(Created page with "= Yocto Project 1.2 (release date: April 6, 2012) = ---- The detailed milestone map for the 1.2 release of Yocto Project is as below. To view the Yocto schedule-at-a-glance, go t...")
 
No edit summary
Line 3: Line 3:
The detailed milestone map for the 1.2 release of Yocto Project is as below.
The detailed milestone map for the 1.2 release of Yocto Project is as below.
To view the Yocto schedule-at-a-glance, go to [[YoctoCalendar]]
To view the Yocto schedule-at-a-glance, go to [[YoctoCalendar]]
<span style="color:red">'''pre-M1 COMPLETED'''</span>


== M1 (Oct. 31 to Dec. 16, 2011 -- 7 weeks: planning done in week 1, development week 1-4, stablization week 5-6, release week 7) ==
== M1 (Oct. 31 to Dec. 16, 2011 -- 7 weeks: planning done in week 1, development week 1-4, stablization week 5-6, release week 7) ==
Line 47: Line 45:


==== Stabilize schedule ====
==== Stabilize schedule ====
'''Release Candidate and Milestone Release schedule (Full Pass QA  test follows every RC build)'''
'''Release Candidate and Milestone Release schedule (Full Pass QA  test follows every RC build)'''
* RC1: 11/23/11
* RC1: 11/23/11
* RC2: 11/30/11
* RC2: 11/30/11

Revision as of 21:43, 31 October 2011

Yocto Project 1.2 (release date: April 6, 2012)


The detailed milestone map for the 1.2 release of Yocto Project is as below. To view the Yocto schedule-at-a-glance, go to YoctoCalendar

M1 (Oct. 31 to Dec. 16, 2011 -- 7 weeks: planning done in week 1, development week 1-4, stablization week 5-6, release week 7)

M1 Feature Development (Oct. 31 to Nov. 23, 2011)

Featuer # Summary Target Milestone Pirority/Estimate/Status Owner
1567 [1] QA Tests: Add recipe for LSB Tests and automate test 1.2 M1 [P2][5D] yi.zhao@windriver.com
1674 [2] run gtk+ over directfb 1.2 M1 [P2][D10] Xiaofeng.yan@windriver.com
1661 [3] meta-intel: streamline and clean up kernel config options and machine conf files 1.2 M1 [P2][5D] tom.zanussi@intel.com
1630 [4] Provide a click through license mechanism 1.2 M1 [P2][10D] New Owner? song.liu@intel.com
1589 [5] Disk space monitoring 1.2 M1 [P3][D10] liezhi.yang@windriver.com
1568 [6] QA Tests: Add recipe for ltp/posix tests and automate test 1.2 M1 [P2][3D] jiajun.xu@intel.com
1580 [7] Add Valgrind support in remote tools 1.2 M1 [P2][d5] jessica.zhang@intel.com
1461 [8] Put a uname and ab name in stdio 1.2 M1 [P3][D0] elizabeth.flanagan@intel.com
1629 [9] Buildstats memory measurements 1.2 M1 [P2][D3] elizabeth.flanagan@intel.com
1635 [10] Drop Grub for Syslinux 1.2 M1 [P2][5D] dvhart@linux.intel.com
1636 [11] Upgrade to EFI 1.2 M1 [P2][5D] dvhart@linux.intel.com
1634 [12] BSP update/intro 1.2 M1 [P2][5D] bruce.ashfield@windriver.com
1644 [13] Use cases 1.2 M1 [P1][2D] bruce.ashfield@windriver.com


Stabilize schedule

Release Candidate and Milestone Release schedule (Full Pass QA test follows every RC build)

  • RC1: 11/23/11
  • RC2: 11/30/11
  • RC3: 12/07/11
  • Release readiness meeting: 12/15/2011
  • M1 release: 12/16/11