Yocto 1.2 Schedule: Difference between revisions
From Yocto Project
Jump to navigationJump to search
No edit summary |
|||
Line 2: | Line 2: | ||
---- | ---- | ||
The detailed milestone map for the 1.2 release of Yocto Project is as below. | The detailed milestone map for the 1.2 release of Yocto Project is as below. | ||
To view the Yocto schedule-at-a-glance, go to [[YoctoCalendar]] | To view the Yocto schedule-at-a-glance, go to [[YoctoCalendar]]. Please note that the estimation for each feature is done based on 'perfect day'. The purpose of the estimation is to estimate the relative size of features, NOT to predict when a single feature could be done. | ||
== M1 (Oct. 31 to Dec. 16, 2011 -- 7 weeks: planning done in week 1, development week 1-4, stablization week 5-6, release week 7) == | == M1 (Oct. 31 to Dec. 16, 2011 -- 7 weeks: planning done in week 1, development week 1-4, stablization week 5-6, release week 7) == |
Revision as of 21:46, 31 October 2011
Yocto Project 1.2 (release date: April 6, 2012)
The detailed milestone map for the 1.2 release of Yocto Project is as below. To view the Yocto schedule-at-a-glance, go to YoctoCalendar. Please note that the estimation for each feature is done based on 'perfect day'. The purpose of the estimation is to estimate the relative size of features, NOT to predict when a single feature could be done.
M1 (Oct. 31 to Dec. 16, 2011 -- 7 weeks: planning done in week 1, development week 1-4, stablization week 5-6, release week 7)
M1 Feature Development (Oct. 31 to Nov. 23, 2011)
Featuer # | Summary | Target Milestone | Pirority/Estimate/Status | Owner |
1567 [1] | QA Tests: Add recipe for LSB Tests and automate test | 1.2 M1 | [P2][5D] | yi.zhao@windriver.com |
1674 [2] | run gtk+ over directfb | 1.2 M1 | [P2][D10] | Xiaofeng.yan@windriver.com |
1661 [3] | meta-intel: streamline and clean up kernel config options and machine conf files | 1.2 M1 | [P2][5D] | tom.zanussi@intel.com |
1630 [4] | Provide a click through license mechanism | 1.2 M1 | [P2][10D] New Owner? | song.liu@intel.com |
1589 [5] | Disk space monitoring | 1.2 M1 | [P3][D10] | liezhi.yang@windriver.com |
1568 [6] | QA Tests: Add recipe for ltp/posix tests and automate test | 1.2 M1 | [P2][3D] | jiajun.xu@intel.com |
1580 [7] | Add Valgrind support in remote tools | 1.2 M1 | [P2][d5] | jessica.zhang@intel.com |
1461 [8] | Put a uname and ab name in stdio | 1.2 M1 | [P3][D0] | elizabeth.flanagan@intel.com |
1629 [9] | Buildstats memory measurements | 1.2 M1 | [P2][D3] | elizabeth.flanagan@intel.com |
1635 [10] | Drop Grub for Syslinux | 1.2 M1 | [P2][5D] | dvhart@linux.intel.com |
1636 [11] | Upgrade to EFI | 1.2 M1 | [P2][5D] | dvhart@linux.intel.com |
1634 [12] | BSP update/intro | 1.2 M1 | [P2][5D] | bruce.ashfield@windriver.com |
1644 [13] | Use cases | 1.2 M1 | [P1][2D] | bruce.ashfield@windriver.com |
Stabilize schedule
Release Candidate and Milestone Release schedule (Full Pass QA test follows every RC build)
- RC1: 11/23/11
- RC2: 11/30/11
- RC3: 12/07/11
- Release readiness meeting: 12/15/2011
- M1 release: 12/16/11