st-22nd (weekly). Go/No-Go will determine if full test pass should be done.
BSP Testing 100% of planned tests are executed and results are logged in bugzilla. First test pass will be May 21st-22nd (weekly). Go/No-Go will determine if full test pass should be done.
Documentation 1.0.1 Release Notes are complete. Release notes to begin May 14th.
Build Performance 1.0.1 does not increase performance above 107 minutes on a developer machine.
Publication 1.0.1 release is built and announced to the community.