Yocto 1.1 Schedule

From Yocto Project
Jump to navigationJump to search

October 2011 (release date: October 6, 2011)


The detailed milestone map for the October 2011 release of Yocto is as below.

pre-M1 (March 14 to April 18 -- Feature List and Schedule Defined April 18)

  • Features Submitted to web - by April 1st
  • Features prioritized and added to schedule - by April 18th

M1 (Apr 18 to Jun 13 -- Design Complete Apr 25, Dev Complete May 23, Stabilize Complete Jun 6, Release Complete Jun 13)

Group Feature Name Description Priority Status Owner Source Comments / Bugzilla Links
Architecture OE Core Restructuring, renaming, rebranding 1 Review Richard Architect
1.0 Carryover multi-lib multi-lib support for 32-bit & 64-bit and capable of being installed at the same time 1 Review Richard 1.0 Carryover
Meta-Data OE Comparison Compare Yocto core set against integration work in OE and other distributions looking for bug fixes, (relevant) feature enhancements, and integration/policy hints. 1 Accept Mark Meta-data
BSPs Support for AVX as in kernel 2.6.30. - Already in 1.0 Any toolchain support needed? 1 Review Saul Jay
Misc User creation at post-install 1 Accept Mark Architect

M2 (May 30 to Jul 25 -- Design Complete Jun 6, Dev Complete Jul 4, Stabilize Complete Jul 18, Release Complete Jul 25)

Group Feature Name Description Priority Status Owner Source Comments / Bugzilla Links
1.0 Carryover Image Creator finish the Image Creator to add features pushed out from 1.0 1 Accept Joshua + Jessica 1.0 Carryover
Architecture Layer Tooling This includes the architectural work plus implementing the changes 1 Review Richard Architect
Meta-data Upstream our patches Placeholder for time for the team to upstream patches 1 Review Saul Meta-Data Team
Meta-data Error handling in bitbake add additional error handling to bitbake 1 Review Saul Architect
ADT Changes for Image Creator Eclipse changes pending Image Creator 1 Review Jessica ADT Team
BSP Tutorials Create tutorials and documentation on how to create a BSP 1 Accept Tom, Scott Team
Kernel Fast Boot Time 2 second boot time target 1 Accept Darren Team
Misc adding eglibc config control this goes with the package config options 1.5 Accept Mark Architect
Misc Directory Ownership 1.5 Accept Mark Architect a bit concerned this will take longer then expected

M3 (Jul 11 to Aug 15 -- Design Complete Jul 18, Dev Complete Jul 25, Stabilize Complete Aug 8, Release Complete Aug 15)

Group Feature Name Description Priority Status Owner Source Comments / Bugzilla Links
X X X 1 Review X X

M4 (Aug 15 to Oct 6 -- Stabilize Complete Aug 29, Release Complete Oct 3)

Group Feature Name Description Priority Status Owner Source Comments / Bugzilla Links
X X X 1 Review X X