== M4 (Mar. 5 to Apr. 27, 2012 -- 2 weeks: planning done in week 1, development week 1-4, stabilization week 5-7, release week 8) ==
== M4 (Mar. 5 to Apr. 27, 2012 -- 8 weeks: planning done in week 1, development week 1-4, stabilization week 5-7, release week 8) ==
=== M4 Feature Development (Mar. 5 to Apr. 27, 2012) ===
=== M4 Feature Development (Mar. 5 to Apr. 27, 2012) ===
{| border="1"
{| border="1"

Revision as of 23:28, 6 November 2011

Yocto Project 1.2 (release date: April 6, 2012)


The detailed milestone map for the 1.2 release of Yocto Project is as below. To view the Yocto schedule-at-a-glance, go to YoctoCalendar. Please note that the estimation for each feature is done based on 'perfect day'. The purpose of the estimation is to estimate the relative size of features, NOT to predict when a single feature could be done.

M1 (Oct. 31 to Dec. 23, 2011 -- 8 weeks: planning done in week 1, development week 1-5, stabilization week 6-7, release week 8)

M1 Feature Development (Oct. 31 to Dec. 23, 2011)

Featuer # Summary Target Milestone Pirority/Estimate/Status Owner
1567 QA Tests: Add recipe for LSB Tests and automate test 1.2 M1 [P2][5D] yi.zhao@windriver.com
1674 run gtk+ over directfb 1.2 M1 [P2][D10] Xiaofeng.yan@windriver.com
1660 crownbay: add support for video acceleration 1.2 M1 [P2][10D] tom.zanussi@intel.com
1661 meta-intel: streamline and clean up kernel config options and machine conf files 1.2 M1 [P2][5D] tom.zanussi@intel.com
1008 New santiy check for userspace packages 1.2 M1 [P2][D4] scott.a.garman@intel.com
1598 Add remote layer support 1.2 M1 [P3][D5][Design] paul.eggleton@linux.intel.com
1565 Package History: Data Collection 1.2 M1 [P1][D4] paul.eggleton@linux.intel.com
1589 Disk space monitoring 1.2 M1 [P3][D10] liezhi.yang@windriver.com
1603 Add recipe supporting autoconf-nativesdk and automake-nativesdk 1.2 M1 [P2] [D10] kai.kang@windriver.com
1582 Host intrusion prevention/Swabber 1.2 M1 [P2][10D][Design] josh@linux.intel.com
1568 QA Tests: Add recipe for ltp/posix tests and automate test 1.2 M1 [P2][3D] jiajun.xu@intel.com
1580 Add Valgrind support in remote tools 1.2 M1 [P2][d10][Design] jessica.zhang@intel.com
1461 Put a uname and ab name in stdio 1.2 M1 [P3][D0] elizabeth.flanagan@intel.com
1546 License file WARNING messages 1.2 M1 [P1][D1] elizabeth.flanagan@intel.com
1627 Autobuilder clean sstate option 1.2 M1 [P2][D1] elizabeth.flanagan@intel.com
1629 Buildstats memory measurements 1.2 M1 [P2][D3] elizabeth.flanagan@intel.com
1635 Drop Grub for Syslinux 1.2 M1 [P2][5D] dvhart@linux.intel.com
1636 Upgrade to EFI 1.2 M1 [P2][5D] dvhart@linux.intel.com
1564 Multilib: Drop MULTILIB_IMAGE_INSTALL 1.2 M1 [P2][D3] dongxiao.xu@intel.com
1634 BSP update/intro 1.2 M1 [P2][5D][Design] bruce.ashfield@windriver.com
1644 Use cases 1.2 M1 [P1][2D][Design review] bruce.ashfield@windriver.com


M1 Stabilize schedule

Release Candidate and Milestone Release schedule (Full Pass QA test follows every RC build)

  • RC1: 11/30/11
  • RC2: 12/7/11
  • RC3: 12/14/11
  • M1 Release readiness meeting: 12/21/2011
  • M1 release: 12/23/11

M2 (Dec. 12, 2011 to Jan. 27, 2012 -- 7 weeks: planning done in week 1, development week 1-4, stabilization week 5-6, release week 7)

M2 Feature Development (Dec. 12, 2011 to Jan. 27, 2012)

Featuer # Summary Target Milestone Pirority/Estimate/Status Owner
1655 Export of source tarball or package 1.2 M2 [P3] [10D] Xiaofeng.yan@windriver.com
1678 kernel usability scripts 1.2 M2 [P2][10D] tom.zanussi@intel.com
1630 Provide a click through license mechanism 1.2 M2 [P2][10D] tom.zanussi@intel.com
1543 Improve error handling and feedback to users 1.2 M2 [P1][D15] scott.a.garman@intel.com
1557 Build Appliance: Pre-configured VM Build image built by Yocto 1.2 M2 [P1][D30] for 2 people saul.wold@intel.com
1654 Layer tooling: Tool to combine layers 1.2 M2 [P3][D1] paul.eggleton@linux.intel.com
1566 Package History: Data Analysis 1.2 M2 [P1][D15] paul.eggleton@linux.intel.com
1651 Incremental image generation 1.2 M2 [P3][D10] liezhi.yang@windriver.com
1682 A scripts to clean obsolote sstate cache files 1.2 M2 [P3][D10] liezhi.yang@windriver.com
1126 pending tasks and discussion about the networked PR service 1.2 M2 [P2][D5] for first 3 tasks in the wiki pages, other tasks pending community feedback lianhao.lu@intel.com
1555 Make BasicHash the default signature generator 1.2 M2 [P1][D1] it wouldn\'t be much workload after we close the bug #1556 and #1126 lianhao.lu@intel.com
1556 Handled Releases with the PR server 1.2 M2 [P1][D10] Need community feedback after we have a working code branch lianhao.lu@intel.com
1656 Recipe creation/import script 1.2 M2 [P3][15D] kai.kang@windriver.com
1608 Improve device management 1.2 M2 [P2][1D] josh@linux.intel.com
1610 Eclipse BSP/Kernel Plugin 1.2 M2 [p2][d5] jessica.zhang@intel.com
1612 Build statistics reporting 1.2 M2 [P2][D16] elizabeth.flanagan@intel.com
1628 Autobuilder layer support 1.2 M2 [P2][D4] elizabeth.flanagan@intel.com
1614 Target module build 1.2 M2 [P3][3D] dvhart@linux.intel.com
1642 Minimal Image unique 1.2 M2 [P2][15D] dvhart@linux.intel.com
1647 Upstream config fragments 1.2 M2 [P2][2D] dvhart@linux.intel.com
1649 Define Kernel policy 1.2 M2 [P2][10D] dvhart@linux.intel.com
1621 Running post installs at rootfs gen time 1.2 M2 [P2][D10] dexuan.cui@intel.com
1643 Kernel Tools 1.2 M2 [P2][10D] bruce.ashfield@windriver.com
1638 replace qemuppc 1.2 M2 [P2] [15D] bruce.ashfield@windriver.com


M2 Stabilize schedule

Release Candidate and Milestone Release schedule (Full Pass QA test follows every RC build)

  • RC1: 1/4/12
  • RC2: 1/11/12
  • M2 Release readiness meeting: 1/18/12 or 1/25/12
  • M2 release: 1/27/12

M3 (Jan. 23 to Mar. 16, 2012 -- 9 weeks: planning done in week 1-2, development week 1-6, stabilization week 7-8, release week 9)

M3 Feature Development (Jan. 23 to Mar. 16, 2012)

Featuer # Summary Target Milestone Pirority/Estimate/Status Owner
1551 Tracing: Systemtap usability in Yocto 1.2 M3 [P2][5D] tom.zanussi@intel.com
1552 Tracing: create separate recipe for perf 1.2 M3 [P2][5D] tom.zanussi@intel.com
1553 Tracing: perf trace scripting support 1.2 M3 [P3][5D] tom.zanussi@intel.com
542 bitbake \"NoProvider\" message doesn\'t aid in resolving the problem 1.2 M3 [P1][D5] scott.a.garman@intel.com
1127 Improve the error reporting when SkipPackage error is raised 1.2 M3 [P1][D5] scott.a.garman@intel.com
1141 bitbake -b prints meaningless error when given an invalid recipe name 1.2 M3 [P1][D4] scott.a.garman@intel.com
1143 Remove python stack trace when do_patch fails 1.2 M3 [P1][D6] scott.a.garman@intel.com
1145 Make bitbake output less noisy for non-error cases 1.2 M3 [P1][D5] scott.a.garman@intel.com
1540 Display a summary of warnings and errors at the end of a bitbake command 1.2 M3 [P1][D4] scott.a.garman@intel.com
1606 Investigate New UI 1.2 M3 [P4][D2] paul.eggleton@linux.intel.com
1620 Finish Oracle/Sun Hotspot JDK/JRE support 1.2 M3 [P2][5D] Can someone else own? nitin.a.kamble@intel.com
1611 enhance the bitbake commander eclipse plugin 1.2 M3 [p2][d10] lianhao.lu@intel.com
1561 Enable cleanup of WORKDIR 1.2 M3 [P3][D5] kai.kang@windriver.com
1625 Init 1.2 M3 [P2][10D] josh@linux.intel.com
717 Improve syslog configurability 1.2 M3 [P?] josh@linux.intel.com
1617 \'perf scripts\' integration 1.2 M3 [p2][d5] jessica.zhang@intel.com
874 [AutoBuilder/FEAT] Set Bug to Fixed automatically when building in AutoBuilder 1.2 M3 [P2][D3] elizabeth.flanagan@intel.com
1547 License file cleanup 1.2 M3 3 Stages: Stage1: [P1][D4] Stage2: [P2][D10] Stage3: [P3][D5] elizabeth.flanagan@intel.com
37 sato-icon-theme lacks generic / unknown icon 1.2 M3 [P2][3D] edwin.zhai@intel.com
1645 kernel bloat - development 1.2 M3 [P2][5D] dvhart@linux.intel.com
1646 Fast boot time 1.2 M3 [P2][15D] dvhart@linux.intel.com


M3 Stabilize schedule

Release Candidate and Milestone Release schedule (Full Pass QA test follows every RC build)

  • RC1: 2/22/12
  • RC2: 2/29/12
  • RC3: 3/7/12
  • M3 Release readiness meeting: 3/14/12
  • M3 release: 3/16/12


M4 (Mar. 5 to Apr. 27, 2012 -- 8 weeks: planning done in week 1, development week 1-4, stabilization week 5-7, release week 8)

M4 Feature Development (Mar. 5 to Apr. 27, 2012)

Featuer # Summary Target Milestone Pirority/Estimate/Status Owner
1640 Tracing/profiling HOWTOs 1.2 M4 [P2][10D+5D] tom.zanussi@intel.com
1648 Real-time process-executed timers 1.2 M4 [P3][20D] dvhart@linux.intel.com


M4 Stabilize schedule

Release Candidate and Milestone Release schedule (Full Pass QA test follows every RC build)

  • RC1: 3/28/12
  • RC2: 4/4/12
  • RC3: 4/11/12
  • RC4: 4/18/12
  • M4 Release readiness meeting: 4/25/12
  • Yocto Project 1.2 release: 4/27/12