Yocto Project 1.2 (release date: April 6, 2012)


The detailed milestone map for the 1.2 release of Yocto Project is as below. To view the Yocto schedule-at-a-glance, go to YoctoCalendar

M1 (Oct. 31 to Dec. 16, 2011 -- 7 weeks: planning done in week 1, development week 1-4, stablization week 5-6, release week 7)

M1 Feature Development (Oct. 31 to Nov. 23, 2011)

Featuer # Summary Target Milestone Pirority/Estimate/Status Owner
1567 [1] QA Tests: Add recipe for LSB Tests and automate test 1.2 M1 [P2][5D] yi.zhao@windriver.com
1674 [2] run gtk+ over directfb 1.2 M1 [P2][D10] Xiaofeng.yan@windriver.com
1661 [3] meta-intel: streamline and clean up kernel config options and machine conf files 1.2 M1 [P2][5D] tom.zanussi@intel.com
1630 [4] Provide a click through license mechanism 1.2 M1 [P2][10D] New Owner? song.liu@intel.com
1589 [5] Disk space monitoring 1.2 M1 [P3][D10] liezhi.yang@windriver.com
1568 [6] QA Tests: Add recipe for ltp/posix tests and automate test 1.2 M1 [P2][3D] jiajun.xu@intel.com
1580 [7] Add Valgrind support in remote tools 1.2 M1 [P2][d5] jessica.zhang@intel.com
1461 [8] Put a uname and ab name in stdio 1.2 M1 [P3][D0] elizabeth.flanagan@intel.com
1629 [9] Buildstats memory measurements 1.2 M1 [P2][D3] elizabeth.flanagan@intel.com
1635 [10] Drop Grub for Syslinux 1.2 M1 [P2][5D] dvhart@linux.intel.com
1636 [11] Upgrade to EFI 1.2 M1 [P2][5D] dvhart@linux.intel.com
1634 [12] BSP update/intro 1.2 M1 [P2][5D] bruce.ashfield@windriver.com
1644 [13] Use cases 1.2 M1 [P1][2D] bruce.ashfield@windriver.com


Stabilize schedule

Release Candidate and Milestone Release schedule (Full Pass QA test follows every RC build)

  • RC1: 11/23/11
  • RC2: 11/30/11
  • RC3: 12/07/11
  • Release readiness meeting: 12/15/2011
  • M1 release: 12/16/11