Yocto Project 1.1

Release Criteria Milestone 1 Target Milestone 1 Status
Functional Completion All M1 features and BSPs are in the build. Schedule-status.PNG
see https://wiki.yoctoproject.org/wiki/Yocto_1.1_Schedule for status
Build and Release (Yocto) All M1 features can be built with no errors. Build is still failing. Beth/Saul will discuss off-line.
Build and Release (BSPs) Core and meta-intel BSPs can be built with no errors. Build is still failing. Beth/Saul will discuss off-line.
Open Bugs All bugs have been dispositioned. High issues have been fixed. NEW bugs
HIGH priority bugs
Functional Tests 100% of planned tests are executed and results are logged in bugzilla. Not done b/c no builds
BSP Testing 100% of planned tests are executed and results are logged in bugzilla. Not done b/c no builds
Documentation M1 documentation deliverables are complete. Only deliverable is allowing documentation to be updated even after code freeze. On-track.
Build Performance Plan for improving performance is defined. See schedule for details.
Upstream Commits Have upstream status updated on 90% of patches (so that we can have a status update) Probably won't have 90%, but goal will be set shortly.
Marketing Deliverables Giveaway plans defined Julie, Jefro, Darren, Tracey are working on a giveaway plan.
Publication M1 release is announced