Yocto Project 1.1 (release date: October 6, 2011)
The detailed milestone map for the 1.1 release of Yocto Project is as below. To view the Yocto schedule-at-a-glance, go to YoctoCalendar
pre-M1 (March 14 to April 18 -- Feature List and Schedule Defined April 18)
- Features Submitted to web - by April 1st
- Features prioritized and added to schedule - by April 12th
pre-M1 COMPLETED
M1 (Apr 18 to Jun 13 -- Design Complete Apr 25, Dev Complete May 23, Stabilize Complete Jun 6, Release Complete Jun 13)
M1 Design (Apr 18 to Apr 22)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Automatically generate package repos - design | automatically generate package repositories (and be able to \"use them\" -- to be defined) for both ipk and rpm/zypper combinations; also, documentation of this process is essential; this stage is the design phase. | 2 | Done | Team | Saul (Dexuan) | M1, Design |
OE Autobuilder rename | 1 | Done | Beth | Beth | M1, Design | |
Strip out LSB, non-LSB build work | Remove the LSB, non-LSB build work done at the end of 1.0 and re-incorporate it with sstate | 1 | Done | Beth | Beth | M1, Design - one minor problem |
M1 Sprint A (Apr 25 to Apr 29)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
OE-Core | Restructuring, renaming, rebranding | 1 | Done | RP Notes | Richard | M1, Sprint A - only remaining piece is for OE Core to work without setting a distro (wasn\'t originally scheduled) - this is a new task for EO this week |
SDK support in sanity test framework | This task includes enabling unfs and toolchain testing in sanity test framework, enabling toolchain testing on PRC autobuilder | 1 | Done | QA | Jiajun/Meilei | M1, Sprint A |
User Creation at preinstall - status check | Design status check | 1 | Done | RP Notes | Mark (ScottG) | M1, Sprint A architecture was sent out as RFC |
Check SRCREV in recipe files | should work, may need dev | 2 | Done | RP Notes | Richard/Ke | M1, Sprint A |
Refactor BSPs to use topic branches | crownbay and fish river island BSP need to be changed to make use of the new eg20t/emgd/gma500 topic branches | 2 | Done | Tom | Tom | M1, Sprint A When other branches (ex. FRI 2) are added, they will use topic branches. |
Additional config options | The following configurations need to be enabled to support DPDK: glibc > 2.7 (for features related to cpuset), kernel configuration: HPET and HPET MMAP configuration options enabled, all UIO kernel options enabled, HUGETLBFS enabled, PROC_PAGE_MONITOR enabled | 1 | 13-May | Rahul | Tom | M1, Sprint A Waiting on ECG |
Autobuilder maintenance | Bring scripts into configuration or get git repo working for those that can\'t be brought in. (takes 2 days) | 1 | 11-May | Beth | Beth | M1, Sprint A RFC is out. Beth/Richard need to talk May 10th. |
Retrospective | Hold a retrospective to discuss what went well and what can be improved in 1.1 with the meta-data team. | 1 | 12-May | Beth | Beth | M1, Sprint A - did with 1/2 of team; will do with next 1/2 this week |
M1 Sprint B (May 2 to May 6)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Layer Tooling - Design | Design/Architect the Layer Tooling approach | 1 | Done | Architect | Richard | M1 Sprint B Paul and PRC discussed this morning, and Paul has had some discussion with Richard. Don\'t have 100% of schedule. |
Test Plan | Create an overall Test Plan for 1.1 and post on Wiki | 1 | Done | Jiajun | Jiajun | M1, Sprint B |
Sync qemugl with MeeGo - Status check | This is a status check on how the work to sync qemugl with MeeGo is going. Completion set for M1, Sprint D. | 2 | Done | Meta-data | Saul (Edwin) | M1, Sprint B - on track. |
Finish LSB \"distribution\" work - QT3 | QT3 work is complete. | 2 | Done | Meta-data | WR Distro Team | M1, Sprint B - patch is pending, need to figure out landing location |
Incompatible License | Design and Review milestone | 2 | Done | Paul | Paul | M1, Sprint B - Paul will send an email next day or so. |
Changes for Image Creator - phase 1 | Phase 1: add mechanism to enable selection of server backend at runtime | 1 | Done | ADT Team | Jessica | M1, Sprint B |
Package Documentation Audit | Make changes defined in the package documentation audit from Yocto 1.0 | 2 | Done | from 1.0 | Scott G | M1, Sprint B - Scott is running the world build and we will examine the data to determine next steps. |
Fast boot analysis | Perform analysis to determine how best to implement a 2 second boot time | 1 | Done | Darren | Darren | M1, Sprint B - Darren has provided kernel data - http://dvhart.com/darren/yocto/boottime/. Still needs to do user space. |
Build Yocto behind firewall - plan | Josh/Darren define plan | 2 | Done | Dave | Darren, Joshua | M1, Sprint B - Josh put some comments and linked to git tree with a sanity check in bug 933. Josh put his plan and code beginnings in bugzilla. |
M1 Sprint C (May 9 to May 13)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
crazygit fetcher | TI issues with fetch2 - per LCS - should this be a P1? | 2 | 13-May | RP Notes | Saul (Ke) | M1, Sprint C |
multi-lib infrastructure | multi-lib support for 32-bit & 64-bit and capable of being installed at the same time - infrastructure in place (bbclass extend and multilib toolchain changes) | 1 | 13-May | from 1.0 | Richard (Qing) | M1, Sprint C |
Package config option enhancement - Plan | Plan our approach to package config option enhancement | 2 | 13-May | from 1.0 | Richard | M1, Sprint C |
Upstream our patches - phase 1 | Have upstream status updated on 90% of patches (so that we can have a status update) | 1 | Accept | Meta-data | Saul | M1, Sprint C - we won\'t be at 90% - Saul will have numbers by EOW and we can revise estimate. |
3G - Design | We have an ofono recipe but need some integration work done. This milestone is a status check and design update. HW needs to be received at this time. | 2 | Saul checking | Meta-data | Saul (Dongxiao) | M1, Sprint C Need hardware and infrastructure to test 3G (MeeGo team has this) |
pam patch integration | add PAM patches throughout the system switchable via the PAM feature (Mark H) | 2 | Mark checking | Meta-data | WR Distro team | M1, Sprint C - does WR Distro own? Need to get true timeline from them. Mark will follow up. |
Automatically generate package repos - complete | automatically generate package repositories (and be able to \"use them\" -- to be defined) for both ipk and rpm/zypper combinations as discussed during the Design phase; also, documentation of this process is essential | 2 | Saul checking | Team | Saul (Dexuan) | M1, Sprint C |
network based PR service | A network based service to repot PR value based on poky task checksum | 2 | 13-May | RP Notes | Jessica | M1, Sprint C |
User Creation at preinstall - complete | Deliverable completed | 1 | 13-May | RP Notes | Mark (ScottG) | M1, Sprint C - may have a slight slip |
BSP image creation | Add text on the website that tells users how to create images from the BSP source. Note: This may include a script to enable the creation. | 1 | 13-May | Tracey | Scott/Beth | M1, Sprint C - may be able to include Beth\'s scripts by EOW - Scott done |
Tarball Doc process | Right now tarball docs are frozen shortly before a release. The tarball never gets updated beyond that during subsequent documentation development. However, website docs are periodically updated as changes are made during the next development cycle. We need a documentation process where the tarball docs are updated along with the website docs. Perhaps releasing and building a separate documentation tarball is an answer... This whole scheme needs thought about and something implemented. | 1 | 13-May | From scratch | ScottR | M1, Sprint C - Just waiting for yocto-docs repo to be merged. |
Enhanced Performance | Also, environmental requirements/suggestions for expected performance - long-term goal is to build in under 1 hour; short-term goal is to build faster than v1.0This is a task to define the performance plan. | 1 | Accept | from 1.0 | Richard/Dongxiao | M1, Sprint C |
Disk Space Reduction | 2 | Saul checking | Team | WR Distro Team | M1, Sprint C - WR distro team has put out RFCs and waiting for comments - we need timeline | |
Share gcc work directories | 2 | Saul checking | Team | WR Distro Team | M1, Sprint C - WR distro team has put out RFCs and waiting for comments - we need timeline | |
kernel port to 2.6.37 | Port the kernel to 2.6.37 | 1 | Done | Darren | Darren | M1, Sprint C - complete, pending pull from Saul |
Tracing: Add Systemtap support for userspace tracing | Add utrace, etc | 2 | 13-May | Tom | Tom | M1, Sprint C |
M1 Sprint D (May 16 to May 20)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
multi-lib RPM | RPM support for multilib added | 1 | Accept | from 1.0 | Richard (Qing) | M1, Sprint D |
Image Creator - 1.0 finish | finish the Image Creator to add features pushed out from 1.0 - See https://wiki.yoctoproject.org/wiki/BitBake/GUI/PostOneOh for details | 1 | Accept | from 1.0 | Josh | M1 Sprint D |
Sync qemugl with MeeGo - COMPLETE | sync qemugl with MeeGo is complete | 2 | Accept | Meta-data | Saul (Edwin) | M1, Sprint D |
Finish LSB \"distribution\" work - ID failures | Identify issues in order to: Merge patches which are pushed during yocto 1.0. Add packages(qt3,xdg-* ...) LSB Test Suite need. Hardware platform x86 and ppc32(if qt4 can be supported) can be finished. | 2 | Accept | Meta-data | WR Distro Team | M1, Sprint D |
OE Comparison | Compare Yocto core set against integration work in OE and other distributions looking for bug fixes, (relevant) feature enhancements, and integration/policy hints. | 1 | Accept | Meta-data | Mark | M1, Sprint D |
End of package revision | Use the network based PR service to get the PR values which will go into package feed. | 2 | Accept | RP Notes | Jessica | M1, Sprint D |
x32 - plan | layer to support toolchain, libc, and kernel - Plan created | 2 | Accept | RP Notes | Saul (Nitin) | M1, Sprint D |
BBXM | Pull in bits from OE (kernel and uboot) | 1 | Accept | Darren | Darren | M1, Sprint D |
Eclipse-native tools interface | More integrated with upstream once there\'s integrated Linux tools that meets our need, e.g. lttng-remote | 2 | Accept | ADT Team | Jessica | M1, Sprint D |
Changes for Image Creator - phase 2 | Phase 2: Bug fix for 7.70 | 1 | Accept | ADT Team | Jessica | M1, Sprint D |
License tracking | Build a parser to do license tracking more gracefully and make sure all recipes are correct. (takes ~2 weeks) | 1 | Accept | Beth | Beth | M1, Sprint D |
Fix Documentation Publishing | fix our documentation publishing so that documents can be published at any time | 1 | Accept | Beth | Beth/Scott | M1, Sprint D |
Tracing: perf trace scripting support | Basically this means allowing perf to be built with the Perl and Python bindings, which turned out to be a headache last time. | 2 | Accept | from 1.0 | Tom | M1, Sprint D |
M1 Stabilize (May 23 to June 3)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Be prepared for Distro upgrades | Our release is right around the time of the 6monthly distro release dates, we should accommodate for this in our testing plan | 2 | Accept | Joshua | Jiajun | check latest distribution in M1 Stabilize, M2 Stabilize, and M3 Stabilize and test them in milestone testing; Should we include more Distributions, besides fedora, ubuntu and opensuse? |
Test Execution Plan | Create a Test Execution Plan for the milestone and send to developers | 1 | Accept | Jiajun | Jiajun | M1 Stabilize; M2 Stabilize; M3 Stabilize |
Development complete | All bugs targeted for 1.0.1 are in the 1.0.1 build. | 1 | Accept | Team | All | M1, Sprint3 to M1, Stabilize |
Stabilize schedule
Week 1
- Day 1, 2: Weekly test pass
- Day 3: Pre-Release Readiness meeting
- If there are issues:
- Day 4, 5: Fix issues and repeat Week 1
- If there are not issues:
- Day 4, 5 and beginning of Week 2: Complete a full test pass
Week 2
- Day 1, 2, 3: Complete full test pass
- Day 4: Release Readiness meeting
- If there are issues, fix and repeat from Week 1
- If there are not issues, proceed to Release phase
M1 Release (June 6 to June 13)
Follow Release Checklist, which includes:
- Release is packaged
- Release is pushed to mirrors
- Release is announced to community via mailing lists and blog
M2 (May 30 to Jul 25 -- Design Complete Jun 6, Dev Complete Jul 4, Stabilize Complete Jul 18, Release Complete Jul 25)
M2 Design (May 30 to June 3)
* Working week. No tasks complete this week.
M2 Sprint A (June 6 to June 10)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Live images | make live images their own image type | 2 | Accept | RP Notes | Saul | M2, Sprint A |
More test cases about toolchain in autobuilder | 2 | Accept | ADT Team | Jessica | Status check in M2, Sprint A, M3, Sprint A | |
Indigo update | Update to the latest Eclipse release (Indigo) | 2 | Accept | ADT Team | Jessica | Status check in M2, Sprint A, M3, Sprint A |
Systemtap integration | Make it easy and convenient for the user to write and execute Systemtap scripts from the IDE. http://www.eclipse.org/linuxtools/projectPages/systemtap/ might provide a good starting point and may be something we can contribute to. We may also need to contribute further up the chain to provide e.g. remote target capabilities. | 2 | Accept | Tom | Jessica | Status check in M2, Sprint A, M3, Sprint A |
\'perf scripting\' integration | Make it easy and convenient for the user to write and execute \'perf scripts\' from the IDE. We should be able to leverage and build on the Systemtap integration for this. | 2 | Accept | Tom | Jessica | Status check in M2, Sprint A, M3, Sprint A |
Finish LSB \"distribution\" work - complete | Complete all work: Merge patches which are pushed during yocto 1.0. Add packages(qt3,xdg-* ...) LSB Test Suite need. Hardware platform x86 and ppc32(if qt4 can be supported) can be finished. | 2 | Accept | Meta-data | WR Distro Team | M2, Sprint A |
M2 Sprint B (June 13 to June 17)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Layer Tooling - Architecture | Implement Layer Tooling changes | 1 | Accept | Architect | Richard (Paul/Daoxien will help) | M2 Sprint B |
Error handling in bitbake | desc | 1 | Accept | RP Notes | Saul (Scott G) | M2, Sprint B |
Package config option enhancement - Implement | Implement approach defined in plan for package config option enhancement | 2 | Accept | from 1.0 | Saul | M2, Sprint B |
Upstream our patches - phase 2 | Everyone has attempted upstreams for patches defined from phase 1 | 1 | Accept | Meta-data | Saul | M2, Sprint B |
MeeGo GPLv2 Sync | compare with Yocto, sync any patches | 2 | Accept | RP Notes | Saul (Ke) | M2, Sprint B |
Directory Ownership | 1.5 | Accept | RP Notes | Mark (w/Qing) | M2, Sprint B | |
Changes for Image Creator - phase 3 | Phase 3: package format job done + image output type job done | 1 | Accept | ADT Team | Jessica | M2, Sprint B |
Meta targets | Part of the challenge of autobuilder is that you have to go into autobuilder, edit script, reconfigure, to change just one build target. This is error prone. What we need is a meta-target where Beth can say she wants to build Poky-image-sato for QEMU x86 and have it just do that. Beth thinks this is done via an override to the web page. (takes ~2 weeks) | 1 | Accept | Beth | Beth | M2, Sprint B |
kernel bloat - analysis | target = boot a minimal image in < 8M - analysis complete | 1 | Accept | Darren | Darren | M2, Sprint B |
M2 Sprint C (June 20 to June 24)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
multi-lib complete | multi-lib support for 32-bit & 64-bit and capable of being installed at the same time fully complete | 1 | Accept | from 1.0 | Richard (Qing) | M2, Sprint C - exact date TBD |
Monitor disk availability | Monitor disk availability and warn the user if it is running low. May only focus on a few directories, for example: poky/build and poky/build/downloads, this would solve the multiple mount point problem | 2 | Review | RP and Robert | WR Distro Team | M2, Sprint C |
btrfs | 2 | Accept | Meta-data | Saul (Nitin) | M2, Sprint C | |
adding eglibc config control | this goes with the package config options | 1.5 | Accept | RP Notes | Mark | M2, Sprint C |
Implement Continuous Autobuilds | Build constantly instead of daily (need fuzz builds for this. once fuzz builds are implemented, this is trivial) | 2 | Accept | from 1.0 | Beth | M2, Sprint C |
M2 Sprint D (June 27 to July 1)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Image Creator polish | polish and refine Image Creator - See https://wiki.yoctoproject.org/wiki/BitBake/GUI/PostOneOh for details | 1 | Accept | from 1.0 | Josh | M2, Sprint D |
Clean up warning messages | A build that runs correctly to completion still includes a ton of WARNING messages. We need a project to clean these up. Beth will work on License Warnings, team will look at other logfile warnings | 2 | Accept | davest and RP | Saul | M2, Sprint D |
3G - Complete | We have an ofono recipe but need some integration work done - This milestone checks that 3G is complete. | 2 | Accept | Meta-data | Saul (Dongxiao) | M2, Sprint D |
running post installs at rootfs gen time | 2 | Accept | RP Notes | Saul (Dexuan) | M2, Sprint D | |
remove gnome-vfs | 3 | Accept | RP Notes | Saul (Edwin) | M2, Sprint D | |
x32 - complete | layer to support toolchain, libc, and kernel - x32 is complete | 2 | Accept | RP Notes | Saul (Nitin) | M2, Sprint D |
BSP update/intro | determine and integrate / create arch reference BSPs (e500, Cortex, ARM, MIPs) | 2 | Accept | Bruce/Richard/team | Bruce | M2, Sprint D |
Changes for Image Creator - phase 4 | Phase 4: complete plug-in | 1 | Accept | ADT Team | Jessica | M2, Sprint D |
Enhance the deploy part in remote debug | ADT is currently using org.eclipse.cdt.remote.launch for remote debug. One limitation in this plug-in is that it can only deploy one single file to the target during the debug. Though it is ok for debugging static linked program, debugging dynamic linked program might require deploying multiple files(including executables and libraries) to the target. | 2 | Accept | Lianhao | Jessica | M2 Sprint D |
BSP builds | Autobuilder git fetcher improvements (3 days) | 2 | Accept | from 1.0 | Beth | M2, Sprint D |
kernel bloat - development | target = boot a minimal image in < 8M - development complete | 1 | Accept | Darren | Darren | M2, Sprint D |
Tracing: Systemtap usability in Yocto | Right now, there are instructions on the wiki on how to configure and use Systemtap with Yocto. While straightforward, they are tedious and unlikely to be useful to most people pressed for time. We need to make it easier to use - in addition to documentation/HOWTO tasks listed elsewhere on this page, we need to make it usable \'out of the box\' (i.e. outside of ADT) e.g. all paths and configuration handled via script or something similar | 2 | Accept | Tom | Tom | M2, Sprint D |
Tracing/profiling HOWTOs | Create a document or extend the current Yocto tracing wiki page to explain in detail how to use all the tracing tools in Yocto. It should detail not only how to use each tool individually, but also how to use them in conjunction with each other, highlighting situations in which each is most useful. There should also be some extensive worked examples of real-life use-cases and how they could be investigated using the Yocto tracing/profiling tools. | 2 | Accept | Tom | Tom | M2, Sprint D |
M2 Stabilize (July 4 to July 15)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Be prepared for Distro upgrades | Our release is right around the time of the 6monthly distro release dates, we should accommodate for this in our testing plan | 2 | Accept | Joshua | Jiajun | check latest distribution in M1 Stabilize, M2 Stabilize, and M3 Stabilize and test them in milestone testing; Should we include more Distributions, besides fedora, ubuntu and opensuse? |
Test Execution Plan | Create a Test Execution Plan for the milestone and send to developers | 1 | Accept | Jiajun | Jiajun | M1 Stabilize; M2 Stabilize; M3 Stabilize |
Lock kernel version | lock the kernel version | 1 | Accept | Team | Darren | M2, Stabilize (ww29) |
Stabilize schedule
Week 1
- Day 1, 2: Weekly test pass
- Day 3: Pre-Release Readiness meeting
- If there are issues:
- Day 4, 5: Fix issues and repeat Week 1
- If there are not issues:
- Day 4, 5 and beginning of Week 2: Complete a full test pass
Week 2
- Day 1, 2, 3: Complete full test pass
- Day 4: Release Readiness meeting
- If there are issues, fix and repeat from Week 1
- If there are not issues, proceed to Release phase
M2 Release (July 18 to July 22)
Follow Release Checklist, which includes:
- Release is packaged
- Release is pushed to mirrors
- Release is announced to community via mailing lists and blog
M3 (Jul 11 to Aug 15 -- Design Complete Jul 18, Dev Complete Jul 25, Stabilize Complete Aug 8, Release Complete Aug 15)
M3 Design (Jul 11 to Jul 15)
* Working week. No tasks complete this week.
M3 Sprint A (Jul 18 to Jul 22)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Upstream our patches - phase 3 | Another round of updates is complete | 1 | Accept | Meta-data | Saul | M3, Sprint A |
Sanity checks on per recipe basis | 2 | Accept | RP Notes Bug#405 | Saul (Scott G) | M3, Sprint A | |
Ability to build SRPM | 3 | Accept | RP Notes | Jeff Polk/Mark | M3, Sprint A - Julie to check with Jeff | |
Fish River Island/Fish River Island II BSP(s) | The base Fish River Island BSP exists already, we now need to add support for the extra devices, and add support for changes introduced by Fish River Island II | 2 | Accept | Tom | Tom | M3, Sprint A |
More test cases about toolchain in autobuilder | 2 | Accept | ADT Team | Jessica | Status check in M2, Sprint A, M3, Sprint A | |
Indigo update | Update to the latest Eclipse release (Indigo) | 2 | Accept | ADT Team | Jessica | Status check in M2, Sprint A, M3, Sprint A |
Systemtap integration | Make it easy and convenient for the user to write and execute Systemtap scripts from the IDE. http://www.eclipse.org/linuxtools/projectPages/systemtap/ might provide a good starting point and may be something we can contribute to. We may also need to contribute further up the chain to provide e.g. remote target capabilities. | 2 | Accept | Tom | Jessica | Status check in M2, Sprint A, M3, Sprint A |
\'perf scripting\' integration | Make it easy and convenient for the user to write and execute \'perf scripts\' from the IDE. We should be able to leverage and build on the Systemtap integration for this. | 2 | Accept | Tom | Jessica | Status check in M2, Sprint A, M3, Sprint A |
Additions to build stats | 1 | Accept | Beth | Beth | M3, Sprint A | |
Alpha | Begin an alpha program after the stabilization period for M3. | 1 | Accept | Team | Julie | M3, Sprint A |
Publish Shared State | Publish the shared state information. | 2 | Review | LCS | Beth | M3, Sprint A if Richard confirms some answers to questions |
Fast boot time | 2 second boot time target | 1 | Accept | Team | Darren | M3, Sprint A - analysis will be complete to show where slowdown is coming from (BIOS or elsewhere); the earliest we can get a system that can use BLDK is August 1st, so getting to the 2s target in 1.1 is not likely |
Update Quick Start for 1.1 | Ensure Quick Start guide has latest 1.1 information, including details on how to use Image Creator. | 2 | Accept | Dave | ScottR | M3, Sprint A |
Update Reference Manual for 1.1 | Ensure Reference Manual has the latest 1.1 information, including details on how to use Image Creator. | 2 | Accept | Dave | ScottR | M3, Sprint A |
M3 Stabilize (Jul 25 to Aug 5)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Be prepared for Distro upgrades | Our release is right around the time of the 6monthly distro release dates, we should accommodate for this in our testing plan | 2 | Accept | Joshua | Jiajun | check latest distribution in M1 Stabilize, M2 Stabilize, and M3 Stabilize and test them in milestone testing; Should we include more Distributions, besides fedora, ubuntu and opensuse? |
Test Execution Plan | Create a Test Execution Plan for the milestone and send to developers | 1 | Accept | Jiajun | Jiajun | M1 Stabilize; M2 Stabilize; M3 Stabilize |
Stabilize schedule
Week 1
- Day 1, 2: Weekly test pass
- Day 3: Pre-Release Readiness meeting
- If there are issues:
- Day 4, 5: Fix issues and repeat Week 1
- If there are not issues:
- Day 4, 5 and beginning of Week 2: Complete a full test pass
Week 2
- Day 1, 2, 3: Complete full test pass
- Day 4: Release Readiness meeting
- If there are issues, fix and repeat from Week 1
- If there are not issues, proceed to Release phase
M3 Release (Aug 8 to Aug 15)
Follow Release Checklist, which includes:
- Release is packaged
- Release is pushed to mirrors
- Release is announced to community via mailing lists and blog
M4 (Aug 15 to Oct 6 -- Stabilize Complete Aug 29, Release Complete Oct 3)
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Yocto Project Development Guide | This manual would be an over-arching document that frames the complete development cycle within Yocto Project. The idea here is that the document would be an umbrella document that spawned and referenced subsequent documents. The organization would be the first chapter overviews the major development pieces such as recipe creation, building, debugging, publishing, fail-safing, back-door hook creation, etc. This manual will also include migration information. Scoping would be about two weeks and length would probably be about 40 pages. Overall development time will likely take up to the release given my experience on the creation of the ADT manual (there is no uniterruped time). | 1 | Not Started | from scratch | ScottR | M4, Scott will send the more detailed milestones |
Various Demo Videos | The idea here is to create screen-capture type tutorials similar to what exists for the ADT Eclipse Plug-in. However, we want to contract out some help for professional voice-over talent to be used with the images. These don\'t have to be limited to screen-capture material but could include well-done PPT decks - similar to how other business units in Intel create various training modules. For 1.1 it would be good to capture the script for the existing ADT Eclipse Plug-in module and have it voiced over. Also, for 1.1 it would be good to create a similar module for the Image Creator application. | 2 | Not Started | From ADT module and scratch | ScottR | Q3 at the earliest |
Open-source Newbie Information | This information will be for developers new to open-source. These people do not know what IRC means. Targeted for developers coming from a non-open-source environment. I think the best place for this information would be the website. I haven\'t looked yet but I suspect information already exists on the web. For Yocto it will be a matter of collecting the best and most useful information, orginizing it and properly referencing/leveraging it. | 2 | Not Started | From scratch | ScottR | M4, this is part of the Yocto Development Guide |
OOB documentation | Create an out of box guide for giveaway systems built using Yocto. | 1 | Accept | Julie | ScottR | Julie to research timing on this. ~Q3 is current thinking. |
Group | Feature Name | Description | Priority | Status | Owner | Source | Comments / Bugzilla Links |
Project | Release Candidate 1 | RC1 generated | 1 | Aug-29 | Beth | Team | |
Project | Release Candidate 2 | RC2 generated | 1 | Sep-5 | Beth | Team | |
Project | Release Candidate 3 | RC3 generated | 1 | Sep-12 | Beth | Team | |
Project | Release Candidate 4 | RC4 generated | 1 | Sep-19 | Beth | Team | |
Project | Release Readiness | Release Readiness Meeting | 1 | Sep-26 | Julie | Julie | |
QA | Holiday | QA team on holiday Oct 1 - 7 | 1 | Oct 1-7 | QA | QA |
Not Scheduled List
Feature Name | Description | Priority | Status | Source | Owner | Comments / Bugzilla Links |
Web-based Image Creator | Create a web-based interface that does what the Image Creator does. | 2.5 | Review | LCS | Jason Kridner? | not scheduled at this time - depends on Image Creator completing |
Recipe-specific sysroot | 3 | Review | from 1.0 | Saul (Dongxiao) | not scheduled at this time (1 month task) | |
Handle old versions in WORKDIR | 3 | Review | from 1.0 | Not scheduled at this time | ||
Executable images | Create images that are executable - for example a pre-installed Ubuntu image with YP installed | 3 | Review | LCS | Not scheduled at this time | |
Self-hosting image | Create customizable chroot; Build an image that would be self-hosting | 2.5 | Review | LCS | Not scheduled at this time | |
Yocto OOPS-type messages | add the equivalent of kernel OOPS to Yocto | 2.5 | Review | LCS | Not scheduled at this time | |
Reduced depth revision history | Decrease the depth of the revision history | 3 | Review | LCS | Not scheduled at this time | |
Open Source Test Cases | Perform technical, legal, and QA steps necessary to move test cases into open source. | 3 | Review | QA | not scheduled at this time | |
Test framework | this is a test framework that we can include in the distribution | 3 | Review | RP Notes | not scheduled at this time - Is it the TI’s test framework we discussed before? A: Not necessarily, we\'re still waiting for someone to step up and really take ownership of this area but it needs some resource commitment as its not a simple task. | |
Replacement for video/audio players currently in Yocto | Codec… | 3 | Review | Meta-data | Not scheduled at this time | |
Investigate New UI | For demos, we would like need a reference UI that is not Sato. Investigate possibilities that the Yocto team won\'t need to maintain. OpenBox? Gnome-desktop? GP? LXDE? KDE Mobile? | 3 | Review | Meta-data | Not scheduled at this time | |
Qemugl upstreaming | Opengl ES Support | 3 | Review | Meta-data | Not scheduled at this time | |
selinux patch integration | add SE Linux patches in a similar way to PAM | 3 | Review | Meta-data | Not scheduled at this time | |
Framework to support multiple library versions co-existing | similar to recipe specific sysroot; needs documentation | 3 | Review | Team | Saul (Dongxiao?) | Not scheduled at this time - we just need to document how to use multiple versions of a library using clutter as the example |
Embedded java environment or even JDK support | 3 | Review | Team | Not scheduled at this time | ||
gtk+ sato filechooser patch | 3 | Review | RP Notes | Not scheduled at this time | ||
sato refresh | 3 | Review | RP Notes | Not scheduled at this time | ||
Secure login | 2 | Review | ADT Team | Jessica | not scheduled at this time | |
Prebuit SDK integration | speedup target image generation by reusing prebuilt tools from SDK native and target binaries. See: http://wiki.secretlab.ca/Yocto_prebuilt_SDK_integration | 2 | Reject | Adrian | Jessica | not scheduled at this time - This functionality looks to have been provided by sstate packages? |
Patch Test System | Create a machine where developers can upload/test patches before submitting them to master to ensure builds won\'t break when patches are added. (developer autobuilders? Fuzz builds?) | 2 | Review | Team | Jiajun | not scheduled at this time - although, team is investigating other mechanisms for ensuring that patches submitted don\'t break build |
Tracing: tuna, oscilloscope recipes | catch up with Tom, likely to remove | 3 | Review | from 1.0 | not scheduled at this time | |
Patchwork | is it worth the overhead, are there alternatives | 3 | Review | RP Notes | not scheduled at this time | |
Bugzilla to Wiki | Create a script which automatically populates and updates the Wiki based on changes in bugzilla. | 2.5 | Review | Darren | not scheduled at this time |