Yocto 1.1 Schedule

From Yocto Project
Revision as of 20:02, 27 April 2011 by Jnfleisc (talk | contribs) (→‎M3 Sprint A (Jul 18 to Jul 22): added shared state)
Jump to navigationJump to search

Yocto Project 1.1 (release date: October 6, 2011)


The detailed milestone map for the 1.1 release of Yocto Project is as below.

pre-M1 (March 14 to April 18 -- Feature List and Schedule Defined April 18)

  • Features Submitted to web - by April 1st
  • Features prioritized and added to schedule - by April 12th

pre-M1 COMPLETED

M1 (Apr 18 to Jun 13 -- Design Complete Apr 25, Dev Complete May 23, Stabilize Complete Jun 6, Release Complete Jun 13)

M1 Design (Apr 18 to Apr 22)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Automatically generate package repos - design automatically generate package repositories (and be able to \"use them\" -- to be defined) for both ipk and rpm/zypper combinations; also, documentation of this process is essential; this stage is the design phase. 2 Complete Team Saul (Dexuan) M1, Design
OE Autobuilder rename 1 26-Apr Beth Beth M1, Design
Strip out LSB, non-LSB build work Remove the LSB, non-LSB build work done at the end of 1.0 and re-incorporate it with sstate 1 26-Apr Beth Beth M1, Design

M1 Sprint A (Apr 25 to Apr 29)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
OE-Core Restructuring, renaming, rebranding 1 at 90% RP Notes Richard M1, Sprint A
SDK support in sanity test framework This task includes enabling unfs and toolchain testing in sanity test framework, enabling toolchain testing on PRC autobuilder 1 Saul will get update by Wed QA Jiajun/Meilei M1, Sprint A
User Creation at preinstall - status check Design status check 1 29-Apr RP Notes Mark (ScottG) M1, Sprint A
Optimise Configure 2 Saul will get update by Wed RP Notes Saul (Dongxiao) M1, Sprint A - Richard writes down his thoughts (Dongxiao determines finish date at this time)
Check SRCREV in recipe files should work, may need dev 2 next time pull done RP Notes Richard/Ke M1, Sprint A - planning complete (may evaporate after this) - Ke needs to check in with Richard to get a go/no-go decision. We just need to ensure SRCREVs are the individual recipe files rather than the group file.
Refactor BSPs to use topic branches crownbay and fish river island BSP need to be changed to make use of the new eg20t/emgd/gma500 topic branches 2 29-Apr Tom Tom M1, Sprint A
Additional config options The following configurations need to be enabled to support DPDK: glibc > 2.7 (for features related to cpuset), kernel configuration: HPET and HPET MMAP configuration options enabled, all UIO kernel options enabled, HUGETLBFS enabled, PROC_PAGE_MONITOR enabled 1 29-Apr Rahul Tom? M1, Sprint A
Autobuilder maintenance Bring scripts into configuration or get git repo working for those that can\'t be brought in. (takes 2 days) 1 3-May Beth Beth M1, Sprint A
Retrospective Hold a retrospective to discuss what went well and what can be improved in 1.1 1 Done Beth Beth M1, Sprint A

M1 Sprint B (May 2 to May 6)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Layer Tooling - Design Design/Architect the Layer Tooling approach 1 Accept Architect Richard M1 Sprint B
crazygit fetcher TI issues with fetch2 - per LCS - should this be a P1? 2 Accept RP Notes Saul (Ke) M1, Sprint B (timescale = 2-3 days)
multi-lib infrastructure multi-lib support for 32-bit & 64-bit and capable of being installed at the same time - infrastructure in place (bbclass extend and multilib toolchain changes) 1 Accept from 1.0 Richard (Qing) M1, Sprint B
Test Plan Create an overall Test Plan for 1.1 and post on Wiki 1 Accept Jiajun Jiajun M1, Sprint B
Sync qemugl with MeeGo - Status check This is a status check on how the work to sync qemugl with MeeGo is going. Completion set for M1, Sprint D. 2 Accept Meta-data Saul (Edwin) M1, Sprint B
Finish LSB \"distribution\" work - QT3 QT3 work is complete. 2 Accept Meta-data WR Distro Team M1, Sprint B
Incompatible License 2 Accept Paul Paul M1, Sprint B - design and review
Optimize support for Intel hardware features We need to understand and track each important Intel hardware feature and how it should be optimally supported in the Intel BSPS. Items that immediately come to mind are power, video, and performance counter settings, etc. 1 Accept Tom Tom/Darren M1, Sprint B, C, D
Upgrade EMGD EMGD needs to be upgraded to the latest version (1.52). A big part of this should also be to make sure everything gets tested and works e.g. 3-d games, video acceleration, etc 2 Accept Tom Tom M1, Sprint B and C
Changes for Image Creator - phase 1 Phase 1: add mechanism to enable selection of server backend at runtime 1 Accept ADT Team Jessica M1, Sprint B
Release Scripts Create Release Scripts that can be used for both a weekly release and for OCT 2011 release to be run by autobuilder (a week. testing on this may take longer) 1 Accept Beth Beth M1, Sprint B
build statistics reporting As someone interested in how long it takes to build different images on different hardware configurations and other assorted build metrics, I would like a web based service, that takes output generated by an extended buildstats.bbclass and stores it, to compare against different machines. The end result should be a way to visualize the collected data. See: https://wiki.yoctoproject.org/wiki/Yocto_Buildbot_Autobuilder_Discussions Accept eflanagan/Jay7/ka6sox Beth/Jay M1, Sprint B and C (or two weeks in here)
Fast boot analysis Perform analysis to determine how best to implement a 2 second boot time 1 Accept Darren Darren M1, Sprint B

M1 Sprint C (May 9 to May 13)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Package config option enhancement - Plan Plan our approach to package config option enhancement 2 Accept from 1.0 Richard M1, Sprint C
Upstream our patches - phase 1 Have upstream status updated on 90% of patches (so that we can have a status update) 1 Accept Meta-data Saul M1, Sprint C
3G - Design We have an ofono recipe but need some integration work done. This milestone is a status check and design update. HW needs to be received at this time. 2 Accept Meta-data Saul (Dongxiao) M1, Sprint C Need hardware and infrastructure to test 3G (MeeGo team has this)
Package reporting system enhancement 2 Accept Meta-data Saul (Lei) M1, Sprint C or D (need additional definition of this item)
Automatically generate package repos - complete automatically generate package repositories (and be able to \"use them\" -- to be defined) for both ipk and rpm/zypper combinations as discussed during the Design phase; also, documentation of this process is essential 2 Accept Team Saul (Dexuan) M1, Sprint C
User Creation at preinstall - complete Deliverable completed 1 Accept RP Notes Mark (ScottG) M1, Sprint C
Upgrade to gcc 4.6 Need to upgrade toolchain to gcc 4.6 1 Accept Nitin Nitin M1, Sprint C or D
License tracking Get common licenses for all packages and consolidate base file licenses. (takes ~3 days) 1 Accept Beth Beth M1, Sprint C
Audotbuilder infrastructure Bring up additional autobuilders and work with sysadmin to configure. 1 Accept Beth Beth M1, Sprint C (dependent on us having a system admin)
Release Scripts Create Release Scripts that can be used for both a weekly release and for OCT 2011 release to be run by autobuilder (a week. testing on this may take longer) 1 Accept Beth Beth M1, Sprint C
kernel port to 2.6.37 Port the kernel to 2.6.37 1 Accept Darren Darren M1, Sprint C
Tracing: Add Systemtap support for userspace tracing Add utrace, etc 2 Accept Tom Tom M1, Sprint C

M1 Sprint D (May 16 to May 20)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
multi-lib complete multi-lib support for 32-bit & 64-bit and capable of being installed at the same time fully complete 1 Accept from 1.0 Richard (Qing) M1, Sprint D
Image Creator - 1.0 finish finish the Image Creator to add features pushed out from 1.0 - See https://wiki.yoctoproject.org/wiki/BitBake/GUI/PostOneOh for details 1 Accept from 1.0 Josh M1 Sprint D
Sync qemugl with MeeGo - COMPLETE sync qemugl with MeeGo is complete 2 Accept Meta-data Saul (Edwin) M1, Sprint D
Finish LSB \"distribution\" work - ID failures Identify issues in order to: Merge patches which are pushed during yocto 1.0. Add packages(qt3,xdg-* ...) LSB Test Suite need. Hardware platform x86 and ppc32(if qt4 can be supported) can be finished. 2 Accept Meta-data WR Distro Team M1, Sprint D
OE Comparison Compare Yocto core set against integration work in OE and other distributions looking for bug fixes, (relevant) feature enhancements, and integration/policy hints. 1 Accept Meta-data Mark M1, Sprint D
End of package revision replace with a network service 2 Accept RP Notes Jessica M1, Sprint D
x32 - plan layer to support toolchain, libc, and kernel - Plan created 2 Accept RP Notes Saul (Nitin) M1, Sprint D
BBXM Pull in bits from OE (kernel and uboot) 1 Accept Darren Darren M1, Sprint D
Eclipse-native tools interface More integrated with upstream once there\'s integrated Linux tools that meets our need, e.g. lttng-remote 2 Accept ADT Team Jessica M1, Sprint D
Changes for Image Creator - phase 2 Phase 2: Bug fix for 7.70 1 Accept ADT Team Jessica M1, Sprint D
License tracking Build a parser to do license tracking more gracefully and make sure all recipes are correct. (takes ~2 weeks) 1 Accept Beth Beth M1, Sprint D
Tracing: perf trace scripting support Basically this means allowing perf to be built with the Perl and Python bindings, which turned out to be a headache last time. 2 Accept from 1.0 Tom M1, Sprint D

M1 Stabilize (May 23 to June 3)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Be prepared for Distro upgrades Our release is right around the time of the 6monthly distro release dates, we should accommodate for this in our testing plan 2 Accept Joshua Jiajun check latest distribution in M1 Stabilize, M2 Stabilize, and M3 Stabilize and test them in milestone testing; Should we include more Distributions, besides fedora, ubuntu and opensuse?
Test Execution Plan Create a Test Execution Plan for the milestone and send to developers 1 Accept Jiajun Jiajun M1 Stabilize; M2 Stabilize; M3 Stabilize
Development complete All bugs targeted for 1.0.1 are in the 1.0.1 build. 1 Accept Team All M1, Sprint3 to M1, Stabilize

Stabilize schedule

Week 1

  • Day 1, 2: Weekly test pass
  • Day 3: Pre-Release Readiness meeting
  • If there are issues:
    • Day 4, 5: Fix issues and repeat Week 1
  • If there are not issues:
    • Day 4, 5 and beginning of Week 2: Complete a full test pass

Week 2

  • Day 1, 2, 3: Complete full test pass
  • Day 4: Release Readiness meeting
  • If there are issues, fix and repeat from Week 1
  • If there are not issues, proceed to Release phase

M1 Release (June 6 to June 13)

Follow Release Checklist, which includes:

  • Release is packaged
  • Release is pushed to mirrors
  • Release is announced to community via mailing lists and blog

M2 (May 30 to Jul 25 -- Design Complete Jun 6, Dev Complete Jul 4, Stabilize Complete Jul 18, Release Complete Jul 25)

M2 Design (May 30 to June 3)

* Working week.  No tasks complete this week.

M2 Sprint A (June 6 to June 10)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Live images make live images their own image type 2 Accept RP Notes Saul M2, Sprint A
More test cases about toolchain in autobuilder 2 Accept ADT Team Jessica Status check in M2, Sprint A, M3, Sprint A
Indigo update Update to the latest Eclipse release (Indigo) 2 Accept ADT Team Jessica Status check in M2, Sprint A, M3, Sprint A
Systemtap integration Make it easy and convenient for the user to write and execute Systemtap scripts from the IDE. http://www.eclipse.org/linuxtools/projectPages/systemtap/ might provide a good starting point and may be something we can contribute to. We may also need to contribute further up the chain to provide e.g. remote target capabilities. 2 Accept Tom Jessica Status check in M2, Sprint A, M3, Sprint A
\'perf scripting\' integration Make it easy and convenient for the user to write and execute \'perf scripts\' from the IDE. We should be able to leverage and build on the Systemtap integration for this. 2 Accept Tom Jessica Status check in M2, Sprint A, M3, Sprint A
Finish LSB \"distribution\" work - complete Complete all work: Merge patches which are pushed during yocto 1.0. Add packages(qt3,xdg-* ...) LSB Test Suite need. Hardware platform x86 and ppc32(if qt4 can be supported) can be finished. 2 Accept Meta-data WR Distro Team M2, Sprint A

M2 Sprint B (June 13 to June 17)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Layer Tooling - Architecture Implement Layer Tooling changes 1 Accept Architect Richard (Paul/Daoxien will help) M2 Sprint B
Error handling in bitbake desc 1 Accept RP Notes Saul (Scott G) M2, Sprint B
Package config option enhancement - Implement Implement approach defined in plan for package config option enhancement 2 Accept from 1.0 Saul M2, Sprint B
Upstream our patches - phase 2 Everyone has attempted upstreams for patches defined from phase 1 1 Accept Meta-data Saul M2, Sprint B
MeeGo GPLv2 Sync compare with Yocto, sync any patches 2 Accept RP Notes Saul (Ke) M2, Sprint B
Directory Ownership 1.5 Accept RP Notes Mark (w/Qing) M2, Sprint B
Changes for Image Creator - phase 3 Phase 3: package format job done + image output type job done 1 Accept ADT Team Jessica M2, Sprint B
Meta targets Part of the challenge of autobuilder is that you have to go into autobuilder, edit script, reconfigure, to change just one build target. This is error prone. What we need is a meta-target where Beth can say she wants to build Poky-image-sato for QEMU x86 and have it just do that. Beth thinks this is done via an override to the web page. (takes ~2 weeks) 1 Accept Beth Beth M2, Sprint B
kernel bloat - analysis target = boot a minimal image in < 8M - analysis complete 1 Accept Darren Darren M2, Sprint B

M2 Sprint C (June 20 to June 24)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
btrfs 2 Accept Meta-data Saul (Nitin) M2, Sprint C
adding eglibc config control this goes with the package config options 1.5 Accept RP Notes Mark M2, Sprint C
Implement Continuous Autobuilds Build constantly instead of daily (need fuzz builds for this. once fuzz builds are implemented, this is trivial) 2 Accept from 1.0 Beth M2, Sprint C

M2 Sprint D (June 27 to July 1)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Image Creator polish polish and refine Image Creator - See https://wiki.yoctoproject.org/wiki/BitBake/GUI/PostOneOh for details 1 Accept from 1.0 Josh M2, Sprint D
Clean up warning messages A build that runs correctly to completion still includes a ton of WARNING messages. We need a project to clean these up. Beth will work on License Warnings, team will look at other logfile warnings 2 Accept davest and RP Saul M2, Sprint D
3G - Complete We have an ofono recipe but need some integration work done - This milestone checks that 3G is complete. 2 Accept Meta-data Saul (Dongxiao) M2, Sprint D
running post installs at rootfs gen time 2 Accept RP Notes Saul (Dexuan) M2, Sprint D
remove gnome-vfs 3 Accept RP Notes Saul (Edwin) M2, Sprint D
x32 - complete layer to support toolchain, libc, and kernel - x32 is complete 2 Accept RP Notes Saul (Nitin) M2, Sprint D
Changes for Image Creator - phase 4 Phase 4: complete plug-in 1 Accept ADT Team Jessica M2, Sprint D
Enhance the deploy part in remote debug ADT is currently using org.eclipse.cdt.remote.launch for remote debug. One limitation in this plug-in is that it can only deploy one single file to the target during the debug. Though it is ok for debugging static linked program, debugging dynamic linked program might require deploying multiple files(including executables and libraries) to the target. 2 Accept Lianhao Jessica M2 Sprint D
BSP builds Autobuilder git fetcher improvements (3 days) 2 Accept from 1.0 Beth M2, Sprint D
kernel bloat - development target = boot a minimal image in < 8M - development complete 1 Accept Darren Darren M2, Sprint D
Tracing: Systemtap usability in Yocto Right now, there are instructions on the wiki on how to configure and use Systemtap with Yocto. While straightforward, they are tedious and unlikely to be useful to most people pressed for time. We need to make it easier to use - in addition to documentation/HOWTO tasks listed elsewhere on this page, we need to make it usable \'out of the box\' (i.e. outside of ADT) e.g. all paths and configuration handled via script or something similar 2 Accept Tom Tom M2, Sprint D

M2 Stabilize (July 4 to July 15)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Be prepared for Distro upgrades Our release is right around the time of the 6monthly distro release dates, we should accommodate for this in our testing plan 2 Accept Joshua Jiajun check latest distribution in M1 Stabilize, M2 Stabilize, and M3 Stabilize and test them in milestone testing; Should we include more Distributions, besides fedora, ubuntu and opensuse?
Test Execution Plan Create a Test Execution Plan for the milestone and send to developers 1 Accept Jiajun Jiajun M1 Stabilize; M2 Stabilize; M3 Stabilize
Lock kernel version lock the kernel version 1 Accept Team Darren M2, Stabilize (ww29)

Stabilize schedule

Week 1

  • Day 1, 2: Weekly test pass
  • Day 3: Pre-Release Readiness meeting
  • If there are issues:
    • Day 4, 5: Fix issues and repeat Week 1
  • If there are not issues:
    • Day 4, 5 and beginning of Week 2: Complete a full test pass

Week 2

  • Day 1, 2, 3: Complete full test pass
  • Day 4: Release Readiness meeting
  • If there are issues, fix and repeat from Week 1
  • If there are not issues, proceed to Release phase

M2 Release (July 18 to July 22)

Follow Release Checklist, which includes:

  • Release is packaged
  • Release is pushed to mirrors
  • Release is announced to community via mailing lists and blog

M3 (Jul 11 to Aug 15 -- Design Complete Jul 18, Dev Complete Jul 25, Stabilize Complete Aug 8, Release Complete Aug 15)

M3 Design (Jul 11 to Jul 15)

* Working week.  No tasks complete this week.

M3 Sprint A (Jul 18 to Jul 22)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Upstream our patches - phase 3 Another round of updates is complete 1 Accept Meta-data Saul M3, Sprint A
Sanity checks on per recipe basis 2 Accept RP Notes Bug#405 Saul (Scott G) M3, Sprint A
Ability to build SRPM 3 Accept RP Notes Jeff Polk/Mark M3, Sprint A - Julie to check with Jeff
Fish River Island/Fish River Island II BSP(s) The base Fish River Island BSP exists already, we now need to add support for the extra devices, and add support for changes introduced by Fish River Island II 2 Accept Tom Tom M3, Sprint A
More test cases about toolchain in autobuilder 2 Accept ADT Team Jessica Status check in M2, Sprint A, M3, Sprint A
Indigo update Update to the latest Eclipse release (Indigo) 2 Accept ADT Team Jessica Status check in M2, Sprint A, M3, Sprint A
Systemtap integration Make it easy and convenient for the user to write and execute Systemtap scripts from the IDE. http://www.eclipse.org/linuxtools/projectPages/systemtap/ might provide a good starting point and may be something we can contribute to. We may also need to contribute further up the chain to provide e.g. remote target capabilities. 2 Accept Tom Jessica Status check in M2, Sprint A, M3, Sprint A
\'perf scripting\' integration Make it easy and convenient for the user to write and execute \'perf scripts\' from the IDE. We should be able to leverage and build on the Systemtap integration for this. 2 Accept Tom Jessica Status check in M2, Sprint A, M3, Sprint A
Additions to build stats 1 Accept Beth Beth M3, Sprint A
Alpha Begin an alpha program after the stabilization period for M3. 1 Accept Team Julie M3, Sprint A
Publish Shared State Publish the shared state information. 2 Review LCS Beth M3, Sprint A if Richard confirms some answers to questions

M3 Stabilize (Jul 25 to Aug 5)

Feature Name Description Priority Status Source Owner Comments / Bugzilla Links
Be prepared for Distro upgrades Our release is right around the time of the 6monthly distro release dates, we should accommodate for this in our testing plan 2 Accept Joshua Jiajun check latest distribution in M1 Stabilize, M2 Stabilize, and M3 Stabilize and test them in milestone testing; Should we include more Distributions, besides fedora, ubuntu and opensuse?
Test Execution Plan Create a Test Execution Plan for the milestone and send to developers 1 Accept Jiajun Jiajun M1 Stabilize; M2 Stabilize; M3 Stabilize

Stabilize schedule

Week 1

  • Day 1, 2: Weekly test pass
  • Day 3: Pre-Release Readiness meeting
  • If there are issues:
    • Day 4, 5: Fix issues and repeat Week 1
  • If there are not issues:
    • Day 4, 5 and beginning of Week 2: Complete a full test pass

Week 2

  • Day 1, 2, 3: Complete full test pass
  • Day 4: Release Readiness meeting
  • If there are issues, fix and repeat from Week 1
  • If there are not issues, proceed to Release phase

M3 Release (Aug 8 to Aug 15)

Follow Release Checklist, which includes:

  • Release is packaged
  • Release is pushed to mirrors
  • Release is announced to community via mailing lists and blog


M4 (Aug 15 to Oct 6 -- Stabilize Complete Aug 29, Release Complete Oct 3)

Group Feature Name Description Priority Status Owner Source Comments / Bugzilla Links
Project Release Candidate 1 RC1 generated 1 Aug-29 Beth Team
Project Release Candidate 2 RC2 generated 1 Sep-5 Beth Team
Project Release Candidate 3 RC3 generated 1 Sep-12 Beth Team
Project Release Candidate 4 RC4 generated 1 Sep-19 Beth Team
Project Release Readiness Release Readiness Meeting 1 Sep-26 Julie Julie
QA Holiday QA team on holiday Oct 1 - 7 1 Oct 1-7 QA QA