The project will be managed as a series of 6-week milestones. The milestones will be broken out as follows:
The project will be managed as a series of 6-8-week milestones. The milestones will be broken out as follows:


* 1 week – planning for this milestone
* 1 week – planning and development week
* 4 weeks – development
* 4 weeks – development
* 1 week – stabilization
* 1-2 week – stabilization
* 1 week – release
* 1 week – release


(The above time adds up to more than 6 weeks due to the planning week overlapping the release week).
(The above time adds up to more than 6-8 weeks due to the planning week overlapping the release week).


The final project milestone is 4 weeks of stabilization and release.
The final project milestone is 4-8 weeks of stabilization and release.


At the end of each milestone there is a milestone release that:
At the end of each milestone there is a milestone release that:
Line 16: Line 16:
* can demonstrate some feature or features
* can demonstrate some feature or features


Milestones are divided into week-long "Sprints."  This division prevents all of a milestone's functionality from hitting at the end of the milestone and causing a collision. Project developers must respect these divisionsit gives the maintainers a break.
Each developer is expected to focus on 1-2 features/tasks at a time, which can help the team focus and also prevent from sending all pull requests at the end of a milestone. Project developers must respect this ruleIt gives the maintainers a break.

Revision as of 12:39, 7 November 2011

The project will be managed as a series of 6-8-week milestones. The milestones will be broken out as follows:

  • 1 week – planning and development week
  • 4 weeks – development
  • 1-2 week – stabilization
  • 1 week – release

(The above time adds up to more than 6-8 weeks due to the planning week overlapping the release week).

The final project milestone is 4-8 weeks of stabilization and release.

At the end of each milestone there is a milestone release that:

  • has been stabilized, with bugs tracked and showstoppers fixed
  • has had some amount of QA applied beyond the nightly sanity test
  • can demonstrate some feature or features

Each developer is expected to focus on 1-2 features/tasks at a time, which can help the team focus and also prevent from sending all pull requests at the end of a milestone. Project developers must respect this rule. It gives the maintainers a break.