The project will be managed as a series of 6-week milestones. The milestones will be broken out as follows:
- 1 week – planning for this milestone
- 4 weeks – development
- 1 week – stabilization
- 1 week – release
(The above time adds up to more than 6 weeks due to the planning week overlapping the release week).
The final project milestone is 4 weeks of stabilization and release.
At the end of each milestone there is a milestone release that:
- has been stabilized, with bugs tracked and showstoppers fixed
- has had some amount of QA applied beyond the nightly sanity test
- can demonstrate some feature or features
Milestones are divided into week-long "Sprints." This division prevents all of a milestone's functionality from hitting at the end of the milestone and causing a collision. Project developers must respect these divisions. it gives the maintainers a break.